QatarEnergy LNG - NEFD: Sulphur Storage and Export Facilities
Qatargas is planning the construction of Sulphur Storage and Export facilities at Ras Laffan Industrial City (RLIC), Qatar.
The current profile includes Package 4.
The US$650 million project includes the following:
1. Construction of a sulphur storage tank with a capacity of 10,000 tonnes
2. Laying of connecting pipelines
3. Installation of a control system and valves
4. Mechanical and instrumentation works
5. Construction of associated facilities
Second Section
No Content
No Content
11 January 2024
The construction works are still ongoing on the project and is expected to be completed by 2026.
17 October 2023
The construction works are still ongoing on the project.
14 September 2023
The construction works are ongoing on the project as per the schedule.
05 July 2023
IRIS Construction is working as civil sub-contractor and the construction works are ongoing on the project as per the schedule.
20 June 2023
Construction works are ongoing on the project and expected to completed by 2028.
18 May 2023
The construction works have been commenced on the project.
08 January 2023
Engineering works are ongoing and the construction works are expected to commenced soon.
02 September 2022
Detailed Engineering works are ongoing on the project.
07 July 2022
QatarEnergy has signed a joint venture agreement with TotalEnergies(6.25%), Shell(6.25%), Eni(3.125%), ExxonMobil(6.25%), and ConocoPhillips(3.125%) for the North Field East Development project, in which QatarEnergy holds a 75 percent stake, and the project is estimated to complete in 2025. (Source: MEED)
13 June 2022
Consolidated Contractors Company is appointed as the pipeline installation subcontractor.
02 May 2022
A JV of Tecnicas Reunidas & Wison Engineering has been appointed the main contractor for the project.
14 April 2022
The main contract bids are under evaluation and the time frame for the award is yet unknown from the client.
30 March 2022
The main contract bids are under evaluation.
28 February 2022
The following companies have submitted the commercial bids for the project: Tecnicas Reunidas, Saipem & Hyundai E&C.
24 February 2022
The commercial bids are expected to be submitted by February 28, 2022.
25 January 2022
The commercial bids are expected to be submitted by the end of February 2022.
08 December 2021
The following companies have submitted the technical bids for the project: Saipem, Tecnicas Reunidas, and Hyundai E&C. The commercial bids are expected to be submitted by early 2022.
20 October 2021
The main contract bids have not been submitted yet.
26 September 2021
Amongst others, Hyundai E&C has been invited for the tender and is likely to submit bids. We are in the process of obtaining the other pre-qualifed companies at this moment.
09 September 2021
The main contract tender was issued and the bid submission deadline is unknown at this juncture.
21 June 2021
There is no news regarding the main contract tender issue yet.
22 February 2021
PQ shortlist is yet to be finalized.
21 October 2020
Solicitation of Interest (SOI) has been issued in the first week of August 2020 and Samsung Engineering amongst the few other EPC's have submitted the SOI documents.
02 August 2020
Chiyoda Corporation is working as the FEED contractor. The client is going for reFEED as the capacity is increasing from 3,000 to 10,000 tonnes.