ADNOC - Habshan Carbon Capture Utilisation and Storage (CCUS)

General Information
Owner ADNOC Gas Processing
Masterplan Project (Parent Profile)
Location Abu Dhabi, Emirate of Abu Dhabi, UAE
Status --
Sector Gas, Upstream, Gas Extraction
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 6
Estimated Budget Value ---
Contract Value 600
Net Value $600m
Award Date October 2023
Completion Date March 2026
Last Updated On November 2023
ProjectId (Old, New) 328061, 328061


ADNOC Gas Processing is planning to construct of CO2 recovery and injection project at the Habshan 5 gas plant field, the UAE.

It will ramp up its carbon capture, utilization, and storage (CCUS) capability to 5 million tonnes per annum by the end 0f 2030.

It is expected to recover almost 4.2 million tpa of carbon dioxide for injection into existing oilfields for enhanced recovery through the Habshan-Bab and Shah gas plants.

The US$740 project includes the following:

1. Installation of CO2 recovery unit (1,500 mtpa reduction in CO2)

2. Installation of CO2 primary compression facility

3. Construction of a triethylene glycol dehydration unit

4. Enhancement of existing tail gas treatment units

5. Construction of associated facilities

Second Section

01 November 2023

The construction works have commenced.

04 October 2023

Petrofac has been appointed as the main contractor with a contract value of US$600 million.

07 September 2023

The financial investment decision (FID) has been approved on the project. (Source: MEED)

29 July 2023

Petrofac is the front runner in the project.

17 May 2023

The bids for the project are under evaluation.

30 March 2023

The commercial bid submission is in April 2023 however the exact date is not yet announced.

22 February 2023

The project completion is expected in first quarter of 2026.

18 January 2023

Larsen & Toubro and Archirodon amongst others have submitted the technical bids. However, the commercial bid submission date is not yet announced.

20 December 2022

The bid submission date has been extended to January 9, 2023

16 November 2022

The main contract tender has been issued with bid submission on November 29, 2022. L&T and few other unknown contracting companies is likely to submit bids

07 October 2022

The main contract tender is yet to be issued on the project.

26 August 2022

The client is planning to issue the main contract tender soon on the project.

21 April 2022

FEED works are completed and the main contract tender is not yet issued.

14 January 2022

The main contract tender is not yet issued.

29 November 2021

Market sources indicate that the main contract tender is yet to be issued.

13 October 2021

The main contract tender is not yet issued.

27 September 2021

Market sources indicate that the main contract tender is not yet issued.

11 July 2021

Market sources indicate that the main contract tender is not yet issued.

09 May 2021

Market sources indicate that the main contract tender is not yet issued.

25 March 2021

Market sources indicate that the main contract tender is not yet issued.

30 July 2020

WorleyParsons is working as the FEED contractor.