ENOWA - NEOM City: Renewable Energy Programme 55,000MW
ENOWA, Energy and Water Subsidiary of NEOM is undertaking the construction of a renewable energy system at NEOM City in Tabuk, Saudi Arabia.
The project aims to deliver up to 55 gigawatts of installed renewable generation capacity mainly solar photovoltaic and wind along with energy transmission, storage, and green-fuel production to power NEOM city entirely by clean energy. Key components include wind farms, large-scale solar farms, grid infrastructure (including high-voltage transmission lines and smart grid systems), battery and possibly pumped hydro storage, and green hydrogen/ammonia facilities. The intended purpose is to meet NEOMâs massive energy demand, facilitate zero-carbon or net-zero operations in industry, transport, water desalination, and urban areas, while enabling exports of green fuels.
This project is a part of the Neom's renewable energy independent power producer (IPP) project.
The US$55,000 million project includes the following:
1. Construction of a solar and wind power plant 3,000MW
2. Construction of a substation
3. Construction of solar panel bases
4. Installation of solar panels
5. Installation of transformers
6. Installation of control systems
7. Installation of a solar tracking system
8. Installation of solar panels
9. Installation of a generator
10. Laying of transmission line
11. Construction of associated facilities
Second Section
No Content
No Content
08 January 2026
The main contract tender is yet to be issued on Airport West and Sharifa solar power plant project.
29 December 2025
Sharifa Solar Power Plant 1500 MW: It is understood that the main contract tender is yet to be issued.
29 July 2025
Renewable Energy Programme Phase 1: Solar & Wind Power Plant 3,000MW: It is understood that the client is looking forward for the further development of the project
18 February 2025
Renewable Energy Programme Phase 1: Solar & Wind Power Plant 3,000MW: The main contract tender is expected to be issued in Q3, 2025. (Source: MEED)
19 December 2024
Airport West Solar Power Plant 1500MW; Hasma Solar Power Plant 1500 MW:Renewable Energy Programme Phase 1: Solar & Wind Power Plant 3000MW: The main contract tender is yet to be issued.
01 November 2024
Renewable Energy Programme Phase 1: Solar Power Plant 3,000MW:The advisory works are progressing on the project and the main contract tender is expected to be issued by the end of the year 2024. SMBC Advisory Services is appointed as the financial adviser and Boston Consulting Group as strategy adviser. (Source: MEED)