Qatargas - North Field South Development

General Information
Owner QatarGas
Masterplan Project (Parent Profile) Qatargas – North Field LNG Expansion – Qatar
Location Ras Laffan, Al Khor Municipality, Qatar
Status --
Sector Gas, Upstream, Gas Extraction
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $9450m
Award Date October 2021
Completion Date December 2028
Last Updated On September 2021
ProjectId (Old, New) 324896, 324896


Qatargas is planning the development of phase 2 of the North Field LNG expansion project by increasing the capacity from 110MTPA to 126MTPA in Ras Laffan Industrial City (RLIC), Qatar.

It is also known as North Field South (NFS) Project.

The US$10,000 million project includes the following:

1. Construction of two LNG trains

2. Construction of an LNG storage tank

3. Construction of a helium recovery unit

4. Construction of a non-technical building

5. Construction of off plot facilities

6. Construction of five wellhead platforms

7. Laying of pipelines

8. Installation of jackets

Second Section

27 September 2021

The following companies have submitted the main contract bids for the Five Wellhead Platforms project: Hyundai Heavy Industries, McDermott, Saipem, Sapura, Subsea7, and Technip Energies. The main contract is expected to be awarded by the end of October 2021.

08 August 2021

The main contract tender has been issued with a bid submission deadline of September 15, 2021 on Five Wellhead Platforms. The following companies are preparing to submit the bids for the project: Hyundai Heavy Industries, McDermott, Saipem, Sapura, Subsea7, and Technip Energies.

24 June 2021

There is no news regarding the main contract tender issue yet for the Five Wellhead Platforms project.

04 May 2021

The FEED works have been completed on Five Wellhead Platforms.

07 January 2021

McDermott has been awarded a FEED contract for the five wellheads package.

05 June 2020

Engineering and construction works are expected to commence after the completion of the 4th LNG train project. Currently, the project is in the initial stage.