Expo City Dubai - Expo Central: Mangrove Residences (Plot No. 521-0754)

General Information
Owner Expo City Dubai
Masterplan Project (Parent Profile) Expo City Dubai – Expo Central – Dubai
Location Dubai, Emirate of Dubai, UAE
Status --
Sector Construction, Residential, Apartments
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 40
Estimated Budget Value ---
Contract Value 160
Net Value $160m
Award Date March 2024
Completion Date January 2026
Last Updated On October 2024
ProjectId (Old, New) 403289, 403289


Expo City Dubai is undertaking the Mangrove Residences project in Madinat Al Mataar at Dubai, the UAE.

Plot no.: 521-075.,

Building permit no.: 393610

The US$160 million project includes the following:

1. Construction of three 3 residential towers:

a. Block (A) 150 Residential units (G+16F+R)

b. Block (B) 155 Residential units (G+16F+R)

c. Block (C) 145 Residential units (G+16F+R)

2. Construction of 450 luxury apartment units (comprising of one-, two-, three- bedroom apartments)

3. Construction of 20 commercial units.

3. Construction of a meeting hall

4. Construction of parking facilities

5. Construction of associated facilities

Second Section

25 October 2024

The construction works are progressing on the project.

15 July 2024

As per the site visit on July 3, 2024, sub-structural works are ongoing and Jacobs and MACE are replaced by Buro Kling Architectural Engineering Consultants as the PMC.

18 June 2024

Proscape has been appointed to carry out infrastructure and clearance works. The groundworks have been completed, with more than 150,000 m3 of earth excavated to prepare for the construction of the foundation, ground slab, and basement car park.

02 April 2024

Menasco Mechanical Contracting has been appointed as the MEP subcontractor and construction works have commenced

14 March 2024

Shapoorji Pallonji has been awarded the main contract.

16 February 2024

The main contract is yet to be awarded.

12 December 2023

Amongst others, iBuild Construction (Innovo) has also submitted bids for the project.

05 December 2023

Shapoorji Pallonji, amongst others has submitted the main contract bids for the project.

15 November 2023

The main contract tender has been issued and the bid submission deadline is on November 23, 2023. Shapoorji Pallonji, amongst others is likely to submit a bid for the project.

09 October 2023

As per the site visit on October 6, 2023, a joint venture of Jacobs and Mace is working as the project management consultant and Zutari is working as the engineer consultant and architect of record on the project.

13 July 2023

International Foundation Group is working as the enabling works contractor.

30 June 2023

Design works are ongoing and are expected to be completed by Q4 2023.

15 March 2023

DP Architects Pte Ltd is working as the architect consultant. Site preparatory works are ongoing and the project is scheduled to be complete by January 2026. The main contract tender is expected to be issued by August 2023.