ADNOC - Hail and Ghasha Sour Gas Development: Package 4

General Information
Owner Abu Dhabi National Oil Company
Masterplan Project (Parent Profile) ADNOC – Hail and Ghasha Sour Gas Development – UAE
Location Abu Dhabi, Emirate of Abu Dhabi, UAE
Status --
Sector Gas, Downstream, Gas Processing Plant
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 0
Estimated Budget Value ---
Contract Value 0
Net Value $5000m
Award Date March 2021
Completion Date November 2024
Last Updated On September 2020
ProjectId (Old, New) 43343, 284588


Abu Dhabi National Oil Co (ADNOC) is planning to undertake the Manayif gas processing plant at Hail and Ghasha Sour gas development in Abu Dhabi, the UAE.

This profile includes Manayif process plant (Package 4)

The US$5,000 million project includes the following:

1. Construction of Manayif processing plant

2. Construction of a gas gathering unit

3. Construction of a processing unit

4. Construction of a sulphur recovery unit

5. Construction of associated facilities

Second Section

16 September 2020

The commercial bid submission date has been further delayed until November 2020 due to adverse market conditions and the client has begun a series of meetings with contractors to discuss scope of work and other aspects related to the project. (Source: MEED)

16 July 2020

The commercial bid submission date has been further extended to November 2, 2020.

15 May 2020

The commercial bid submission date has been further extended to July 31, 2020.

20 April 2020

The commercial bid submission date has been further extended to May 31, 2020. (Source: MEED)

30 March 2020

The commercial bid submission date has been further extended to April 22, 2020. (Source: MEED)

19 March 2020

The client has scheduled the commercial bid submission date on March 29, 2020. (Source: MEED)

05 February 2020

The technical evaluation is underway and the commercial bids are yet to be submitted. (Source: MEED)

06 January 2020

The technical evaluation is underway and the commercial submission date is yet to be issued. (Source: MEED)

05 December 2019

The JV of Tecnimont and L&T, JV of Petrofac and Samsung Engineering, JV of Tecnicas Reunidas and McDermott International, JV of CPECC and Saipem has submitted the technical bids.

04 December 2019

The commercial bids are due to be submitted in January 2020 and the contract is expected to be awarded by the end of the first quarter of 2020. (Source: MEED)

12 November 2019

The technical bid submission has taken place and Petrofac has submitted the bids amongst the few other companies.

08 November 2019

The technical bid submission date has been further extended to November 11, 2019. (Source: MEED)

29 October 2019

The technical bid submission date has been further extended to October 31, 2019. (Source: MEED)

25 September 2019

The technical bid submission date has been further extended to October 13, 2019.

17 September 2019

The technical bid submission date has been extended to September 23, 2019.

28 August 2019

The technical bid submission date is due on September 9, 2019. (Source: MEED)

07 August 2019

ITB has been issued, the last date for technical bid submission is August 18, 2019 and for commercial submission, it is likely to be in October 2019. The following companies have been pre-qualified: Fluor (USA), TechnipFMC (France), Hyundai Engineering & Construction (South Korea), Maire Tecnimont (Italy), Samsung Engineering (South Korea), Petrofac (UK), Saipem (Italy), Daewoo Engineering and Construction (South Korea), Tecnicas Reunidas (Spain), JGC Corporation (Japan), Hyundai Engineering Company (South Korea), Daewoo Shipbuilding and Marine Engineering (South Korea), G S Engineering and Construction (South Korea), SK Engineering & Construction (South Korea), McDermott International (US), China Petroleum Engineering and Construction Corporation (China), Consolidated Contracting Engineering and Procurement Company – SAL offshore, National Petroleum Construction Company (NPCC – UAE), Subsea7 (UK), Larsen & Toubro Hydrocarbon Engineering (India), Archirodon (Greece), China Petroleum Pipeline Engineering Company (China), Essar Projects (India), ENPPI (Egypt), Sinopec Engineering (China) and Siirtec Nigi (Italy).

16 May 2019

The client has formally asked prequalified contractors for Hail and Ghasha to form JVs or consortiums between themselves for packages 1 and 4. The ITB for the four packages in expected to be issued by August 2019. (Source: MEED)

04 April 2019

ITB for the project is expected to be issued by May 2019 and the EPC contract would be awarded in Q3 2019.

29 January 2019

Bechtel is carrying out the FEED activities and KBR is the PMC for the project. The following list of companies has submitted pre-qualifying documents for the EPC contract: Hyundai Engineering and Construction, Samsung Engineering, Larsen & Toubro, Saipem, Petrofac, McDermott, GS Engineering & Construction and JGC. (Source: MEED)

20 January 2019

Adnoc is in the process of shortlisting the pre-qualified companies for EPC contact. The list of following companies is aiming to pre-qualify for EPC contract. Hyundai Engineering and Construction (South Korea), Samsung Engineering (South Korea), Larsen & Toubro (India), Petrofac (UK), McDermott (USA), Saipem, GS Engineering & Construction (South Korea), JGC (Japan). PQ deadline has been extended to 26 January 2019. (Source: MEED)

24 December 2018

The Feed activities are underway.

06 November 2018

The Feed activities are underway, ITB is yet to be issued.

10 September 2018

PQ documents have not yet been issued for the project.

12 August 2018

PQ documents have not yet been issued for the project.

30 July 2018

PQ documents have not yet been issued for the project.

18 July 2018

The FEED is ongoing on the project and is expected to be completed in 2019.

06 June 2018

The feed is ongoing on the project and completion is expected in Q2 2019

04 June 2018

It is understood that the Expression of interest submission has been taken place on May 20, 2018. We are trying to identify the companies interested to participate in the project. Currently the FEED is also ongoing on the project.