TotalEnergies/QatarEnergy/National Oil Company/BOC - Gas Growth Integrated Project (GGIP)
Iraq Government along with TotalEnergies (45%), QatarEnergy (25%), Iraqâs National oil company, and the Basrah Oil Company (30%) is undertaking the construction of the Gas Growth Integrated Project (GGIP) in southern Iraq.
The Project is divided into four different stages. It includes CSSP, AGUP, GMP, and 1GW Solar Energy Project.
The US$27000 million project includes the following:
Common Seawater Supply Project (CSSP):
1. Construction of de-oxygenation tower and boosting pumps
2. Construction of a water disposal unit
3. Construction of a water handling and injection system
4. Construction of eight interconnecting stations and 10 delivery stations
5. Installation of high-flow water injection pumps
6. Installation of sand filters
7. Laying of 426km pipeline
8. Drilling of injection well & separation challenges
9. Installation of process monitoring and control systems
10. Construction of seawater treatment plant (1192404m3/day)
11. Construction of seawater intake facility
12. Construction of a power plant (430MW)
13. Construction of pumping stations
14. Construction of pre & post-treatment facilities
15. Construction of chemical units
16. Installation of dual media filter
17. Installation of the polishing filter
18. Installation of the safety filter
19. Construction of accommodations and administration buildings
20. Construction of potable water & sewage treatment systems
21. Construction of public amenities
Associated Gas Upstream Project:
1. Upgrade of existing gas flare tips with new tips
2. Upgrade of the existing steam system
3. Installation of new steam pipeline
4. Construction of an acid gases injection well
5. Construction of a wastewater injection well
6. Construction of a building of separation, stabilizing and sweetening facilities of gas condensates
7. Construction of a storage tank for gas condensates
8. Associated facilities.
Artawi Oil Field Development (Central Gas Complex in Artawi)/ GMP:
1. Construction of gas complex
2. Installation of gas gathering unit
3. Construction of gas processing units
4. Installation of the compressor unit
5. Installation of the separation unit
6. Associated facilities
Artawi 1000 MW Solar PV Plant:
1. Construction of a substation
2. Installation of 132 kV booster station
3. Installation of solar panels
4. Installation of transformers
5. Laying of transmission lines
6. Construction of related infrastructure
Second Section
No Content
No Content
08 October 2024
Artawi Oil Field Development: Central Gas Complex: The main contract bids has been submitted & the bids are under evaluation.
26 September 2024
Artawi Oil Field Development (Central Gas Complex in Artawi): KBR has completed the front-end engineering and design (feed) work for the project. The tendering process is ongoing and several international contractors are interested in ultimately submitting the bids for the project. Artawi 1000 MW Solar PV Plant: China Energy Engineering International Group has been awarded the main contract. Common Seawater Supply Project (CSSP): Total Energies and Hyundai E&C are in discussion regarding Hyundai's potential involvement in a $2.45 billion water treatment plant package within the project.
13 June 2024
For the Associated Gas Upstream Project: Phase 1 package: The front-end engineering design (FEED), detailed design, procurement support, and construction and commissioning assistance contract worth US$46 million has been awarded to the Wood Group.
22 January 2024
TotalEnergies has signed a contract with Vallourec to supply casing and tubing equipment for the development of first phase of the Project. (Source: MEED)
14 July 2023
TotalEnergies signed a $10bn deal for the project with the aim of increasing oil production and energy capacity.