KOC - South Kuwait Excavation, Transportation, and Remediation SKETR-2: Zone C
Kuwait Oil Company (KOC) is undertaking the South Kuwait Excavation, Transportation, and Remediation Project SKETR-2 works in South Kuwait, Kuwait.
Tender No. RFP-2076069
The current profile included Zone C.
The US$200 million project included the following:
1. Expansion of an existing landfill facility for hydrocarbon contaminated soil
2. Remediation & excavation works of all wet oil lakes (WOL), dry oil lakes (DOLs) and oil contaminated piles (OCPs), coastal deposits, wellhead pits, coastal trench, tartrate
3. Backfilling works
4. Development of treatment platform areas and facilities
5. Enabling works
a. Installation of fencing
b. Site offices/facilities
c. Establishment of water supply, storage, treatment, and power
d. Preparation of treatment areas
e. Lay-down areas
f. Material stockpiles/holding areas
g. Provision of new roads and gatch roads
6. Main works
a. Excavation of oil-contaminated soil
b. Mixing of the contaminated soil from piles and dry oil lakes with the liquid sludge in wet oil lakes to allow easier handling of wet oil lake contents
c. Soil treatment using bioremediation
d. Sampling and analysis to monitor treatment progress
e. Staging and disposal of other excavated materials
f. Recovery and handling of liquids from excavation
g. Treated soil placement
h. Site restoration
7. Construction of disposal facilities
8. Installation of weighbridge
9. Construction of storage facilities
10. Construction of the treatment pads
11. Groundwater works
12. Construction of temporary site facilities
Second Section
No Content
No Content
16 February 2024
Full scale remediation works are ongoing on the project. (Source: MEED)
07 September 2023
Mobilization works are ongoing on the project.
06 June 2023
The project is expected to be completed before the end of 2027. (Source: MEED)
16 May 2023
The main contractor is still awaiting for the kick-off meeting to take place and mobilization work is expected to commence by mid August 2023. (Source: MEED)
16 March 2023
The Pilot project has been completed. (Source: MEED)
10 March 2023
The contract was signed on March 07, 2023.
31 January 2023
Zaopin Hangzhou in partnership with the Contractor General Trading & Contracting Company has been awarded the main contract worth US$152 million. (Source: MEED)
30 November 2022
The main contract bids are under evaluation.
13 October 2022
The main contract bids are under evaluation.
29 August 2022
Contractor General Trading & Contracting Company has emerged as the lowest bidder (US$152.80 million) and Al-Sayer General Trading & Contracting Construction Company as the second lowest bidder (US$165.08 million). (Source: MEED)