Dubai Holding - Dubailand Mixed Use Development

General Information
Owner Dubai Holding
Masterplan Project (Parent Profile)
Location Dubai, Emirate of Dubai, UAE
Status --
Sector Construction, Mixed-Use, Mixed-Use
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 73
Estimated Budget Value ---
Contract Value 0
Net Value $19579m
Award Date July 2005
Completion Date December 2030
Last Updated On March 2024
ProjectId (Old, New) 9724, 289297


Dubai Holding is undertaking the construction of Dubailand development on 27,871ha of land in Dubai, the UAE.

The US$85,000 million project includes the following:

1. Construction of 1390ha attractions & experience world

a. Construction of F1-X theme park Dubai

b. Construction of Tiger Woods Dubai

c. Construction of Bawadi

d. Construction of Falcon city of wonders

e. Construction of Tourism world

f. Construction of Legends of Dubailand

g. Construction of Aviation world

h. Construction of Islamic culture and science world

i. Construction of Global village

j. Construction of Kids City

k. Construction of Giants world

l. Construction of water parks.

m. Construction of hotel apartments

2. Construction of 3290Ha sports and outdoor world

a. Construction of Dubai Sports City

b. Construction of Dubai Motor City

3. Construction of ecotourism world

4. Construction of themed leisure and vacation world

5. Construction of 180ha of downtown

a. Mall of Arabia

b. Wadi walk

c. Virtual game world

Second Section

19 March 2024

Vincitore Benessere (Plot No. 6734123) project is complete.

26 February 2024

Arjan: UniEstate Supreme Residence project is complete.

14 December 2023

Azizi Sports City: Azizi Grand: Construction works are ongoing as per the schedule.

08 October 2023

Construction works on the Hotel Apartment (Plot No. 6489017) project are ongoing and likely to be completed by mid-2024. The in-house division of ARCO Turnkey Solutions Contracting is undertaking the MEP works.

26 September 2023

Excavation works are underway on the Dubailand: Sobha Reserve project.

26 August 2023

Mobilization works on the Arjan: Adhara Star project have been completed and Spots Electromechanical Works is handling the MEP works for the project. Construction works on the Dubailand: Tilal Al Ghaf: Boulevard & Vibe Roads project are ongoing and the time frame for its completion is unknown at this juncture.

02 August 2023

Construction works are ongoing on Tilal Al Ghaf: Elan Townhouses project and the timeframe for its completion is unknown at this juncture.

20 July 2023

The project Dubailand: Green Residency (Plot No. 648-8657) has been put on hold and block works are underway in the project Hotel Apartment (Plot No. 6489017).

14 June 2023

Aladdin Tower (Plot no: 6457549) project continues to be on hold and the timeframe for the revival is unknown at this juncture.

18 May 2023

External cladding works are still ongoing on the Dubai Sports City: Profile Residence (Plot No 599-7499) project.

20 April 2023

Construction works are progressing on the SDland: Arjan: Al Barsha South Gardenia Livings.

14 March 2023

Tilal Al Ghaf: 132/11 kV Substation and Associated Works the project is complete.

20 February 2023

Construction works on the Tilal Al Ghaf: Alaya Villas: Infrastructure Package project is ongoing and the project is expected to complete by the end of December 2025.

29 January 2023

Construction works are ongoing and are expected to be completed by March 2023 on the 132/11 kV Substation and Associated Works project.

09 December 2022

Construction works have commenced on the Arjan: Prime Gardens project.

09 November 2022

Arjan Street Scape Development Phase I : the project is completed.

06 October 2022

Construction works have progressed up to 85 per cent and the project is expected to be completed by December 2023 on the Vincitore Benessere Development.

28 June 2022

External finishing works are still ongoing on the Majan Residential Building (Plot No.6458039) project.

25 February 2022

Design work are ongoing on Tilal Al Ghaf: Alaya and Aura Villas.

27 December 2021

The Golf City: Indigo Zen II project continues to be on hold and the time frame for its revival is unknown at this juncture.

