SEWA - Hamriyah Seawater Reverse Osmosis IWP
Sharjah Electricity, Water and Gas Authority (SEWA) is undertaking the construction of a seawater reverse osmosis plant at Al Hamriyah, Sharjah, the UAE.
The SWRO plant will be the first independent water project (IWP) in Sharjah.
The project aims to meet the increasing demand for potable water in the region.
The plant will generate approximately 272,000 cm/d of desalinated water by the second quarter of 2027 and after the completion, the plant will generate 410,000 cm/d of desalinated water by the third quarter of 2028.
The US$682 million project includes the following:
1. Construction of a seawater reverse osmosis plant with a capacity to produce 90 MIGD (410,000 cm/d)
2. Construction of control rooms
3. Construction of storage tanks
4. Construction of seawater intake pumping station
5. Laying of pipelines
6. Construction of associated facilities
Second Section
No Content
No Content
18 September 2024
Veolia and its subsidiary Sidem has been appointed as the main contractor on the project. (Source: MEED)
05 September 2024
The water purchase agreement has been signed and ACWA Power has been appointed as the developer on the project while we are in the process of identifying the main contractor. Construction works are expected to be completed by the third quarter of 2028. (Source: MEED)
04 June 2024
We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.
19 January 2024
Acwa power has submitted the main contract bid for the project. (Source: MEED)
13 December 2023
The main contract bid submission deadline has been extended from November 27, 2023 to December 14, 2023. (Source: MEED)
19 October 2023
The main contract bid submission deadline has been extended from October 12, 2023 to November 27, 2023. (Source: MEED)
05 September 2023
The main contract bid submission has been further extended to October 12, 2023. (Source: MEED)
30 April 2023
The site visit has been completed and the representatives from the following companies participated in the site visit: ACCIONA. Acwa Power, Aljomaih Holding, Engie, GS Inima Environment, Marubeni Corporation. (Source: MEED)
04 April 2023
The main contract tender has been issued with bid submission due on August 1, 2023. (Source: MEED)
14 March 2023
The main contract tender is expected to be issued in May 2023. (Source: MEED)
22 February 2023
The following companies have been qualified to bid for the project: Acciona, Acwa Power, JV of Aljomaih Holding and Sogex Oman, cobra Group, Engie, GS Inima, Marubeni, and Metito. (Source: MEED)
12 January 2023
The RFQ has been issued in October 2022 and submitted in November 2022 and the bids are under evaluation.
12 October 2022
The client, Sharjah Electricity, Water & Gas Authority (Sewa) is expected to issue the request for qualifications (RFQ) by end of October or early November 2022.
17 August 2022
The main contract tender is yet to be issued.
20 July 2022
The request for proposal (RFP) is yet to be issued.
07 June 2022
The EOI documents have been submitted. The following companies amongst others have submitted the EOI: Al Nasr Contracting Company, Besix, Veolia, ACWA Power, Cobra Group, Metito and Hyundai.
18 May 2022
The client has issued an expression of interest (EoI) for the developers with a submission deadline of June 2, 2022.
08 February 2022
Sharjah Electricity, Water and Gas Authority (SEWA) has revealed the start of implementing a plan to develop the project and has signed a contract with a number of consultants and international houses of expertise.