Saudi Aramco - COUR: Jafurah: Utilities & Interconnecting Facility (Package-2)
Saudi Aramco is undertaking the construction of the sulphur utilities and interconnecting facility as a part of the Commercialisation of Unconventional Resources Jafurah Gas Plant in Saudi Arabia.
The US$1,700 million project includes the following:
1. Construction of inlet and export facilities
2. Installation of interconnecting pipe racks
3. Construction of sulphur recovery unit (SRU)
4. Construction of sulphur loading and handling unit
5. Installation of flare system
6. Installation of MAC coordinator
7. Development of storage area
8. Installation of gas-insulated switchgear
9. Construction of central control rooms
10. Construction of associated buildings
11. Construction of associated facilities
Second Section
No Content
No Content
10 January 2024
Construction works are progressing and are expected to be completed by 2025.
11 September 2023
Construction works are progressing and are expected to be completed by 2025.
07 June 2023
Construction works are ongoing on the project.
09 May 2023
The construction works are ongoing and is expected to complete by 2025.
30 March 2023
Construction works are progressing as per schedule on the project.
29 December 2022
The construction work is ongoing and is expected to complete by 2025.
17 August 2022
Construction works are ongoing as per schedule. (Source: MEED)
25 July 2022
Worley is appointed both as a project management consultant and construction management consultant. (Source: MEED)
27 March 2022
Engineering works are progressing on the project.
13 February 2022
Detailed Engineering works have commenced on the project
29 November 2021
Hyundai Engineering & Construction has been appointed as the main contractor on the project.
14 November 2021
Hyundai Engineering & Construction has emerged as the lowest bidder on the project. (Source: MEED)
03 November 2021
The main contract tender is not yet awarded.
16 September 2021
The main contract bids are under evaluation.
19 July 2021
The following companies have submitted the main contract bids for the project: Hyundai Engineering & Construction, Saipem, and Samsung Engineering. Hyundai Engineering & Construction has emerged as the lowest bidder. (Source: MEED)
08 July 2021
The client has asked the contractors to resubmit the main contract bids and Samsung Engineering is likely to submit the bids.
19 May 2021
The client has revived the project and the contractors are seeking for bid validity extension till the end of September 2021.
12 August 2020
The project is expected to be awarded by December 2020 as the client has asked the contractor's for bid validity till the end of 2020.
09 April 2020
JV of Hyundai Engineering and Hyundai Engineering & Construction has been emerged as the preferred bidder and the contract expected to be awarded by December 2020.
29 January 2020
The bid evaluation is underway and Hyundai E&C has emerged as the lowest bidders.
30 September 2019
The bid submission has taken place and the following companies have submitted the bids: Hyundai E&C, Samsung Engineering and Saipem.
05 August 2019
ITB has been issued with the bid submission due on September 30, 2019. The following are the PQ shortlisted companies: L&T, JGC, Hyundai E&C, Samsung Engineering, Dragados, Saipem, Technip and GS E&C.
25 July 2019
PQ submission has taken place and the following companies have submitted the PQ documents: JGC Corporation, L&T Hydrocarbons, Tecnicas Reunidas, Saipem, McDermott International, Hyundai E&C, Samsung Engineering, Daragdos, Technip and GS E&C.
30 May 2019
The SOI has been issued and Wood Group is working as the FEED contractor for the project.