Taziz - Petrochemical Derivative Complex in Ruwais

General Information
Owner Taziz
Masterplan Project (Parent Profile)
Location Ar Ruways, Emirate of Abu Dhabi, UAE
Status --
Sector Chemical, Production, Petrochemical Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $374m
Award Date April 2023
Completion Date December 2028
Last Updated On March 2023
ProjectId (Old, New) 338040, 338040


Taziz, a joint venture of ADNOC and ADQ is planning to develop the derivative park in Ruwais, Abu Dhabi.

The US$7,270 million project includes the following:

1. Construction of Chlor-alkali production plant with a capacity to produce 940 thousand tons per year

2. Construction of ethylene dichloride production plant with a capacity to produce 1.1 million tons per year

3. Construction of polyvinyl chloride production plant with a capacity to produce 360 thousand tons per year

4. Construction of methanol production plant

5. Construction of ammonia production plant

6. Construction of isopropyl alcohol production plant

7. Construction of elastomers production plant

8. Construction of port facilities

9. Installation of a feedstock supply system

10. Infrastructure works

11. Construction of associated facilities

Second Section

05 March 2023

Ruwais Blue Ammonia Plant:KBR has announced has been awarded a contract to provide the technology licence, basic engineering design, proprietary equipment and catalyst for the low-carbon ammonia plant.

31 January 2023

Cogeneration Plant in Ruwais : The following companies has submitted the bids: Larsen and Toubro (L&T) and Alghanim International General Trading & Contracting and the bids are under evaluation.

29 December 2022

Cogeneration Plant in Ruwais: The main contract bid submission has been further extended to January 24, 2023.

23 December 2022

The bid submission date has been extended to January 4, 2023.

08 November 2022

The site preparation works are ongoing and the final investment decision on first phase is expected by end of 2022. Taziz: Blue Ammonia Production Facility & Methanol Production Facility: The client is focused on progressing of the project at the TA’ZIZ Industrial Chemicals Zone. Port and Logistics Facility in Ruwais: The research team was able to confirm that the main contract tender has been issued in October 2022 with a bid submission date on January 27, 2023, and the following companies have been pre-qualified and are likely to submit bids for the project:1. National Marine Dredging Company (NMDC) 2. DEME 3. Van Oord 5. Jan De Nul 6. Boskalis.

25 September 2022

Blue Ammonia Production Facility: FEED works are still ongoing on the project. Cogeneration Plant in Ruwais: The main contract bids are still under evaluation.

20 July 2022

Cogeneration Plant in Ruwais- The main contract bids were submitted on July 15, 2022. Amongst others, Al-Ghanim International, Doosan, Elsewedy Electric, Hyundai Engineering & Construction, Power China, Samsung C&T, Samsung Engineering, and Sepco 3 have submitted bids for the project.

12 July 2022

Cogeneration Plant in Ruwais- The main contract bids submission deadline has been further extended to July 15, 2022.

03 June 2022

The bids for main FEED contract are under evaluation.

18 May 2022

Shaheen Chem Holdings Investment (Shaheen) will join the joint venture of Abu Dhabi Chemicals Derivatives Company (Taziz) and Reliance Industries, for Taziz EDC & PVC plant project.

01 May 2022

The main contract bids submission deadline has been extended to May 27, 2022, on Cogeneration Plant in Ruwais Project.

22 April 2022

The following companies have submitted the main feed contractor bids for the project Chlor-Alkali, EDC and PVC Production Facility: Worley parson, Technip, and Thyssenkrupp, and are currently under evaluation. SNC-Lavalin has been appointed as the Project Management Consultant.

29 March 2022

The main contract bids submission deadline for the Cogeneration Plant project has been extended to the end of April 2022.

01 March 2022

The client has prequalified 11 companies to bid for the contract to develop the Cogeneration Plant in Ruwais project.: Al-Ghanim International, Doosan, Elsewedy Electric, Harbin, Hyundai Engineering & Construction, Larsen & Toubro Power, Orascom, Power China, Samsung C&T, Samsung Engineering, and Sepco 3.

13 January 2022

The main contract tender has been issued with a bid submission deadline of March 17, 2022, for the Cogeneration Plant project.

14 October 2021

The main FEED contractor is yet to be appointed for the project Chlor-Alkali, EDC and PVC Production Facility.

05 July 2021

Fertiglobe has signed an agreement with Taziz for the development of the project for Blue Ammonia Production facility. (Source: MEED)

04 July 2021

Wood Group has been appointed the pre-feed contractor for the project. The main FEED contractor is yet to be appointed.

28 March 2021

ITB has been issued for the FEED works. (Source: MEED)

16 February 2021

Land survey works are complete and the construction works are expected to commence by early 2022. (Source: MEED)