Taziz, Fertiglobe, GS Energy, Mitsui - Taziz Chemicals Production: Industrial Chemicals Zone Phase I: Ruwais Blue Ammonia Plant 1
A joint venture of TAâZIZ, Fertiglobe, Mitsui & Co., and GS Energy Corporation is planning to undertake the construction of a blue ammonia plant at Ruwais in Abu Dhabi, UAE.
The plant will be built with a capacity of 1 million tonnes per annum at the new TAZIZ industrial ecosystem and chemicals hub
The US$1496 million project includes the following:
1. Construction of ammonia production plant
2. Construction of processing units
3. Construction of storage facilities
4. Construction of distribution units
5. Installation of hydrogen compressors
6. Installation of ammonia converter
7. Installation of air compressor
8. Installation of process heater systems
9. Construction of associated facilities
Second Section
No Content
No Content
05 March 2025
The construction works are ongoing on the project and are expected to be completed by the fourth quarter of 2027.
12 November 2024
The construction works are ongoing on the project and are expected to be completed by the fourth quarter of 2027.
13 August 2024
The project have reached the Final Investment Decision (FID) stage.
26 June 2024
Mitsui has signed a loan agreement with the Japan Bank for International Cooperation (âJBICâ) to finance the development of the project and the construction works have commenced and are expected to be completed by 2027.
30 May 2024
The construction works are expected to be commenced by the third quarter of 2024 and are expected to be completed by 2027.
03 November 2023
Construction works are yet to commence.
11 October 2023
Construction works are yet to commence.
28 September 2023
Construction works are yet to commence on the project.
30 May 2023
The construction works are yet to commence.
05 March 2023
KBR has been awarded a contract to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant. (Source: MEED)
14 February 2023
The EPC contract has been awarded to Tecnimont. (Source: MEED)
19 January 2023
The client falls short of a final investment decision to develop the planned project. (Source: MEED)
11 December 2022
The final investment decision (FID) will be done by early 2023.
08 November 2022
The client is focused on progressing of the project at the TAâZIZ Industrial Chemicals Zone.
02 August 2022
FEED works are still ongoing on the project.
18 November 2021
Mitsui and GS Energy have signed an agreement for the development of the project.
24 October 2021
The main FEED Contractor is yet to be appointed.
05 July 2021
Fertiglobe has signed an agreement with Taziz for the development of the project. (Source: MEED)
27 May 2021
Wood Group has been appointed to undertake the initial Front-End Engineering and Design (pre-Feed) works for the project. The final investment decision is expected in 2022, and the overall project is expected to be completed by 2025.