Expo City Dubai - Expo Central: Mangrove Residences (Plot No. 521-0754)
Expo City Dubai is undertaking the Mangrove Residences project in Madinat Al Mataar at Dubai, the UAE.
Plot no.: 521-075.,
Building permit no.: 393610
The US$160 million project includes the following:
1. Construction of three 3 residential towers:
a. Block (A) 150 Residential units (G+16F+R)
b. Block (B) 155 Residential units (G+16F+R)
c. Block (C) 145 Residential units (G+16F+R)
2. Construction of 450 luxury apartment units (comprising of one-, two-, three- bedroom apartments)
3. Construction of 20 commercial units.
3. Construction of a meeting hall
4. Construction of parking facilities
5. Construction of associated facilities
Second Section
No Content
No Content
25 October 2024
The construction works are progressing on the project.
15 July 2024
As per the site visit on July 3, 2024, sub-structural works are ongoing and Jacobs and MACE are replaced by Buro Kling Architectural Engineering Consultants as the PMC.
18 June 2024
Proscape has been appointed to carry out infrastructure and clearance works. The groundworks have been completed, with more than 150,000 m3 of earth excavated to prepare for the construction of the foundation, ground slab, and basement car park.
02 April 2024
Menasco Mechanical Contracting has been appointed as the MEP subcontractor and construction works have commenced
14 March 2024
Shapoorji Pallonji has been awarded the main contract.
16 February 2024
The main contract is yet to be awarded.
12 December 2023
Amongst others, iBuild Construction (Innovo) has also submitted bids for the project.
05 December 2023
Shapoorji Pallonji, amongst others has submitted the main contract bids for the project.
15 November 2023
The main contract tender has been issued and the bid submission deadline is on November 23, 2023. Shapoorji Pallonji, amongst others is likely to submit a bid for the project.
09 October 2023
As per the site visit on October 6, 2023, a joint venture of Jacobs and Mace is working as the project management consultant and Zutari is working as the engineer consultant and architect of record on the project.
13 July 2023
International Foundation Group is working as the enabling works contractor.
30 June 2023
Design works are ongoing and are expected to be completed by Q4 2023.
15 March 2023
DP Architects Pte Ltd is working as the architect consultant. Site preparatory works are ongoing and the project is scheduled to be complete by January 2026. The main contract tender is expected to be issued by August 2023.