ADNOC Gas - Ruwais NGL Fractionation Train V
Adnoc Gas is planning to undertake the construction of Ruwais NGL Fractionation Train V in the UAE.
The US$1,000 million project includes the following:
1. Construction of NGL fractionation plant with a capacity of 22,000 t/d
2. Construction of downstream treatment units
3. Installation of sulfur recovery units
4. Laying of flares and interconnection pipelines with existing facilities
5. Construction of Two propane liquefied petroleum gas storage tanks and one paraffinic naphtha storage tank
6. Construction of central control building
7. Construction of outstations, substations, and plant amenities
8. Installation of electrical power connections.
Second Section
No Content
No Content
30 September 2025
The technical and commercial bids submission for FEED works has been extended to October 6 2025 and November 2025. (Source: MEED)
28 July 2025
The main contract tender is yet to be awarded.
22 May 2025
The main contract tender is yet to be awarded on the project.
26 March 2025
The contractors are planning to submit their feed proposals by September and client is expected to award the main EPC contract by November. (Source: MEED)
26 February 2025
The main contractor bids are under evaluation.
17 January 2025
The client has selected the following contractors to perform feed work as part of the design competition: JGC Corporation, Technip Energies, and Tecnimont. (Source: MEED)
12 December 2024
The main contract tender has been issued, and the technical and commercial bids are currently under evaluation. The following companies have submitted bids for the feed works: Technip Energies, Petrofac, GS Engineering and Construction, JGC International, Tecnimont, and Tecnicas Reunidas. (Source: MEED)
11 September 2024
The EOI has been submitted. The main contract tender is expected to be issued by the end of 2024. The following companies are participating in this project: NPCC, Technip Energies, Petrofac, Hyundai E&C, JGC International, Tecnimont, Saipem and Samsung Engineering.
19 March 2024
The client has issued an expression of interest (EoI) document with submission due on March 11, 2024. The main tender for the projectâs FEED-to-EPC competition is expected to be issued by the end of March 2024. The owner company, Adnoc, plans to select contractors for the FEED contest in May 2024. (Source: MEED)