SPPC - Gas Fired Power Plant 3600MW : Al-Nairiyah 1,800 MW IPP II
Saudi Power Procurement Company is undertaking the construction of Al Nairyah IPP 2 1,800 MW Gas Fired Power Plant in Al-Nairiyah, Jubail, Saudi Arabia.
The US$2000 million project includes the following:
1. Construction of 1800 MW power plant
2. Construction of a powerhouse
3. Construction of access roads
4. Installation of gas turbines
5. Installation of heat recovery steam generators
6. Installation of gas-insulated switchgear (GIS) substation
7. Installation of control system
8. Installation of transformers
9. Installation of the air-compression system
10.Construction of related facilities
Second Section
No Content
No Content
20 November 2024
Harbin Electric and China Railway Fourth Bureau First Engineering has been appointed as the main contractor. (Source: MEED)
08 November 2024
The consortium of Abu Dhabi National Energy Company, Jera and Al Bawani has been appointed as developer and Siemens has been appointed as gas turbine supply contractor. (Source: MEED)
22 October 2024
The main contract bids are under evaluation and it is expected to be awarded in few weeks. (Source: MEED)
23 August 2024
The following companies have submitted the bids: JV of Abu Dhabi National Energy Company and Jera, JV of Acwa Power, Korea Electric Power Corporation and Saudi Electricity Company. (Source: MEED)
01 August 2024
The main contract bid submission has been further extended to August 15, 2024. (Source: MEED)
01 July 2024
The main contract bid submission deadline has been extended from June 30, 2024 to July 31, 2024. (Source: MEED)
09 June 2024
The final consortiums of bidders are being formed to submit the bids, which are due on June 30, 2024. The consortiums are likely to bid include: 1. Abu Dhabi National Energy Company/Jera/Albawani, 2. Acwa Power, 3. Korea Electric Power Corporation/Saudi Electricity Company. (Source: MEED)
18 March 2024
Three consortiums are planning to submit bids for the project and we are in the process of identifying companies. (Source: MEED)
09 March 2024
The prequalified bidders have been invited to attend the job explanation meeting and to visit the site. (Source: MEED)
02 February 2024
The following companies are the prequalified developers: Abu Dhabi National Energy Company, Kahrabel /Engie, Electricite de France, General Electric Company, International Company for Water & Power Projects, Jera, Korea Electric Power Corporation, Marubeni Corporation, Nebras Power, The Kansai Electric Power Company, Saudi Electricity Company, Power & Water Utility Company for Jubail & Yanbu, Samsung C&T Corporation, Sumitomo, NTPC, China Power International Holding/ Ajlan Brothers, Al Jomaih Energy & Water Company/ Edra Power Holdings and Sojitz Corporation and the request for proposals has been issued and are expected to be submitted by June 30, 2024 (Source: MEED)
08 January 2024
Request for qualifications is expected to be issued in February 2024. (Source: MEED)