ADNOC Offshore - LTDP: Lower Zakum - Phase 1: Omairah Island Topside Facilities Package II

General Information
Owner ADNOC Offshore
Masterplan Project (Parent Profile) ADNOC Offshore – Long-Term Development Plan: Lower Zakum - Phase I – Emirate of Abu Dhabi
Location Dubai, Emirate of Dubai, UAE
Status --
Sector Oil, Downstream, Oil Refinery
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 3394
Net Value $3394m
Award Date January 2025
Completion Date December 2027
Last Updated On September 2025
ProjectId (Old, New) 466104, 466104


ADNOC Offshore is undertaking the development of the Omairah Island topside facilities at Das Island under the Phase 1 of Lower Zakum Long Term Development Plan in Abu Dhabi, the UAE.

The US$3,394 million project includes the following:

1. Construction of production separation unit

2. Construction of process facilities

3. Construction of gas compression unit

4. Construction of produced water treatment and disposal unit

5. Construction of vapour recovery units

6. Construction of water injection units

7. Construction of riser tower and flare towers

8. Construction of local equipment rooms

9. Construction of associated facilities

10. Installation of the power distribution facility

11. Installation of substations

12. Installation of various wellheads

Second Section

17 September 2025

The engineering works are ongoing and construction works are yet to commence on the project.

16 May 2025

The engineering works are ongoing on the project and construction works are expected to commence by the third quarter of 2025. (Source: MEED)

19 April 2025

The client has appointed KBR, Penspen and Engineers India Limited as the project management consultants (PMC). These three firms will provide engineering and other technical personnel to assist the main contractors in executing the project. (Source: MEED)

12 February 2025

Tecnicas Reunidas has been appointed as the main contractor for the development of the project. (Source: MEED)

02 January 2025

The main contractor is not yet awarded.

28 October 2024

The main contract commercial bids have been submitted.

18 September 2024

The main contract tender has been issued and the technical bids have been submitted. The following companies have submitted the technical bids: L&T, Petrofac, Mcdermott, Saipem, CPECC, Tecnicas Reunidas, Tecnimont, and Target Engineering.