ADNOC - Hail and Ghasha Sour Gas Development: Onshore Package II
Abu Dhabi National Oil Co (ADNOC) is undertaking the construction of onsite utilities and onshore pipelines at Hail and Ghasha Sour gas development in Abu Dhabi, UAE.
This profile includes Manayif Onsite Utilities and Onshore Pipelines.
The CO2 recovery facility will have a total capacity to capture and store 1.5 million tonnes a year and NextChem Tech's scope of work encompasses the PDP for the raw gas compression station, the dehydration and separation unit, the CO2 compression station, and other associated facilities.
The scope of work for packages 3&4 has been merged into a single profile under the name "Onshore Package."
The US$8700 million project includes the following:
1. Construction of Manayif onshore processing plant
2. Construction of two gas processing units
3. Construction of three sulfur recovery sections
4. Laying of 231.7km onshore pipeline
5. Utilities and offsite works
6. hydrogen and carbon dioxide (CO2) recovery unit
7. Installation of solar PV plants for Camps and TCF ( 2MW)
8. Construction of associated facilities
Second Section
No Content
No Content
14 April 2025
Cactus General Transport is working as the equipment mobilization sub-contractor and 15 percent of mobilization works have been completed on the project.
05 March 2025
The construction works are ongoing on the project and are expected to be completed by the second quarter of 2028.
26 December 2024
The Construction works have commenced on the project.
01 October 2024
Dome International LLC has been awarded the design, supply, and installation of solar PV plants for Camps and TCF. The total capacity is 2MW.
26 August 2024
INCO awarded Tank & Sphere Package for 21 tanks and 2 sphere tanks.
23 August 2024
The sub-contracts have been awarded on the project. Denholm Yam has been awarded the mechanical contract, the Nasser S Al-Hajri Corporation has been awarded the civil works contract, and NBTC has been awarded the electrical and instrumentation contract on the project (Source: MEED)
06 August 2024
Maire Tecnimont has appointed Emarat Al Oula Industries (EAI) Company (Ali & Sons) for supply subcontract of 1.4 million inch-dia piping works with an contract value of US$70.7 million.
26 June 2024
Maire Tecnimont has announced that it has appointed NextChem as the technology design integrator consultant with a value of US$60m. (Source: MEED)
03 April 2024
Dome Oilfield Engineering & Services LLC has been appointed for conducting the Environmental studies on the project.
13 February 2024
Engineering works are ongoing on the project and subcontractor has not yet appointed.
28 December 2023
Construction works are yet to commence.
05 October 2023
Tecnimont has been awarded as the main contractor.
29 August 2023
Tecnimont is the front-runner for the project.
31 July 2023
The EOIs has been submitted. The following companies are participating : L&T, Tecnimont, Samsung Engineering, Technip Energies.
23 May 2023
EoI documents submission date was extended to May 19, 2023. The firms have submitted EoIs. (Source: MEED)
01 May 2023
The pre-construction service agreements (PCSA) have been cancelled and ADNOC has re-issued EoI documents for the selection of the main contractor and the prequalification deadline is on May 14, 2023. (Source: MEED)
19 January 2023
Onshore Package: Early Development Works - The client has signed pre-construction service agreements (PCSAs) with Technip Energies, Samsung Engineering and Tecnimont at a contract value of around US$80 million to commence initial detailed engineering works, the early procurement for long-lead items required for the project and also includes preparation of an open book cost estimate of the project which will be reviewed while making the final investment decision (FID). (Source: MEED)
13 January 2023
The client is in the process of signing pre-construction service agreements (PCSA) with the shortlisted bidder companies. The scope of the agreement includes the starting of detailed engineering works and also early procurement for long-lead items required for the project. The value for the agreement is estimated to be around US$150 million. (Source: MEED)
04 January 2023
The main contract bids are under evaluation.
01 November 2022
The FEED works are still ongoing on the project however the timeframe for completion is currently unknown.
26 September 2022
The main contract bids have been submitted by the consortium of Samsung Engineering, Technip Energies and Tecnimont.
19 September 2022
The bid submission date for the EPC works is on September 26, 2022. The early engagement process with the considered contractors has been started by the client and the FEED work is ongoing simultaneously. (Source: MEED)
08 September 2022
The client has considered a consortium of Technip Energies, Samsung Engineering, and Tecnimont for the EPC works on the project. There is no formal agreement or contract signed with any contractor. The project EPC contract is likely to be awarded in June 2023 and currently the feed work is ongoing on the project.
