ADNOC - Habshan Carbon Capture Utilisation and Storage (CCUS)
ADNOC Gas Processing is planning to construct of CO2 recovery and injection project at the Habshan 5 gas plant field, the UAE.
It will ramp up its carbon capture, utilization, and storage (CCUS) capability to 5 million tonnes per annum by the end 0f 2030.
It is expected to recover almost 4.2 million tpa of carbon dioxide for injection into existing oilfields for enhanced recovery through the Habshan-Bab and Shah gas plants.
The US$740 project includes the following:
1. Installation of CO2 recovery unit (1,500 mtpa reduction in CO2)
2. Installation of CO2 primary compression facility
3. Construction of a triethylene glycol dehydration unit
4. Enhancement of existing tail gas treatment units
5. Construction of associated facilities
Second Section
No Content
No Content
01 November 2023
The construction works have commenced.
04 October 2023
Petrofac has been appointed as the main contractor with a contract value of US$600 million.
07 September 2023
The financial investment decision (FID) has been approved on the project. (Source: MEED)
29 July 2023
Petrofac is the front runner in the project.
17 May 2023
The bids for the project are under evaluation.
30 March 2023
The commercial bid submission is in April 2023 however the exact date is not yet announced.
22 February 2023
The project completion is expected in first quarter of 2026.
18 January 2023
Larsen & Toubro and Archirodon amongst others have submitted the technical bids. However, the commercial bid submission date is not yet announced.
20 December 2022
The bid submission date has been extended to January 9, 2023
16 November 2022
The main contract tender has been issued with bid submission on November 29, 2022. L&T and few other unknown contracting companies is likely to submit bids
07 October 2022
The main contract tender is yet to be issued on the project.
26 August 2022
The client is planning to issue the main contract tender soon on the project.
21 April 2022
FEED works are completed and the main contract tender is not yet issued.
14 January 2022
The main contract tender is not yet issued.
29 November 2021
Market sources indicate that the main contract tender is yet to be issued.
13 October 2021
The main contract tender is not yet issued.
27 September 2021
Market sources indicate that the main contract tender is not yet issued.
11 July 2021
Market sources indicate that the main contract tender is not yet issued.
09 May 2021
Market sources indicate that the main contract tender is not yet issued.
25 March 2021
Market sources indicate that the main contract tender is not yet issued.
30 July 2020
WorleyParsons is working as the FEED contractor.