QatarEnergy LNG - NFED: Pipelines and Topsides Facilities

General Information
Owner QatarEnergy LNG
Masterplan Project (Parent Profile) QatarEnergy LNG – North Field East Development: Offshore – Al Khawr
Location Doha, Doha Municipality, Qatar
Status --
Sector Gas, Upstream, Gas Extraction
Contract Type Engineering Procurement Construction (EPC)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 84
Estimated Budget Value ---
Contract Value 1000
Net Value $1000m
Award Date January 2022
Completion Date September 2024
Last Updated On March 2024
ProjectId (Old, New) 47542, 297467


Qatargas is undertaking the construction of offshore pipelines and topside facilities as part of the North Field Expansion (NFE) project in Qatar.

The US$1,250 million project includes the following:

1. Construction of eight unmanned wellhead platforms (WH-14,15,16,17,18,19,20&21)

2. Laying of four 38-inch trunklines

3. Laying of four 28-inch intra-field lines

4. Installation of interfaces and tie-ins with EPC-1&3

5. Installation of power and fiber optic (PFO) subsea cable rings

6. Installation of 500 km of pipelines and 225 km of 33kV subsea cables

7. Construction of associated facilities

Second Section

18 March 2024

The construction works are still ongoing on the project and are expected to be completed by 2024.

04 January 2024

The construction works are still ongoing on the project and is expected to be completed by May 2024.

02 November 2023

The construction works are ongoing on the project and is expected to be completed by 2025.

04 July 2023

The construction works have been commenced on the project.

17 March 2023

AlJaber Engineering has been appointed as a sub-contractor on the project at a contract value of US$50 million.

08 January 2023

Engineering works are ongoing and the construction works are expected to commenced soon.

18 August 2022

Detailed Engineering works are ongoing on the project.

07 July 2022

QatarEnergy has signed a joint venture agreement with TotalEnergies(6.25%), Shell(6.25%), Eni(3.125%), ExxonMobil(6.25%), and ConocoPhillips(3.125%) for the North Field East Development project, in which QatarEnergy holds a 75 percent stake, and the project is estimated to complete in 2025. (Source: MEED)

08 May 2022

Detailed engineering works are ongoing on the project.

04 January 2022

McDermott has been awarded a contract to undertake engineering, procurement, construction, and installation (EPCI) works for the project. (Source: MEED)

28 December 2021

The main contract bids are still under evaluation and expected to be awarded very soon.

25 October 2021

The main contract bids are under evaluation and expected to be awarded by November 2021.

17 October 2021

The following companies have submitted the commercial bids for the project: Hyundai Heavy Industries, McDermott, Saipem, Sapura, Subsea7, and Technip Energies. The main contract is expected to be awarded by the end of October 2021.

08 August 2021

The client has sought revised commercial offers from contractors by September 15, 2021. The following companies are preparing to submit the bids for the project: Hyundai Heavy Industries, McDermott, Saipem, Sapura, Subsea7, and Technip Energies. (Source: MEED)

07 June 2021

The bids are still under evaluation and the main contract is yet to be awarded.

15 February 2021

The commercial bid submission took place on February 12, 2021, and McDermott, Saipem, Sapura, and Subsea7 have submitted the bids. (Source: MEED)

03 September 2020

The main contract tender has been issued and Saipem, McDermott, L&T, Sapura and Subsea7 are the pre-qualified shortlisted companies. FEED works are progressing.

14 July 2020

FEED works are still progressing and there is no news regarding the issuance of tender.

12 March 2020

FEED works are still underway and the time frame for completion is unknown at this juncture.

10 December 2019

FEED works are ongoing

12 July 2019

The FEED works have commenced and the project will be executed from McDermott's Doha offices. The award also includes submission of an EPCI proposal by McDermott International.

24 June 2019

McDermott International has been awarded the FEED contract and the works are expected to be complete by June 2020. (Source: MEED)