Qatar Energy - CO2 Sequestration Complex

General Information
Owner Qatar Energy
Masterplan Project (Parent Profile)
Location Ras Laffan, Al Khor Municipality, Qatar
Status --
Sector Gas, Storage, Gas Tank
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 2500
Net Value $2500m
Award Date September 2025
Completion Date March 2028
Last Updated On September 2025
ProjectId (Old, New) 418562, 418562


QatarEnergy is undertaking the construction of a carbon dioxide sequestration project covering its liquefied natural gas (LNG) operations in Ras Laffan Industrial City, Qatar.

The planned facility will capture carbon dioxide (CO2) from seven LNG trains at QG North and three LNG trains at QG South.

Once completed, the sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy’s LNG production operations located in Ras Laffan Industrial City.

The US$2,500 million project includes the following:

QG North complex:

1. Installation of four new electric-driven compressors

2. Construction of new power substation for power import from Kahramaa 65MW

3. Construction of new ITR for DCS/ESD/F&G

4. Construction of tie-ins with utility units

5. Installation of dehydration package

6. Installation of pig launcher

QG South complex:

1. Installation of two new electric-driven compressors

2. Construction of integration with South injection system unit 85

3. Installation of solvent reformulation for South trains 1/23

4. Construction of new power substation for power import from Kahramaa 35MW

5. Construction of new SIH for DCS/ESD/F&G

6. Construction of tie-ins with utility units

7. Installation of dehydration package

8. Installation of chillers package

9. Installation of pig launcher

RLIC corridors:

1. Installation of common 22-inch export pipeline stretching 18 kilometres

2. Installation of power tie-in RLF3 with Kahramaa

3. Installation of electric cables

4. Installation of fiber optic cable

Lot W15

1. Installation of six injection wells by QatarEnergy LNG subsurface

2. Installation of six injection flowlines and metring skid

3. Installation of six wellhead control panels

4. Installation of power tie-in from Barzan

5. Construction of substation

6. Installation of pig receiver

7. Construction of access road and fencing

Second Section

25 September 2025

Samsung C&T has been appointed as the main contractor on the project.

28 August 2025

The main contract bids are currently under evaluation.

27 April 2025

Based on the initial evaluation of the main contract bids, Larsen & Toubro Energy Hydrocarbon is understood to have pulled ahead in the race for the project’s contract. (Source: MEED)

25 March 2025

The following companies have submitted the main contract bids are Chiyoda Corporation, Consolidated Contractors Company, Larsen & Toubro Energy Hydrocarbon, Samsung C&T and amongst others. (Source: MEED)

22 November 2024

The main contract tender has been issued with unknown bid submission at this moment.

10 May 2024

The FEED works on the project are still ongoing and expected to be completed by the fourth quarter of 2024.

30 January 2024

The FEED works are still ongoing on the project and are expected to be completed by 2024.

28 September 2023

Worley has been appointed as the front-end engineering and design (FEED) consultant and is expected to complete in 2024.