ADNOC/Total/PetroChina/ENI - Umm Shaif Gas Cap Condensate Development: Phase 1
The JV of ADNOC Offshore, Total, PetroChina and ENI are planning to develop phase 1 of the Umm Shaif Gas Cap Condensate Development in the northwest of Abu Dhabi.
The French giant Total, PetroChina and Italyâs Eni together hold a 40% stake in the new Umm Shaif and Nasr concession. Total holds a 20% stake and PetroChina and Eni hold 10% each, with the majority stake of 60% being held by Adnoc Offshore.
The project involves the development of a gas field with a production capacity of 500MMSCFD. (Million Standard Cubic Feet Per Day)
This project is one of the most important oil and gas projects in the MENA region
The US$1,500 million project includes the following:
1. Construction of three offshore wellhead towers
2. Construction of a riser tower platform
3. Construction of a gas processing and separation platform
4. Laying of a condensate subsea pipeline of 24" and 20"
5. Laying of intrafield pipelines
6. Construction of associated facilities
Second Section
No Content
No Content
15 March 2024
The main contract is yet to be awarded.
19 December 2023
The main contract is yet to be awarded.
16 October 2023
The main contract is yet to be awarded.
14 August 2023
The main contract is yet to be awarded. Saipem is the front runner on this project.
09 June 2023
The main contract is yet to be awarded
05 April 2023
The main contract is yet to be awarded
23 February 2023
The main contract bids are still under negotiations.
05 January 2023
The main contract is yet to be awarded
17 November 2022
Saipem is the preferred bidder on the project. (Source: MEED)
04 October 2022
The consortium of Saipem/China Petroleum Engineering & Construction Company (CPECC) have submitted the commercial bids for the EPC works. (Source: MEED)
19 September 2022
The re-feed works have been completed and currently the contractors are preparing the commercial bids. The EPC contract is expected to be awarded by end 2022. (Source: MEED)
19 August 2022
The re-feed works are still ongoing and is expected to complete in next 2 months.
27 July 2022
The re-feed works are almost completed till 85-90 per cent and the overall completion is expected in next 2-3 months.
12 May 2022
The re-FEED process is still ongoing on the project.
25 March 2022
The re-FEED process is still ongoing on the project.
10 January 2022
The re-FEED process is ongoing and Saipem is executing the revised works.
30 November 2021
The main contract tender is yet to be awarded.
13 October 2021
The participant companies are still awaiting for an official news from Adnoc regarding the main contract award.
31 August 2021
The participant companies are still awaiting for an official news from Adnoc regarding the main contract award.
27 July 2021
The participant companies are still awaiting official news from Adnoc regarding the main contract award.
06 June 2021
The participant companies are still awaiting for an official news from Adnoc regarding the main contract award.
19 April 2021
The participant companies are still awaiting for an official news from Adnoc regarding the main contract award.
28 March 2021
The participant companies are still awaiting for an official news from Adnoc regarding the main contract award.
12 January 2021
The participant companies are still awaiting for an official news from Adnoc regarding the main contract award. (Source: MEED)
05 November 2020
The project continues to be under bid evaluation stage. However, the client is in talks with the JV of Petrofac and Saipem for the development of the project. (Source: MEED)
22 October 2020
The project is yet to be awarded and the time frame for same is unknown at this juncture.
18 September 2020
JV of Saipem & Petrofac has been emerged as the lowest bidder while the JV of NPCC & Technip and McDermott International has been emerged as the second and third lowest bidders respectively. (Source: MEED)
26 August 2020
The commercial bid submission has taken place on August 24, 2020 and JV of NPCC & TechnipFMC, JV of Petrofac & Saipem and McDermot International have submitted the bids. (Source: MEED)
19 August 2020
The commercial bid submission date has been further extended to August 24, 2020.
09 August 2020
The commercial bid submission date has been further extended to August 16, 2020.
27 July 2020
The commercial bid submission date has been further extended to August 2, 2020. (Source: MEED)
18 June 2020
The commercial bid submission date has been further extended to July 15, 2020.
05 May 2020
The commercial bid submission date has been further extended to June 15, 2020.
23 April 2020
The commercial bid submission date has been further extended to May 3, 2020.
06 April 2020
The commercial bid submission date has been further extended to April 15, 2020.
20 January 2020
The technical bid submission has been done and the commercial bid submission date has been extended to March 31, 2020.
18 July 2019
The FEED works are progressing as per the schedule with the technical and commercial bid submission date is due on November 15, 2019 and December 5, 2019. The EPC contract is expected to be awarded by the first quarter of 2020.
12 May 2019
JV of National Petroleum Construction Company & TechnipFMC, McDermot International and JV of Petrofac & Saipem are the pre-qualified shortlisted companies for FEED+EPC competition. The main contractor will be appointed post the submission of FEED documents.
01 May 2019
KBR has been appointed as the Project Management Consultant (PMC).