ADNOC Gas - ESTIDAMA: Habshan 7 New Gas Processing Train
ADNOC Gas Processing is planning to undertake the construction of a Habshan 7 new gas processing train project in Abu Dhabi, the UAE.
The gas processing plant having a capacity of 670 MMSCFD.
The project is a part of the Habshan gas processing complex
The US$1100 million project involves the following:
1. Construction of a new high-pressure pipeline
2. Construction of the separation and condensate stabiliser unit
3. Installation of acid gas removal unit
4. Installation of mercury removal unit
5. Construction of a deep NGL recovery unit
6. Installation of sales gas and residue gas compressor
7. Construction of NGL product storage and transfer pump
8. Installation of utility units
a. Installation of Instrument Air (IA) System
b. Installation of Nitrogen (N2) System
c. Installation of Potable Water (PW) System
d. Installation of Fire Water (FW) System
e. Installation of Steam Generation System
f. Installation of Demineralized (DM) Water System
9. Construction of the flare unit
10. Installation of flare gas recovery package
11. Construction of water treatment package
12. Construction of non-process buildings
13. Installation of power generation system
14. Construction of NGL pipeline
15. Construction of sales gas pipeline
Second Section
No Content
No Content
26 August 2025
The main contractor tender has been issued and the following companies biding are Petrofac, Tecnimont, Samsung, Sinopec, L&T, CPECC, Petrojet /ENPPI in a consortium.
12 August 2025
The main contractor tender has been issued with the submission in mid September of 2025. (Source: MEED)
17 June 2025
The expression of interest (EoI) was issued in March, and the contractors have submitted their interests on April 8, 2025, Wood Group has performed the study & initial engineering design on the project. (Source: MEED)