27 October 2021

Wadi Al Safa 3 : Residential Building (Plot 6455963):finishing works are progressing and it is expected to be completed by April 2022.

12 October 2021

Finishing works are on final stage of development on Echo Plex (Phase 2).

08 September 2021

Majan Residential Building continues on hold.

21 July 2021

Construction works are progressing on Elan Townhouses.

20 June 2021

The project Dubailand 10 villas have been revived and the construction works are ongoing at a slow pace due to financial issues.

12 May 2021

Structural works are progressing on Arabian Gate 1 (Plot No. 648-8569).

15 April 2021

Dubailand : Fox Themed Park and Resorts continues to be on hold and the time frame for the revival is unknown at this juncture.

14 March 2021

Finishing works are still progressing on Residential Building (Plot 6455963).

04 January 2021

Finishing works are in final stage of development on Residential Building (Plot 6455963).

10 December 2020

Al Saud Company - Residential Building at Wadi Al Safa 5 (Plot No. 6488736) : The project continues to be on hold.

26 November 2020

Private Developer - Dubailand : Mixed Use Building (Plot no:6457773) : The project continues to be on hold.

17 November 2020

The project Dubailand 10 villas have put on hold due to unknown reasons.

16 October 2020

The project Hotel Apartment (Plot No. 6489017) continues to be on hold.

08 October 2020

Finishing works are in final stage on Dubailand: Residential Building in Wadi Al Safa and it is expected to complete by November 2020.

01 September 2020

The project Liwan Hotel Apartment (Plot No. 6489017) put on hold due to the financial issues.

13 August 2020

Finishing works are progressing on Wadi Al Safa 5 (Plot No.: 6489194) and the expected timeline for completion is unknown at this juncture.

15 July 2020

Construction works are progressing in slow pace on Residential Building in Majan (Plot No.6458039) due to unwanted situation in the region.

21 June 2020

Finishing works are progressing on Arabian Dubailand K1 (Plot No. 648-9213) the project and the expected timeline for completion is unknown at this juncture.

06 May 2020

Construction works are ongoing on Alfardan group - Dubailand : Bin Fardan and exact time frame for completion is unknown at this juncture.

07 April 2020

The project is still on hold on Condor Group - Dubailand : (Majan) Condor Fortuna Hotel (Plot No. 645-7978).

17 March 2020

The construction works are ongoing and are scheduled to be completed by July 2021 on La Quinta.

23 January 2020

Construction works are ongoing on Al Owais Tower (Plot no 6730917) and it is expected to complete by the first quarter of 2020 and The project (Majan) Condor Fortuna Hotel (Plot No. 645-7978) is continues to be on hold due to financial issue from client and the time frame for the revival is unknown at this juncture.

31 December 2019

Construction works are progressing on Dubailand: Gargash Tower (Plot no 6730919 )and the overall project is expected to complete by June 2020.

04 December 2019

Construction works completed on residential building (Plot no :6731140).

02 October 2019

Finishing activities are underway on Al Barsha South and the project is expected to be completed by the fourth quarter of 2019.

28 August 2019

Construction works are ongoing for Amina Residence II.

22 July 2019

The construction works on Q zone for MU 7 is complete and Mu 5/6 is still in progress with the scheduled completion of December 2019.

16 June 2019

The construction works on Indigo Zen 2 package have progressed up to 40%.

26 May 2019

The project Residential Building (Plot no. 6489222) is 95 percent complete and finishing works are underway.

29 April 2019

Construction works are underway for 8 Storey Residential Building in Majan

13 March 2019

Structural works have progressed till 10th floor on Gargash Tower project.

08 February 2019

Superstructure works completed on the Samana Greens project

08 January 2019

20% of construction activities are completed and the residential building K1 on a plot 648-9213 project is expected to finish by June, 2019.

18 December 2018

80% of the construction activities are complete for 16 story Champions Tower III, the project is expected to complete by February, 2019.

