Red Sea - TRSTP: Phase 1: Shura Island: Hotel Central 3

General Information
Owner Red Sea Global
Masterplan Project (Parent Profile) Red Sea – TRSTP: Phase 1: Shura Island – Tabuk
Location Tabuk Province, Saudi Arabia
Status --
Sector Construction, Hospitality, Hotel, Resort
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 71
Estimated Budget Value ---
Contract Value 40
Net Value $40m
Award Date July 2022
Completion Date December 2024
Last Updated On November 2023
ProjectId (Old, New) 356900, 356900


Red Sea Global is planning to undertake the development of a project named Hotel Central No. 3 on a built up area of 18,472 sqm as part of Shura Island (currently called as Shura/ Shaura) in Red Sea Tourism Project in Tabuk region, Saudi Arabia.

The project was earlier planned by The Red Sea Development Company (TRSDC), and in October 2022, Red Sea was merged with Amaala to form a new company name Red Sea Global to implement the project.

The US$50 million project includes the following:

1. Construction of a 150-room hotel

2. Construction of 12 suites

3. Construction of 15 villas

4. Construction of spa

5. Construction of a fitness centre

6. Construction of an altitude pool

7. Construction of a ballroom

8. Construction of access roads

9. Construction of associated facilities

Second Section

20 November 2023

The construction works are progressing on the project.

20 July 2023

The construction works are progressing on the project and it is expected to be completed by end of 2024.

20 March 2023

The construction works are progressing on the project. Abdul Mohsen Al Tamimi Partner Group has been appointed as the main contractor on the project.

22 March 2022

The Design works are ongoing on the project.

02 November 2021

Lissoni + Partners is working as the interior designer.