ADNOC Offshore - LTDP: Lower Zakum - Phase 1: Omairah Island Topside Facilities Package II
ADNOC Offshore is undertaking the development of the Omairah Island topside facilities at Das Island under Phase 1 of the Lower Zakum Long Term Development Plan in Abu Dhabi, the UAE.
This project is part of the Lower Zakum Long-Term Development Phase 1 (LTDP-1) and aims to deliver the Al-Omairah Island Topside Facilities Package II. It is designed to support production of 520,000 barrels of oil per day through 2040. Key systems include export gas compression trains, gas dehydration units, offshore flare structures, a riser platform, and drill pad areas. The facility will collect, treat and compress production gas, reduce moisture content, and safely burn off excess gases. Its aim is to enhance overall output, improve efficiency, reduce emissions, and support ADNOCâs long-term production objectives in Lower Zakum.
The US$3394 million project includes the following:
1. Construction of the production separation unit
2. Construction of process facilities
3. Construction of gas compression unit
4. Construction of the produced water treatment and disposal unit
5. Construction of vapour recovery units
6. Construction of water injection units
7. Construction of riser tower and flare towers
8. Construction of local equipment rooms
9. Construction of associated facilities
10. Installation of the power distribution facility
11. Installation of substations
12. Installation of various wellheads
Second Section
No Content
No Content
28 September 2026
ASTRA Engineering & Construction LLC has been working as the sub-contractor on the project and construction works are progressing .
02 July 2026
Preliminary construction activities are ongoing for the project.
10 June 2026
Middle East Specialised Cables Company has been appointed as the cable supply contractor with a contract value of US$46.6 million for the development of the project. (Source: MEED)
18 February 2026
The construction works have been commenced on the project.
08 December 2025
The construction works are expected to commence soon on the project.
17 September 2025
The engineering works are ongoing and construction works are yet to commence on the project.
16 May 2025
The engineering works are ongoing on the project and construction works are expected to commence by the third quarter of 2025. (Source: MEED)
19 April 2025
The client has appointed KBR, Penspen and Engineers India Limited as the project management consultants (PMC). These three firms will provide engineering and other technical personnel to assist the main contractors in executing the project. (Source: MEED)
12 February 2025
Tecnicas Reunidas has been appointed as the main contractor for the development of the project. (Source: MEED)
02 January 2025
The main contractor is not yet awarded.
28 October 2024
The main contract commercial bids have been submitted.
18 September 2024
The main contract tender has been issued and the technical bids have been submitted. The following companies have submitted the technical bids: L&T, Petrofac, Mcdermott, Saipem, CPECC, Tecnicas Reunidas, Tecnimont, and Target Engineering.