ADNOC Gas - ESTIDAMA: New Compressor Plant at Habshan Gas Compressor Plant Package 2
ADNOC Gas Processing is planning to undertake the development of a new compressor plant at KP-30 location of Habshan Gas Compressor Plant (HGCP) in Abu Dhabi, the UAE. The project includes three gas compressors of 400 MMcfd capacity each.
It is part of project is known as ESTIDAMA and is also known as EPC Package 2.
The sales gas pipeline network consists of four main clusters of facilities and manifolds located in Abu Dhabi: Thammama-C manifold, Maqta manifold facility, KM-42 station, and Taweelah gas compressor station (TGCS). The Sales Gas Pipeline Network Enhancement Project aims to construct a new Gas Compression Plant and accompanying gas pipelines to enhance and supply gas to current and future customers, including those in the northern emirates. It also aims to maintain an integrated pipeline network for gas self-sufficiency, debottleneck existing gas network constraints, and enable LNG growth in Fujairah.
The US$700 million project involves the following:
1. Development of a HGCP station (805 MMscfd - Phase 1 (Pkg 2)
2. Installation of variable frequency drive (VFD) motor-driven compressors (5 Nos.)
3. Construction of compressor trains
4. Construction of high-pressure gas discharge units
5. Laying of trunk lines
6. Installation of power transformers
7. Installation of FOC and other communication equipment
8. Installation of control system
Second Section
No Content
No Content
04 March 2025
Penta Global Engineering Company is working as the mechanical subcontractor, and Dome International as the electrical subcontractor for the project.
30 January 2025
The construction works are ongoing on the project and are expected to be completed by September 2026.
23 October 2024
Petrofac has appointed Douglas OHI as a civil subcontractor for the development of the project.
04 October 2024
Construction works are ongoing on the project and are expected to be completed by the end of 2025.
26 July 2024
Construction works are ongoing on the project and are expected to be completed by fourth quarter of 2025.
07 May 2024
Penta Global Engineering Company is working as the MEP Sub-Contractor for the project. The construction works are still ongoing on the project and are expected to be completed by the end of 2025.
15 April 2024
Dome Oilfield Engineering & Services LLC have been appointed for conducting the HSE studies on the project.
21 February 2024
Construction works are ongoing on the project and are expected to be completed by the end of 2025.
09 October 2023
Construction works are ongoing on the project.
03 July 2023
Petrofac has been appointed as the main contractor on the project with a contract value of US$700 million.
19 June 2023
The main contract is yet to be awarded.
16 May 2023
The main contract bids are under evaluation on the project.
29 March 2023
The following companies amongst others have submitted the commercial bids: Archirodon, Engineering for Petroleum & Process Industries (Enppi), Larsen and Toubro Energy Hydrocarbon, National Petroleum Construction Company and Petrofac. (Source: MEED)
27 March 2023
Archirodon amongst others have submitted the commercial bids.
20 March 2023
The commercial bid submission date has been extended till March 27, 2023.
14 March 2023
The following companies amongst others have submitted the technical bids on February 24, 2023: Archirodon, Engineering for Petroleum & Process Industries (Enppi), Larsen and Toubro Energy Hydrocarbon, National Petroleum Construction Company and Petrofac. The commercial bid submission is on March 20, 2023. (Source: MEED)
20 February 2023
The technical bid submission date has been extended till February 24, 2023.
10 February 2023
The technical bid submission date has been extended till February 17, 2023.
07 February 2023
The client has re-issued the tender with some changes in the scope of work and the technical bid submission is on February 10, 2023.
20 December 2022
The commercial bid submission date is not yet announced by the client.
09 November 2022
The commercial bid submission date is not yet announced by the client.
21 September 2022
The commercial bid submission date is not yet announced by the client.
29 August 2022
The following companies amongst others have submitted the technical bids: 1. Al-Asab General Transport & Contracting Establishment, 2. Al-Nasr Contracting Company, 3. Archirodon, 4. Arkad, 5 China Petroleum Engineering & Construction Company, 6. Dodsal Engineering & Construction, 7. ENPPI, 8. Galfar Engineering & Construction, 9. Kalpataru Power Transmission, 10. Larsen & Toubro Energy Hydrocarbon, 11. National Petroleum Construction Company, 12. Petrofac, 14. Petrojet and 14. Robt Stone Middle East. The project completion is expected by 2025. (Source: MEED)
18 August 2022
The technical bid submission date has been extended till August 24, 2022.
22 July 2022
The bid submission date has been extended till August 17, 2022. Al Nasr Contracting Company, Arkad Engineering & Construction Company and CAT Group amongst others are also planning to submit the bids. (Source: MEED)
21 July 2022
The main contract tender is issued and the submission date is on July 25, 2022. Archirodon, China Petroleum Engineering & Construction Corporation, Robt Stone, Galfar Engineering & Contracting, Petrojet, Enppi, Larsen&Toubro, NPCC, Dodsal, Petrofac, Al Asab Est, Tecton, Target Engineering and Kalpataru amongst others are planning to submit the bids.
06 June 2022
The main contract tender is yet to be issued.
13 April 2022
ITB is expected to be issued by May 2022 to Al Asab Est, Archirodon, Galfar Engineering, MMEC Mannesmann, CPECC, Adyard and Descon with any PQ shortlisting process.
21 February 2022
The PQ shortlist is not yet finalized and the main contract tender is yet to be issued.
14 February 2022
Amongst others, Al Asab Est, Archirodon, Galfar Engineering & Contracting MMEC Mannesmann, and China Petroleum Engineering & Construction Corporation have submitted EOI documents and the main contract tender is expected to be issued by the end of February 2022.
29 December 2021
The expression of interest (EOI) for the main contract has been issued and the EOI documents were submitted on December 20, 2021. (Source: MEED)
11 November 2021
FEED works are ongoing and expected to be complete by March 15, 2022.
21 September 2021
Feed works are underway and the main contract tender is expected to be issued by end of 2021. (Source: MEED)