ADNOC - Aviation Fuel Tank Farm

General Information
Owner Abu Dhabi National Oil Company
Masterplan Project (Parent Profile)
Location Abu Dhabi, Emirate of Abu Dhabi, UAE
Status --
Sector Oil, Storage, Oil Tank
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 7
Estimated Budget Value ---
Contract Value 400
Net Value $400m
Award Date July 2024
Completion Date May 2027
Last Updated On August 2024
ProjectId (Old, New) 418208, 418208


Abu Dhabi National Oil Company (Adnoc) is planning to undertake the construction of an aviation fuel tank farm in the UAE.

The project's objective is to build underground tank farms at two sites in the vicinity of Abu Dhabi International Airport which will have a total capacity to store 192 million liters of jet A1 fuel.

Each tank farm will have a gross storage capacity of 96 million tonnes, with a pumping-out capacity of 5 million litres an hour.

The US$400 million project includes the following:

1. Construction of 16 underground storage tanks, measuring 30m in diameter and 8.8m in height, surrounded by a secondary concrete dyke offset by 3m from the tank shell

2. Construction of 22 delivery pumps, each with a capacity of 240,000 liters per hour

3. Construction of two delivery pumps, each with a capacity of 150,000 per hour

4. Construction of two metering skids at the discharge header before connecting to the existing hydrant header at two different locations

5. Construction of a closed drain system consisting of closed drain vessels, closed drain transfer pumps, product recovery tanks, product recovery tank transfer pumps, filter water separators, and sampling pumps

6. Construction of an open drain system consisting of open drain vessels, open drain transfer pumps, and oily water separator packages

7. Construction of a substation building including switchgear, and transformers

8. Installation of an air/instrument air system and potable/utility water systems

9. Installation of a vent pipe

10. Installation of a fire and gas detection and alarm system

11. Installation of a process control system

12. Installation of a safety instrumented system

13. Installation of an emergency shutdown system

14. Installation of a fire protection system, including a foam storage system, and a spray system

Second Section

27 August 2024

The construction works are yet to commence.

11 July 2024

The consortium of Trojan Construction Group and Cylingas has been appointed as the engineering, procurement and construction (EPC) contract with a value of US$400 million for the project. (Source: MEED)

14 June 2024

The client has selected a consortium of Trojan Construction Group and Cylingas for the main engineering, procurement and construction (EPC) contract for the project. The official award is yet to be announced. (Source: MEED)

06 March 2024

The main contract bids have been submitted on March 1, 2024. The client has received revised commercial prices from contractors for the engineering, procurement and construction (EPC) works on the project. (Source: MEED)

28 February 2024

The main contract bids are under evaluation.

28 December 2023

The main contract bids are under evaluation.

10 November 2023

The commercial bid submission has been extended till November 13, 2023. (Source: MEED)

01 November 2023

The commercial bid submission is due on November 6, 2023. (Source: MEED)

25 October 2023

The following companies have submitted the bids: Petrojet, China Petroleum Engineering & Construction Corporation, Adyard, Al Asab Contracting Establishment, Target Engineering, Cylingas and Enppi.

05 October 2023

The technical bids are submitted on the project. (Source: MEED)

25 September 2023

The following companies have been pre-qualified to bid for the project: Al Asab Contracting Establishment, Adyard Gmbh, Butec, Cylingas, Dhafir Development and Contracting, Enppi, Integrated Specialized Gen Cont. Co. Wll, Litwin, Petrojet, Vijay Tanks & Vessels Ltd, Kalpataru, Galfar, China Petroleum Engineering & Construction Corp and Al Yaseah Engineering.

20 September 2023

The main contract tender was issued with technical bid submission due on September 28, 2023. Penspen is working as a front-end engineering consultant. (Source: MEED)