24 June 2022
The bid process is still at an initial stage, some of those expected to show initial interest include Italyâs Saipem and Tecnimont, Abu Dhabiâs National Petroleum Construction Company (NPCC), Indiaâs Larsen & Toubro (L&T), McDermott International of the US, Spainâs Tecnicas Reunidas, UKâs Petrofac, Chinaâs China Petroleum Engineering & Construction Corporation (CPECC), South Korean giants Samsung E&C and Hyundai E&C, Greek player Archirodon and Chinaâs Sinopec.
15 April 2022
The companies have not yet been PQ shortlisted.
07 April 2022
NPCC and Robtstone have submitted the EOI documents.
14 March 2022
The EOI submission deadline has been extended till March 21, 2022. Amongst others, Target Engineering and Al Asab Est are likely to submit the PQ documents.
09 March 2022
The scope of Package 4 is merged with package 3.
07 March 2022
ADNOC has issued expressions of interest (EoI) to contractors for participation in the EPC tendering phase. Contractors to submit general documents for the EoI process by March 6, 2022, and detailed information by March 14, 2022. Simultaneously, Feed is progressing and expected to be completed by the end of the year. (Source: MEED)
07 January 2022
FEED works are ongoing on the project.
22 December 2021
The main contract tender have been cancelled due to the ongoing optimization process.
22 November 2021
Technip Energies has been awarded the contract for the revised front-end engineering and design (feed) works on the project. (Source: MEED)
27 October 2021
The submission of commercial bids for Feed tender has taken place on October 23, 2021. Flour Corporation, Technip Energies and Worley have submitted the commercial bids. (Source: MEED)
06 October 2021
The submission of technical bids for Feed tender has taken place on October 4, 2021.
27 September 2021
The technical bid submission date for Feed tender has been further extended to October 4, 2021. Flour Corporation, Technip Energies and Worley are likely to submit the technical bids. (Source: MEED)
18 August 2021
The tender for Feed works has been re-issued and the technical bid submission date for the revised feed tender is due on September 23, 2021. FEED optimization is being carried out by KBR and the client company, ADNOC has asked all the previous main contract bidders to extend the bid validity for one year.
29 July 2021
The client has restarted the project from the initial stage due to cost optimization. On July 25, 2021 Adnoc had issued an notification to release new tender for pre-feed and Feed works and Flour Corporation, KBR, Technip Energies, Wood Group and Worley have received the documents. (Source: MEED)
16 June 2021
ADNOC is in the process of re-designing the project for FEED optimization with revised scope. Once the final designs are drafted and approved by ADNOC, the tender process would be either continued or re-initiate. Currently, it is unknown that the client will reissue the tender or request the existing tender participant companies to resubmit new bids with respect to the revised scope at this moment
02 May 2021
The main contract is yet to be awarded by the client company and the market sources indicate that the client company ADNOC is likely to re-initiate the FEED works as the bids submitted are expensive.
05 April 2021
The bids are still under evaluation and the main contract is yet to be awarded
28 February 2021
The commercial bid submission has taken place and currently, the bids are under evaluation. (Source: MEED)
18 February 2021
The commercial bid submission has been further extended to February 24, 2021. (Source: MEED)
25 January 2021
The commercial bid submission date has been further extended to February 17, 2021. (Source: MEED)
07 January 2021
The commercial bid submission date has been further extended to January 24, 2021. (Source: MEED)
09 December 2020
The commercial bid submission date has been further extended to January 10, 2021.
07 December 2020
The commercial bid submission is due on December 10, 2020 and it is expected to be further extended.
26 October 2020
The firms are in the process of preparing the commercial bid submission which is due on December 6, 2020 and MMEC Mannesmann is also the pre-qualified shortlisted company.
30 September 2020
The commercial bid submission date has been further extended to December 6, 2020.
16 September 2020
The commercial bid submission date has been further delayed until November 2020 due to adverse market conditions and the client has begun a series of meetings with contractors to discuss scope of work and other aspects related to the project. (Source: MEED)
16 July 2020
The commercial bid submission date has been further extended to November 2, 2020.
15 May 2020
The commercial bid submission date has been further extended to July 31, 2020.
