NAT - High Speed Rail Network: Ain Sokhna-Al Alamein High-Speed Railway(Phase 1)

General Information
Owner National Authority for Tunnels (NAT)
Masterplan Project (Parent Profile) NAT Egypt – High Speed Rail Network – Suez
Location Ain Sokhna, Suez Governorate, Egypt
Status --
Sector Transport, Infrastructure, Railway
Contract Type Design Build (DB)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 81
Estimated Budget Value ---
Contract Value 4500
Net Value $4500m
Award Date April 2021
Completion Date December 2024
Last Updated On March 2024
ProjectId (Old, New) 41157, 232293


National Authority for Tunnels (NAT) is undertaking a high-speed railway line from Ain Sukhna to Al-Alamein in Egypt.

The track extends from Ain Sukhna to Hadaik October, then branches in the south to Fayoum / Beni Suef to connect with the second line and branches in the north to Alexandria, El

Alamein and Marsa Matrouh, with a length of about 660 km.

The project is also know as "Green Line".

The initial phase will be used for freight transport and will link Ain Sokhna to Al-Alamein via the New Administrative Capital.

The US$7,800 million project includes the following:

1. Laying of 660km railway tracks

2. Construction of five main stations

3. Construction of six substations

4. Construction of workshop building

5. Construction of administrative centers

6. Construction of control centers

7. Construction of Nile bridge (494 meters)

8. Construction of overhead lines

9. Installation of signaling and safety systems

10. Construction of related infrastructure

Second Section

06 March 2024

Construction works are progressing on the project.

13 December 2023

The construction works on the Nile Bridge are progressing.

22 November 2023

Finishing works are progressing on workshop building and Cairo station.

18 September 2023

The construction works progressing on the project.

20 July 2023

The installation of railway track has been started from Muhammad Najib station to Al-Sukhna station which is 50 km.

15 June 2023

The construction works are progressing on the project and the line from Ain Sokhna to Marsa Matrouh expected to complete by 2024 Year end.

04 April 2023

Islamic Development Bank has approved projects US$403 million for the project.

24 February 2023

TSO, a subsidiary of French company NGE has appointed for laying of 330km of track line and installation of more than 100 turnouts between Ain Al Sokhna and Borg El Arab city in the project.

16 December 2022

Construction works are progressing on the project.

08 August 2022

The first line of the electric train is expected to be completed by November 2023.

25 July 2022

Construction works are progressing on the project.

19 May 2022

The German company, Vossloh has been appointed to supply rail fastening systems for the project.

19 April 2022

The construction works have commenced on the project.

01 November 2021

Mobilization works are ongoing on the project.

30 August 2021

The construction works are yet to commence on the project.

18 July 2021

Egypt cabinet approved the request of NAT to contract with a consortium of companies led by Siemens (Siemens, Orascom Construction, and Arab Contractors) to start implementing this project. The contract includes maintenance operations for a period of 15 years. Siemens will receive $3 billion, while Orascom and Arab Contractors would receive $5.2 billion.

17 January 2021

The client has signed the Memorandum of Understanding (MoU) with Orascom Construction, Siemens, and The Arab Contractors to build the project. The scope of work includes design, installation, and commission.

25 November 2020

The client also selected Arab Contractors, Orascom Construction, and Concord for Engineering & Contracting along with the consortium of Samcrete Engineers & Contractors, China Railway Construction Corp, Arab Organization for Industrialization, China Railway Engineering Corporation to develop the project. The final agreements are yet to be signed.

16 November 2020

The main contract bids are still under evaluation.

10 September 2020

The consortium of Samcrete Engineers & Contractors, China Railway Construction Corp, Arab Organization for Industrialization, China Railway Engineering Corporation companies are the lowest bidder among others and awaiting an official announcement on the main contract award.

28 January 2020

The main contract bids are under evaluation.

29 July 2019

Bid evaluation process is still ongoing.

13 March 2019

Two consortium Avic (China) / China Railway Group Engineering Corporation (China) / Siemens (Germany) / SNCF (France) / Orascom (local) / Arab Contractors (local) and China Civil Engineering Construction (CCEC) / China Railway 14th Bureau Group / China Railway Fifth Survey and Design Institute Group (CR5DI) (China)/Samcreet (local) have submitted bids for the main contract. (Source: MEED)

05 February 2019

MoT has extended the bid submission date for the main contract to March 10, 2019 (Source: MEED)

19 December 2018

MoT has extended the bids submission due date to January 31, 2019. (Source: MEED)

04 November 2018

MoT has extended the bids submission due date to December 17, 2018. (Source: MEED)

10 September 2018

MoT has extended the bids submission due date to October 31, 2018. (Source: MEED)

27 July 2018

MoT has invited prequalified consortiums to bid for the build, finance and operate contract with the bid submission due date as September 9, 2018. (Source: MEED)

06 June 2018

The main contract tender is expected to be issued by Q3 2018.

25 May 2018

MoT is working currently on the technical evaluation and the financial evaluation of this project

28 March 2018

Following is the list of pre-qualified companies: Ferrovie dello Stato Italiane/Ansaldo/Hitachi/Saipem JV, Vinci/Colas Rail/Alstom/Bouygues Travaux/SNCF JV, AVIC/CSCEC/Siemens/Deutsche Bahn/Orascom Construction/The Arab Contractors JV, China Power Construction Corporation/Elsewedy Electric/Imathia JV, China Gezhouba Group Corporation/CRCC/Samco Egypt JV, Imathia/Talgo/Indra/Inabensa JV, Hyundai E&C/Hyundai Rotem JV, CCEC/China Railway Shisiju Group Corporation/CD5DI JV, Eiffage/Hassan Allam Hold

14 March 2018

Systra & Aecom are appointed as the consultants on the project.

13 March 2018

A total of 20 companies have submitted the pre- qualification documents for the contract.

08 February 2018

The tender for consultancy services has been issued. Three companies have submitted their offers, the client will select the best offer on February 15, 2018.

27 November 2017

Among others four international conglomerates have been invited to bid for the project. The bidding process for the same is expected to take place between January 2018 to late February 2018. AVIC international and China Railway Group Limited (CREC) is one of the bidders on the project.

27 November 2017

The European Bank for Reconstruction and Development (EBRD) will be funding the project.

14 February 2017

NAT announced the plans to a high-speed railway line from Ain El Sokhna to El Alamein.