Taziz - Taziz Chemicals Production: Industrial Chemicals Zone Phase I
Taziz, a joint venture of ADNOC and ADQ is planning to develop the derivative park in Ruwais, Abu Dhabi.
This project is one of the most important oil and gas projects in the MENA region
The US$10246 million project includes the following:
1. Construction of Chlor-alkali production plant with a capacity to produce 940 thousand tons per year
2. Construction of an ethylene dichloride production plant with a capacity to produce 1.1 million tons per year
3. Construction of polyvinyl chloride production plant with a capacity to produce 360 thousand tons per year
4. Construction of methanol production plant
5. Construction of ammonia production plant
6. Construction of isopropyl alcohol production plant
7. Construction of elastomers production plant
8. Construction of port facilities
9. Construction of two liquid berths of 640m
10. Construction of one dry bulk berth of 320m
11. Construction of 12-tank farm
12. Installation of pipelines
13. Construction of pumping stations (for feedstock and final products)
14. Installation of a feedstock supply system
15. Infrastructure works
16. Construction of associated facilities
Second Section
No Content
No Content
05 March 2025
Ruwais Blue Ammonia Plant: The construction works are ongoing on the project and are expected to be completed by the fourth quarter of 2027.
03 February 2025
Methanol Production Facility: Samsung E&A has been appointed as the Engineering Procurement & Construction Contractor with the value of US$1700 million.
03 December 2024
Methanol Production Facility: The main contractor is not yet awarded officially to Samsung E&A.
12 November 2024
Ruwais Blue Ammonia Plant: The construction works are ongoing on the project and are expected to be completed by the fourth quarter of 2027.
08 November 2024
Methanol Production Facility: Samsung E&A Company has emerged as the frontrunner for the project. Chemical Port at Ruwais Industrial City: NMDC Group has been appointed as the main contractor for the development of the project. (Source: MEED)
18 October 2024
Methanol Production Facility: The commercial bids have been submitted, and the following companies are bidding: Samsung E&A, Technip Energies, Larsen & Toubro Energy Hydrocarbons, and Petrojet.
08 September 2024
Petrochemical Derivative Complex: Methanol Production Facility: The commercial bid submission is due on September 16, 2024.
23 July 2024
Methanol Production Facility: The technical bids for engineering, procurement, and construction (EPC) works have been submitted on July 22, 2024.
04 July 2024
Project Landing: The bidders are now engaged in technical bid clarifications and further commercial negotiations with a client.
13 June 2024
Chlor-Alkali, EDC and PVC Production Facility: Thyssenkrupp Uhde has won FEED contracts for an ethylene dichloride (EDC) plant and a chlor-alkali plant & Technip Energies has won the FEED contract for a polyvinyl chloride (PVC) facility. (Source: MEED)
23 May 2024
Project Landing: The commercial bids have been submitted on April 22, 2024. Audex and Rotary Engineering have submitted bids for the project.
08 May 2024
Cogeneration Plant in Ruwais: Orascom Construction Company amongst others have submitted the main contract bids for the project.
24 March 2024
Project Landing: The commercial bid submission has been extended till March 29, 2024. (Source: MEED)
08 March 2024
Project Landing: The commercial bid submission has been extended till March 22, 2024. (Source: MEED)
01 March 2024
Project Landing: The commercial bid submission has been extended till March 15, 2024.
22 February 2024
Ruwais Blue Ammonia Plant: Construction works have commenced on the project.
06 February 2024
Cogeneration Plant in Ruwais: The project scope has been revised and the main contract tender has been re-issued. (Source: MEED)
28 January 2024
Project Landing: The following companies have submitted bids for the project. They are Audex, Petrojet, and Rotary Engineering.
25 January 2024
Project Landing: The commercial bid submission has been extended till February 05, 2024.
20 December 2023
Project Landing: The commercial bid submission has been extended till January 25, 2024.
05 December 2023
Ruwais Derivative Park 400/220KV Substation and OHL: National Contracting Company has been appointed as the main contractor.
26 October 2023
Project Landing: The commercial bid submission has been extended till December 15, 2023.
10 October 2023
Chlor-Alkali, EDC and PVC Production Facility: The FEED contract is yet to be awarded.
05 September 2023
The Isopropyl Alcohol Production Facility and maleic Anhydride Production Facility are in the study stage.
