KSPF - King Salman International Park: Royal Art Complex
King Salman Park Foundation (KSPF) is undertaking the construction of a 1.2 km art complex comprising on an area of 300,000m2 named Royal Art Complex at King Salman Park in Riyadh, Saudi Arabia.
The complexâs national and outdoor theatres are expected to have a seating capacity of 2,500 and 8,000, respectively.
The US$1,600 million project includes the following:
1. Construction of a museums on 300,000 sqm GFA
2. Construction of 2,500 Car parking spaces
Plot A:
3. Construction of cinema halls
4. Construction of a National Theater with 2,300 seating capacity
5. Construction of a Mastercraft Studios
6. Construction of Museum of World Cultures
7. Construction of Art Dome
8. Construction of Sculpture Pavilion
9. Construction of National Theater
10. Construction of Library
11. Construction of Cinema Halls
Plot B:
12. Construction of MOC Academies
13. Construction of Multipurpose Theater
14. Associated Facilities
Second Section
No Content
No Content
12 March 2024
The construction works are progressing on the project.
10 January 2024
The construction works are progressing on the project.
06 September 2023
The construction works are progressing on the project.
01 May 2023
Site visit as on April 2023, reveals that the construction works are progressing on the project.
22 November 2022
Structural works are progressing on the project and MEP works are being carried out by First Fix.
14 July 2022
Foundation waterproofing has commenced on the project.
21 June 2022
Mobilisation works have commenced on the project.
20 April 2022
The main contract has been awarded to Modern Building Leaders Co LLC and the final contract has been signed for around US$1333 million.
29 March 2022
The main contract bids are under evaluation. (Source: MEED)
06 January 2022
The client has asked the contractors to submit revised bids by January 16, 2022. Al-Bawani, El-Seif Engineering Contracting/Alec, Modern Building Leaders are the preferred bidders on the project. (Source: MEED)
17 November 2021
The main contract tender bids are under evaluation and expected to be awarded by December 2021.
07 October 2021
The main contract bids have been submitted and the following companies have submitted the bids: Al-Bawani, El-Seif Engineering Contracting/Alec, Modern Building Leaders, and Nesma / Alsaad General Contracting / Saudi Constructioneers (Saudico) / Modern Architecture Contracting Company. (Source: MEED)
15 September 2021
The main contract bid submission deadline has been shortended from October 17, 2021, to early October 2021. (Source: MEED)
30 August 2021
The main contract bid submission deadline has been extended from August 31, 2021, to October 17, 2021. (Source: MEED)
18 July 2021
The main contract bid submission deadline has been extended from August 2, 2021, to August 31, 2021. (Source: MEED)
16 June 2021
The main contract tender has been issued with the bid submission due on August 2, 2021. Typsa is working as an architect and consulting engineer, Buro Happold as consulting engineer, Ricardo Bofill Taller de Arquitectura as a design consultant, Parsons as PMC, Gleeds as cost consultant, and Theatre Consultants as a theatre consultant. (Source: MEED)