Qatargas - Sulphur Storage and Export Facilities (EPC-4)

General Information
Owner QatarGas
Masterplan Project (Parent Profile) Qatargas – North Field East Development: Onshore – Qatar
Location Ras Laffan, Al Khor Municipality, Qatar
Status --
Sector Gas, Storage, Gas Tank
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 800
Net Value $800m
Award Date April 2022
Completion Date December 2026
Last Updated On May 2022
ProjectId (Old, New) 329689, 329689


Qatargas is planning the construction of Sulphur Storage and Export facilities at Ras Laffan Industrial City (RLIC), Qatar.

The current profile includes Package 4.

The US$1,000 million project includes the following:

1. Construction of a sulphur storage tank with a capacity of 10,000 tonnes

2. Laying of connecting pipelines

3. Installation of a control system and valves

4. Mechanical and instrumentation works

5. Construction of associated facilities

Second Section

02 May 2022

A JV of Tecnicas Reunidas & Wison Engineering has been appointed the main contractor for the project.

14 April 2022

The main contract bids are under evaluation and the time frame for the award is yet unknown from the client.

30 March 2022

The main contract bids are under evaluation.

28 February 2022

The following companies have submitted the commercial bids for the project: Tecnicas Reunidas, Saipem & Hyundai E&C.

24 February 2022

The commercial bids are expected to be submitted by February 28, 2022.

25 January 2022

The commercial bids are expected to be submitted by the end of February 2022.

08 December 2021

The following companies have submitted the technical bids for the project: Saipem, Tecnicas Reunidas, and Hyundai E&C. The commercial bids are expected to be submitted by early 2022.

20 October 2021

The main contract bids have not been submitted yet.

26 September 2021

Amongst others, Hyundai E&C has been invited for the tender and is likely to submit bids. We are in the process of obtaining the other pre-qualifed companies at this moment.

09 September 2021

The main contract tender was issued and the bid submission deadline is unknown at this juncture.

21 June 2021

There is no news regarding the main contract tender issue yet.

22 February 2021

PQ shortlist is yet to be finalized.

21 October 2020

Solicitation of Interest (SOI) has been issued in the first week of August 2020 and Samsung Engineering amongst the few other EPC's have submitted the SOI documents.

02 August 2020

Chiyoda Corporation is working as the FEED contractor. The client is going for reFEED as the capacity is increasing from 3,000 to 10,000 tonnes.