ROSHN - National Guard Stadium

General Information
Owner ROSHN
Masterplan Project (Parent Profile)
Location Riyadh, Riyadh Province, Saudi Arabia
Status --
Sector Construction, Leisure, Sport Facility, Stadium
Contract Type Design Build (DB)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $315m
Award Date May 2025
Completion Date June 2032
Last Updated On February 2025
ProjectId (Old, New) 452166, 452166


ROSHN, owned by the Public Investment Fund (PIF) is planning to undertake the construction of an iconic stadium spanning over a site approximately 800,000m2 located adjacent to the National Guard facilities in the southwest of Riyadh, Saudi Arabia.

The stadium is one of the key venues for the FIFA World Cup 2034.

The US$315 million project includes the following:

1. Construction of a stadium (46,000 seats covering an area of over 450,000 square metres)

-Net capacity (40,000 Seats)

-Hospitality seats (4,670 nos.)

-Sky box seats (1,100 nos.)

-Media tribune seats (1,280 nos.)

-VVIP seats (100 nos.)

-VIP seats (800 nos.)

-Access seats (427 nos.)

2. Construction of 4 4 training football courts

3. Construction of administrative offices

4. Construction of parking facility

5. Construction of a training academy including offices

6. Construction of 2 hotels and other mixed-use requirement (F&B plus Retail)

7. Infrastructure works

8. Construction of associated facilities.

Second Section

23 February 2025

Al Yamama, and the following JVs amongst others have been invited to bid *Almabani, Tekfen Construction and China Harbour Engineering Company *FCC and Nesma & Partners *Al Bawani and Besix *China Railway Construction Corporation and Sapac *Elseif and Midmac Foster & partners are working as the client designers on the project. (Source: MEED)

03 February 2025

The bid submission date has been extended from February 10, 2025, to March 2025. (Source: MEED)

21 November 2024

The bid submission date has been extended from December 3, 2024 to February 10, 2025.

05 November 2024

Al Bawani amongst others have been invited to bid and the bid submission date is on December 3, 2024.

27 October 2024

The main contract PQ documents submission date has been extended from October 22, 2024 to November 5, 2024. (Source: MEED)

23 October 2024

The invitation for pre-qualification was issued and documents have been submitted on October 22, 2024. (Source: MEED)

31 July 2024

The project is unveiled and we are in the process of identifying the design consultant.