Borouge - Borouge 4 Petrochemical Complex: Polymers Production Unit
Abu Dhabi Polymers Company (Borouge) is undertaking the construction of the Polymers Production package at Borouge 4 petrochemical complex in Abu Dhabi, the UAE.
The US$1350 million project includes the following:
1. Construction of Polymer production unit
2. Construction of two new polyethylene manufacturing plants
3. Construction of storage facilities
4. Construction of a laboratory
5. Construction of associated facilities
Second Section
No Content
No Content
11 March 2024
Construction works are ongoing on the project and are expected to be completed by 2025.
30 January 2024
Construction works are ongoing on the project and are expected to be completed by 2025.
21 December 2023
Construction works are ongoing on the project and are expected to be completed by 2025.
19 October 2023
Construction works are ongoing and are expected to be completed by 2025.
08 August 2023
Construction works are progressing and are expected to be completed by 2025.
09 May 2023
Construction works are progressing and are expected to be completed by 2025.
13 January 2023
Ducab and Union Pipes Industry have signed a contract worth US$15 million to produce energy and infrastructure applications to construct Borouge 4.
27 October 2022
The site preparatory works are ongoing on the project.
29 July 2022
The site preparatory works are underway on the project. (Source: MEED)
17 February 2022
Site preparatory works have commenced on the project.
06 December 2021
Maire Tecnimont has been appointed as the main contractor.
17 November 2021
Maire Tecnimont has emerged as the front runner and the main contract tender is yet to be awarded.
10 November 2021
The main contract bids are still under evaluation.
04 October 2021
The main contract bids are under evaluation.
07 September 2021
The commercial bid submission has taken place. Amongst others, L&T and Maire Tecnimont, has submitted bids for the project.
28 July 2021
The commercial bid submission has been extended to August 29, 2021. (Source: MEED)
04 July 2021
Technical bid submission took place. The commercial bid submission has been extended to August 18, 2021.
04 May 2021
Technical bid submission took place. L&T and Samsung amongst few others have submitted bids.
02 May 2021
The technical bid submission due on May 2, 2021 and the commercial bid submission due on July 29, 2021.
19 April 2021
The technical bid submission has been extended to April 27, 2021.
14 April 2021
The technical bid submission has been extended to April 18, 2021. (Source: MEED)
05 April 2021
ITB has been issued with the technical bid submission due on April 12, 2021. GS Engineering & Construction, Hyundai E&C, L&T, Maire Tecnimont and Samsung Engineering are likely to submit bids.