TotalEnergies/QatarEnergy/National Oil Company/Basra Oil - Gas Growth Integrated Project (GGIP)

General Information
Owner TotalEnergies
Masterplan Project (Parent Profile)
Location Baghdad, Baghdad Province, Iraq
Status --
Sector Gas, Transmission, Gas Pipeline
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 8
Estimated Budget Value ---
Contract Value 0
Net Value $19096m
Award Date August 2024
Completion Date December 2028
Last Updated On April 2025
ProjectId (Old, New) 413232, 413232


Iraq Government along with TotalEnergies (45%), QatarEnergy (25%), and the Basrah Oil Company (30%) is undertaking the construction of the Gas Growth Integrated Project (GGIP) in southern Iraq.

The Project is divided into four different stages. It includes CSSP, AGUP, GMP, and 1GW Solar Energy Project.

The US$27000 million project includes the following:

Common Seawater Supply Project (CSSP):

1. Construction of de-oxygenation tower and boosting pumps

2. Construction of a water disposal unit

3. Construction of a water handling and injection system

4. Construction of eight interconnecting stations and 10 delivery stations

5. Installation of high-flow water injection pumps

6. Installation of sand filters

7. Laying of 426km pipeline

8. Drilling of injection well & separation challenges

9. Installation of process monitoring and control systems

10. Construction of seawater treatment plant (1192404m3/day)

11. Construction of seawater intake facility

12. Construction of a power plant (430MW)

13. Construction of pumping stations

14. Construction of pre & post-treatment facilities

15. Construction of chemical units

16. Installation of dual media filter

17. Installation of the polishing filter

18. Installation of the safety filter

19. Construction of accommodations and administration buildings

20. Construction of potable water & sewage treatment systems

21. Construction of public amenities

Associated Gas Upstream Project:

1. Upgrade of existing gas flare tips with new tips

2. Upgrade of the existing steam system

3. Installation of new steam pipeline

4. Construction of an acid gases injection well

5. Construction of a wastewater injection well

6. Construction of a building of separation, stabilizing and sweetening facilities of gas condensates

7. Construction of a storage tank for gas condensates

8. Associated facilities.

Artawi Oil Field Development (Central Gas Complex in Artawi)/ GMP:

1. Construction of gas complex

2. Installation of gas gathering unit

3. Construction of gas processing units

4. Installation of the compressor unit

5. Installation of the separation unit

6. Associated facilities

Artawi 1000 MW Solar PV Plant:

1. Construction of a substation

2. Installation of 132 kV booster station

3. Installation of solar panels

4. Installation of transformers

5. Laying of transmission lines

6. Construction of related infrastructure

Second Section

24 April 2025

GGIP: Associated Gas Upstream Project: Wood Group has been awarded engineering and procurement framework agreements worth $11 million for the development of the project.

13 March 2025

GGIP: Artawi 1000 MW Solar PV Plant: The construction works are commenced.

27 October 2024

Artawi 1000 MW Solar PV Plant: Construction work is expected to commence soon, with the project scheduled for completion by early 2027. GGIP: Associated Gas Upstream Project: FEED works are completed. The main contract tender has been issued and the technical bids have been submitted in September 2024. China Petroleum Engineering & Construction Corporation and a few other unknown contracting companies have submitted the technical bids, The commercial bid submission is yet to be announced by the owner company, Total Energies. (Source: MEED)

08 October 2024

Artawi Oil Field Development: Central Gas Complex: The main contract bids has been submitted & the bids are under evaluation.

26 September 2024

Artawi Oil Field Development (Central Gas Complex in Artawi): KBR has completed the front-end engineering and design (feed) work for the project. The tendering process is ongoing and several international contractors are interested in ultimately submitting the bids for the project. Artawi 1000 MW Solar PV Plant: China Energy Engineering International Group has been awarded the main contract. Common Seawater Supply Project (CSSP): Total Energies and Hyundai E&C are in discussion regarding Hyundai's potential involvement in a $2.45 billion water treatment plant package within the project.

13 June 2024

For the Associated Gas Upstream Project: Phase 1 package: The front-end engineering design (FEED), detailed design, procurement support, and construction and commissioning assistance contract worth US$46 million has been awarded to the Wood Group.

22 January 2024

TotalEnergies has signed a contract with Vallourec to supply casing and tubing equipment for the development of first phase of the Project. (Source: MEED)

14 July 2023

TotalEnergies signed a $10bn deal for the project with the aim of increasing oil production and energy capacity.