25 August 2023
Methanol Production Facility: Prequalification documents have been submitted for the project. (Source: MEED)
28 July 2023
Petrochemical Derivative Complex: Methanol Production Facility: Technip Energies has been awarded as front-end engineering and design (feed) consultant. The front-end engineering and design (feed) work is currently progressing on the project. The FEED works are expected to be completed by Q3 2023. (Source: MEED)
27 July 2023
Abu Dhabi National Energy Company - Cogeneration Plant in Ruwais - The project is yet to be awarded.
30 May 2023
Maleic Anhydride Production Facility, Isopropyl Alcohol Production Facility, Taziz: Methanol Production Facility: The project is in study stage and Ruwais Blue Ammonia Plant : Construction is yet to commence. Taziz: Chlor-Alkali, EDC and PVC Production Facility: The FEED contract is yet to be awarded.
05 March 2023
Ruwais Blue Ammonia Plant:KBR has announced has been awarded a contract to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant.
31 January 2023
Cogeneration Plant in Ruwais : The following companies has submitted the bids: Larsen and Toubro (L&T) and Alghanim International General Trading & Contracting and the bids are under evaluation.
29 December 2022
Cogeneration Plant in Ruwais: The main contract bid submission has been further extended to January 24, 2023.
23 December 2022
The bid submission date has been extended to January 4, 2023.
08 November 2022
The site preparation works are ongoing and the final investment decision on first phase is expected by end of 2022. Taziz: Blue Ammonia Production Facility & Methanol Production Facility: The client is focused on progressing of the project at the TAâZIZ Industrial Chemicals Zone. Port and Logistics Facility in Ruwais: The research team was able to confirm that the main contract tender has been issued in October 2022 with a bid submission date on January 27, 2023, and the following companies have been pre-qualified and are likely to submit bids for the project:1. National Marine Dredging Company (NMDC) 2. DEME 3. Van Oord 5. Jan De Nul 6. Boskalis.
25 September 2022
Blue Ammonia Production Facility: FEED works are still ongoing on the project. Cogeneration Plant in Ruwais: The main contract bids are still under evaluation.
20 July 2022
Cogeneration Plant in Ruwais- The main contract bids were submitted on July 15, 2022. Amongst others, Al-Ghanim International, Doosan, Elsewedy Electric, Hyundai Engineering & Construction, Power China, Samsung C&T, Samsung Engineering, and Sepco 3 have submitted bids for the project.
12 July 2022
Cogeneration Plant in Ruwais- The main contract bids submission deadline has been further extended to July 15, 2022.
03 June 2022
The bids for main FEED contract are under evaluation.
18 May 2022
Shaheen Chem Holdings Investment (Shaheen) will join the joint venture of Abu Dhabi Chemicals Derivatives Company (Taziz) and Reliance Industries, for Taziz EDC & PVC plant project.
01 May 2022
The main contract bids submission deadline has been extended to May 27, 2022, on Cogeneration Plant in Ruwais Project.
22 April 2022
The following companies have submitted the main feed contractor bids for the project Chlor-Alkali, EDC and PVC Production Facility: Worley parson, Technip, and Thyssenkrupp, and are currently under evaluation. SNC-Lavalin has been appointed as the Project Management Consultant.
29 March 2022
The main contract bids submission deadline for the Cogeneration Plant project has been extended to the end of April 2022.
01 March 2022
The client has prequalified 11 companies to bid for the contract to develop the Cogeneration Plant in Ruwais project.: Al-Ghanim International, Doosan, Elsewedy Electric, Harbin, Hyundai Engineering & Construction, Larsen & Toubro Power, Orascom, Power China, Samsung C&T, Samsung Engineering, and Sepco 3.
13 January 2022
The main contract tender has been issued with a bid submission deadline of March 17, 2022, for the Cogeneration Plant project.
14 October 2021
The main FEED contractor is yet to be appointed for the project Chlor-Alkali, EDC and PVC Production Facility.
05 July 2021
Fertiglobe has signed an agreement with Taziz for the development of the project for Blue Ammonia Production facility. (Source: MEED)
04 July 2021
Wood Group has been appointed the pre-feed contractor for the project. The main FEED contractor is yet to be appointed.
28 March 2021
ITB has been issued for the FEED works. (Source: MEED)
16 February 2021
Land survey works are complete and the construction works are expected to commence by early 2022. (Source: MEED)