ADNOC Offshore - UZ1000 Expansion: Development of Surface Facilities

General Information
Owner ADNOC Offshore
Masterplan Project (Parent Profile) ADNOC Offshore – Upper Zakum FFD: UZ1000 Expansion – Abu Dhabi
Location UAE
Status --
Sector Oil, Upstream, Oil Extraction
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 3
Estimated Budget Value ---
Contract Value 825
Net Value $825m
Award Date March 2024
Completion Date December 2026
Last Updated On April 2024
ProjectId (Old, New) 49072, 317607


ADNOC Offshore plans to develop surface facilities for UZ1000 expansion at Upper Zakum Full Field Development, the UAE.

This project is also known as UZ1.2MMBD

The package covers the development of surface facilities, specifically on four main drilling islands: Al-Ghallan (Central Island), Umm al-Anbar (West Island), Ettouk (North Island) and Asseifiya (South Island).

The US$1032 million project includes the following:

A. The EPC work on Al-Ghallan island includes the following:

1. Construction of production, water injection and produced water disposal wells

2. Laying of pre-assembled pipe racks and manifold

3. Construction of gas lift compressor and glycol dehydration unit

4. Construction of water injection plant

5. Construction of produced water treatment package

6. Installation of gas turbine generators

7. Installation of water-winning pump

8. Construction of coarse filtration package

9. Construction of air compressor and dryer package

10. Construction of chemical injection packages

11. Construction of module technical Rooms

12. Construction of electrical substation

13. Construction of local equipment room

B. EPC work on Umm al-Anbar island includes the following:

1. Construction of booster gas compression package

2. Construction of low pressure gas cooler

3. Construction of crude oil transfer pumps

4. Installation of water-winning pump

5. Construction of coarse filtration package

6. Installation of instrument air compressor and dryer package and receiver

7. Installation of nitrogen generation package and receiver

8. Installation of low pressure flare gas recovery compressor package

9. Construction of electrical substation

10. Construction of module technical Rooms

C. EPC work on Ettouk island includes the following:

1. Construction of produced water treatment package

2. Construction of new produced water disposal header and disposal wells

3. Construction of produced water disposal pumps

D. EPC work on Asseifiya island includes the following:

1. Construction of produced water treatment and re-injection train

2. Construction of produced water booster/disposal and re-injection pumps

3. Construction of electrical substation

Second Section

18 April 2024

Target Engineering Construction Company has been appointed as the main contractor for the project. (Source: MEED)

10 April 2024

The main contract is yet to be awarded.

06 February 2024

The main contract is not yet awarded.

05 January 2024

Target Engineering Construction Company is the front-runner and the main contract is expected to be awarded by January 2024. (Source: MEED)

19 December 2023

The main contract bids are still under evaluation.

17 November 2023

The following companies have submitted the bids: Petrofac, Target Engineering Construction Company, and Tecnicas Reunidas. (Source: MEED)

02 November 2023

The commercial bid submission due is on November 13, 2023. (Source: MEED)

10 October 2023

The commercial bid submission due is on October 23, 2023. (Source: MEED)

20 September 2023

The commercial bid submission is yet to be done on the project.

03 July 2023

Petrofac, Tecnicas Reunidas, NPCC and a few other unknown contracting companies have submitted technical bids for the project. The commercial bid submission is yet to be done on the project.

07 June 2023

The technical bids are submitted for the project. (Source: MEED)

01 June 2023

Technical bid submission deadline for the EPC works has been extended from May 29, 2023 to June 5, 2023. (Source: MEED)

26 May 2023

Technical bid submission deadline for the EPC works has been extended from May 18, 2023 to May 29, 2023. (Source: MEED)

16 May 2023

Technical bid submission deadline for the EPC works has been extended to May 18, 2023. (Source: MEED)

05 April 2023

The following companies are likely to submit bids on the project: Tecnicas Reunidas, Petrofac and Saipem.

26 March 2023

The tender for the EPC works had been issued by late February 2023 and the technical bid submission date is on April 20, 2023. (Source: MEED)

09 January 2023

The main contract tender is yet to be issued.

17 October 2022

ExxonMobil is initiating a meeting with ADNOC, regarding the project development.

23 August 2022

The project continues to be on hold and the time frame for its revival is unknown at this juncture.

25 January 2022

The project continues to be on hold.

21 October 2021

The project is still on hold.

11 May 2021

The project has been placed on hold due to investment issues.

29 March 2021

ITB is not yet issued and the time frame for the same is unknown at this juncture.

31 January 2021

ITB is yet to be issued and the time frame for the same is unknown at this juncture.

02 November 2020

ITB is yet to be issued and the time frame for same is unknown at this juncture.

24 August 2020

ITB is not yet issued and the time frame for same is unknown at this juncture.

17 June 2020

Wood Group has been appointed as the Project Management Consultant (PMC). (Source: MEED)

21 April 2020

ITB is not yet issued and the time frame for same is unknown at this moment. Saipem, Petrofac, Hyundai E&C, L&T Hydrocarbons among the few other's have submitted the PQ documents.

27 January 2020

ITB is expected to be issued in April 2020 with the main contract award by the third quarter of 2021. The project is scheduled to be completed by the end of 2022. (Source: MEED)

26 December 2019

The bid submission has taken place on December 23, 2020 for PMC contract and Tier-1 project consultants are understood to have been submitted the bids. (Source: MEED)

01 December 2019

ITB has been issued to Tier-1 project consultants for PMC contract with the bid submission date due on December 23, 2019. (Source: MEED)

26 November 2019

The PQ submission has taken place for main contract on November 25, 2019 and 24 companies understood to have been submitted the pre-qualification documents. (Source: MEED)

10 May 2019

Tecnicas Reunidas is working as the FEED Contractor.