16 April 2020
The commercial bid submission date has been further extended to May 31, 2020.
30 March 2020
The commercial bid submission date has been further extended to April 22, 2020. (Source: MEED)
13 March 2020
The client has scheduled the commercial bid submission date on March 29, 2020. (Source: MEED)
05 February 2020
The technical evaluation is underway and the commercial bids are yet to be submitted.
06 January 2020
The technical evaluation is underway and the commercial submission date is yet to be issued. (Source: MEED)
05 December 2019
Tecnimont, JV of Petrofac and Samsung Engineering, JV of Archirodon, Sinopec and CCC, Dodsal, have submitted the technical bids.
04 December 2019
The commercial bids are due to be submitted in January 2020 and the contract is expected to be awarded by the end of the first quarter of 2020. (Source: MEED)
20 November 2019
Maire Tecnimont, Consolidated Contractor Company amongst others have submitted bids for the project.
12 November 2019
The technical bid submission has taken place and Petrofac, Archirodon, Dodsal has submitted the bids amongst the few other companies.
08 November 2019
The technical bid submission date has been further extended to November 11, 2019. (Source: MEED)
29 October 2019
The technical bid submission date has been further extended to October 31, 2019. (Source: MEED)
25 September 2019
The technical bid submission date has been further extended to October 13, 2019.
17 September 2019
The technical bid submission date has been extended to September 23, 2019.
20 August 2019
The technical bid submission date is due on September 9, 2019.
07 August 2019
ITB for the project has been issued on June 2019. The last date for technical bid submission is August 18, 2019 and for commercial submission, it is likely to be in October 2019. The following companies have been pre-qualified: Dodsal (UAE), Fluor (USA), TechnipFMC (France), Hyundai Engineering & Construction (South Korea), Maire Tecnimont (Italy), Samsung Engineering (South Korea), Petrofac (UK), Saipem (Italy), Daewoo Engineering and Construction (South Korea), Tecnicas Reunidas (Spain), JGC Corporation (Japan), Hyundai Engineering Company (South Korea), Daewoo Shipbuilding and Marine Engineering (South Korea), G S Engineering and Construction (South Korea), SK Engineering & Construction (South Korea), McDermott International (US), China Petroleum Engineering and Construction Corporation (China), Consolidated Contracting Engineering and Procurement Company â SAL offshore, National Petroleum Construction Company (NPCC â UAE), Subsea7 (UK), Larsen & Toubro Hydrocarbon Engineering (India), Archirodon (Greece), China Petroleum Pipeline Engineering Company (China), Essar Projects (India), ENPPI (Egypt), Sinopec Engineering (China) and Siirtec Nigi (Italy). (Source: MEED)
13 May 2019
The ITB not yet issued for the project.
04 April 2019
The ITB for the project is expected to be issued by May 2019 and the EPC contract would be awarded in December 2019
05 February 2019
TATA projects have also submitted PQ for the project on January 26, 2019.
29 January 2019
Bechtel is carrying out the FEED activities and KBR is the PMC for the project. The following list of companies has submitted pre-qualifying documents for the EPC contract: Hyundai Engineering and Construction, Samsung Engineering, Larsen & Toubro, Saipem, Petrofac, McDermott, GS Engineering & Construction and JGC. (Source: MEED)
20 January 2019
Adnoc is in the process of shortlisting the pre-qualified companies for EPC contact. The list of following companies is aiming to pre-qualify for EPC contract. Hyundai Engineering and Construction (South Korea), Samsung Engineering (South Korea), Larsen & Toubro (India), Petrofac (UK), McDermott (USA), Saipem, GS Engineering & Construction (South Korea), JGC (Japan). PQ deadline has been extended to 26 January 2019. (Source: MEED)
24 December 2018
The Feed activities are underway.
06 November 2018
The Feed activities are underway, ITB is yet to be issued.
10 September 2018
PQ documents have not yet been issued for the project.
12 August 2018
PQ documents have not yet been issued for the project.
30 July 2018
PQ documents have not yet been issued for the project.
18 July 2018
The FEED is ongoing on the project and is expected to be completed in 2019.
06 June 2018
The feed is ongoing on the project and completion is expected in Q2 2019
04 June 2018
It is understood that the Expression of interest submission has been taken place on May 20, 2018. We are trying to identify the companies interested to participate in the project. Currently, the FEED is also ongoing on the project.