KPA - Shuaiba Port Administration Complex

General Information
Owner Kuwait Ports Authority (KPA)
Masterplan Project (Parent Profile)
Location Kuwait City, Al Asimah Governorate, Kuwait
Status --
Sector Construction, Public, Government Facility
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 42
Estimated Budget Value ---
Contract Value 42
Net Value $42m
Award Date January 2023
Completion Date December 2025
Last Updated On November 2023
ProjectId (Old, New) 342611, 342611


Kuwait Ports Authority (KPA) is undertaking the development of an administration complex in Shuaiba Port in Kuwait.

Tender No. KPA/12/2019/2020

The US$50 million project includes the following:

1. Construction of conference rooms

2. Construction of office space

3. Construction of parking facilities

4. Construction of a cafeteria

5. Installation of safety and security systems

6. Construction of other associated facilities

Second Section

01 November 2023

The official agreement is yet to be signed.

17 October 2023

The official agreement is yet to be signed

31 January 2023

United Building Company has been awarded the main contract worth US$42.31 million.

23 November 2022

The main contract is yet to be awarded. The warranties have been extended till December 19, 2022.

01 September 2022

The warranties have been extended till September 13, 2022.

28 June 2022

The main contract is yet to be awarded.

29 March 2022

Specialties Group Holding Company has submitted the bids for the waterproofing works and their sister company Construction Specialties has submitted the bids for the main contractor.

11 March 2022

The main contract bids are still under evaluation.

05 January 2022

The main contract bids are under evaluation.

18 November 2021

The following companies have submitted the main contract bids for the project: Privacy Construction Company for General Trading and Contracting LLC (US$ 39.5 million), United Buildings Company K LLC (US$ 42.7 million), Mohammed Abdul Mohsen Al-Kharafi & Sons Company for General Trading, General Contracting and Industrial Facilities LLC (US$ 44.6 million), First Group General Trading and Contracting Company LLC (US$ 45.7 million), Aldar Engineering and Construction Company KSCC (US$ 48.6 million), Construction and Real Estate Manufacturing Company K.S.C. (US$ 49 million), Kuwait Factory Building and Contracting Company K.S.C. (US$ 52.5 million), ), Syed Hamid Behbehani & Sons Company LLC (US$ 58 million), United Gulf Construction Company LLC (US$ 58.4 million), KCC Engineering and Contracting Company / Closed Joint Stock (US$ 64.2 million).

20 September 2021

The main contract bid submission deadline has been extended to October 19, 2021.

05 September 2021

The main contract bid submission deadline has been extended to September 19, 2021.

26 July 2021

The main contract bid submission deadline has been extended to September 05, 2021.

27 June 2021

The main contract bid submission deadline has been extended to August 03, 2021.

31 May 2021

The main contract bid submission deadline has been extended to July 04, 2021.

24 May 2021

The construction supervision consultant tender has been issued and the bid submission for the same is August 24, 2021.

27 April 2021

The main contract bid submission deadline has been extended to June 01, 2021.

11 April 2021

The main contract tender has been issued with a bid submission deadline of April 27, 2021.