SATORP - Amiral Complex
Saudi Aramco and Total (SATORP) are planning to develop a chemical plant named as Amiral complex in Jubail, Saudi Arabia.
The US$11,000 million project includes the following:
1. Construction of Ethylene plant (1.65 MTPA)
2. Construction of Propylene plant (50,000 TPA)
3. Construction of Acrylonitrile plant with the capacity of 425,000tpa
4. Construction of Linear Alpha Olefin (LAO) plant with the capacity of 400,000tpa
5. Construction of Poly Alpha Olefin (PAO) plant
6. Construction of Logistic Area
7. Construction of Utility Flare and Interconnection
8. Construction of Tank Farm
9. Laying of Pipelines and value park integration
10. Satorp integration
11. Construction of storage facilities
12. Construction of associated facilities
Second Section
No Content
No Content
23 March 2023
Pkg 2,3,5A,5B&5C- The main contract is not yet awarded. (Source: MEED)
16 March 2023
Pkg 1&4: Hyundai Engineering & Construction has been awarded the contract however the official announcement is still awaited.
10 March 2023
The project has been announced in the first wave of private sector projects under Shareek programme.
14 February 2023
The main contract is expected to be awarded in third or fourth week of March 2023. (Source: MEED)
11 January 2023
The main contract bids on the packages: Tank Farm: Package 5A, Utility Flare and Interconnection: Package 4, High-Density Polyethylene and Logistic Area: Package 3, Site Preparation Works (Package 8), Temporary Construction Facilities (Package 7), Pipelines: Package 5B, Derivatives Unit: Package 2, Mixed Feed Cracker: Package 1 are still under evaluation and are expected to be awarded by March 2023.
27 December 2022
The construction is expected to be commenced in 2023 and is is set to start operations in 2027.
16 December 2022
The client has taken the final investment decision for the construction of the complex. The investment is around US$11 billion out of which US$4 billion will be funded through equity by Aramco (62.5%) and TotalEnergies (37.5%).
07 December 2022
The main contract bid for the Cogeneration independent steam and power plant (ISPP) is expected to be submitted by end of March 2023.
25 November 2022
Hyundai Engineering & Construction, Larsen & Toubro Energy Hydrocarbon and Technip Energies has come up as the lowest bidder for the package 1&4, package 2 and package 3 respectively. (Source: MEED)
15 November 2022
The main contract bids are still under evaluation and the time-frame for the award is currently unknown.
20 October 2022
Bids are under evaluation for the Packages 1, 2, 3, 4, 5A, 5B and 5C. Hyundai E&C, CTCI, Technip, Tecnicas Reunidas and Saipem amongst others have submitted the bids.
12 October 2022
Pkg 1&4: Hyundai E&C amongst others have submitted the commercial bids.
21 September 2022
Pkg 3,5A,5B & 5C: The technical bids were submitted on September 18, 2022. We are in the process of identifying the bidders. (Source: MEED)
20 September 2022
Pkg 1&4: Hyundai E&C amongst others have submitted the technical bids.
13 September 2022
Pkg 2: Hyundai E&C amongst others have submitted the technical bids. JGC Corporation has declined to participate in the project. Pkg 1,3,4,5A,5B,5C,7&8: The technical bid submission date has been extended till September 18, 2022. (Source: MEED)
24 August 2022
The technical bid submission date has been extended till September 11, 2022 and the commercial bid submission is on October 09, 2022. (Source: MEED)
14 July 2022
The bid submission date has been extended till August 31, 2022. (Source: MEED)
13 June 2022
The main contract tender is issued on project. The bids are expected to be submitted by August 15, 2022. Hyundai E&C, Saipem, Mc Dermott, Técnicas Reunidas, Sinopec, CPECC, CTCI, L&T, Samsung, JGC and Technip have prequalified companies on the project.
20 April 2022
The main contract PQ documents are yet to be shortlisted for Site Preparation Works (Package 8) and Temporary Construction Facilities (Package 7).
24 November 2021
The project is facing delays.
29 September 2021
There is no news regarding the main contract PQ shortlist on Jubail 2 Complex and Ethylene & Propylene Plant yet.
20 June 2021
The client has issued SOI for packages one to six on April 22, 2021 and for package seven & eight on May 25, 2021. The EoI documents have been submitted by May 30, 2021 for packages one to six and by June 10, 2021 for package seven & eight. (Source: MEED)
11 April 2021
FEED works are ongoing and the main contract tender is yet to be issued.
02 June 2020
FEED works are getting delayed
21 April 2020
JXTG Nippon Oil & Energy Corporation has been appointed as the feasibility study consultant on Ethylene & Propylene Plant package. FEED works are progressing as per the schedule and the time frame for completion is unknown at this juncture.
10 December 2019
FEED works are ongoing and Saudi authority in talks with potential companies for further development. (Source: MEED)
23 October 2019
McDermott International has been appointed as the technology provider.
24 July 2019
The client is in talks with several chemical firms for the development of the project. (Source: MEED)
11 June 2019
SATORP and INEOS have signed an MOU for the development of Acrylonitrile Plant, LinearAlphaOlefin Plant and PolyAlphaOlefin Plant.
15 November 2018
TechnipFMC and WorleyParsons have been appointed as the FEED and PMC contractors respectively