16 December 2018

The Diamond Star on (Plot No 673-1266) project is still on hold due to financial issues.

12 December 2018

Construction activities have commenced for Al Fahim Tower and the project is expected to complete by end of 2021. The residential building on (Plot No 6488612) project is still on hold due to financial issues.

11 December 2018

The construction activities for residential building on (Plot No 682 to 131) under Dubai Sports City are expected to complete by fourth quarter of 2019.

06 December 2018

The Falcon City of Wonders: Taj Arabia project is placed on hold, Falcon Head Mall is in the initial stage of development and in the process of appointing a consultant.

28 November 2018

17% of construction activities have been progressed on Residential Building(Plot No 682 - 146)and is expected to complete by December, 2019. 70% of construction activities have been progressed on Profile Residences on (Plot No 682-273). The project continues to be on hold for residential building located on (Plot No 682-267) and universal tower on (Plot No 6821372).

26 November 2018

Construction activities are underway for Mazaya Q Zone MU 002 and is expected to complete by November, 2019. Mobilization works are going on Jamil Tower and construction activities will start in January, 2019. 70% construction works are completed for Green Residency and is expected to complete by March, 2019. Construction works have progressed up to the fourth floor on the plot no. 645 - 7845 in Majan and is expected to complete by June, 2019. Construction activities are underway for MU 5/6 and is expected to complete by October, 2019 and MU 7 is expected to complete by May, 2019. Construction works on Plot no. 6437699 are underway and is expected to be completed by November 2019.

09 October 2018

*Al Maskan Al Hadeeth - Dubailand: Paradise View 2 at Majan (Plot 645-6063) Site visit on October 09, 2018 reveals that the construction works are progressing on the 09th and 10th floor of the project.

31 August 2018

*Distinguished Real Estate - Dubailand: Residential Building at Wadi Al Safa 5 Site visit on August 29, 2018 reveals that structural works are progressing on twenty eighth floor and block works are progressing on twenty fifth floor.

01 August 2018

*Binghatti Developer- Dubailand: Binghati East & West (Plot No. 6489211, 6489207): Binghatti east is expected to be completed by September 2018.

22 July 2018

*Dubai Land Residences - Liwan: Hotel Apartment The main contract has been awarded to Ur Contracting Co.

17 July 2018

*Union Properties - Motorcity : Oia Residences The finishing works are ongoing on the project. The expected completion date is unknown at this juncture.

12 July 2018

*Private Developer - Residential Building At Al Barsha South (Plot no :6731140) Al Habbai Contracting is working as the main contractor and foundation contractor on the project. Technomech Electromechanical Works is appointed as the MEP contractor on the project. Raft foundation works are ongoing.

05 July 2018

*Private Developer - Residential Building at Al Barsha South 2(Plot No - 6729632) Due to no instruction from the client, the construction works have not commenced yet MEP is not appointed yet.

01 July 2018

*Private Developer - Hotel Apartment at Wadi Al Safa 5 (Plot No.6488593) Due to some changes in the scope, the completion is extended to August 2018.

19 June 2018

*Private Developer - Dubailand : Residential Building (Plot no:6457773): As per site visit on June 16, 2018 reveals that excavation works are ongoing but at a slow pace. Advance Building Construction Company is doing the MEP works on the project.

14 June 2018

*Dubai Holding - Dubailand: Arjan - Fidarjan Limited - Arjan : Showrooms and Office Building (Plot no. 6731199): As per site image on June 6, 2018 reveals that external cladding works are ongoing on the project. *Private Developer - Majan : Residential Building (Plot 6455963): As per site visit on June 14, 2018 reveals that sub-structural works are ongoing on the project.

10 June 2018

Dubai Holding - Dubailand: Arjan - Private Developer - Arjan : Residential Building (Plot no: 6731257): As per site visit on June 7, 2018 reveals that the project is complete.

28 May 2018

*Binghatti Developer- Dubailand: Binghati East & West (Plot No. 6489211, 6489207) Construction works are progressing at an accelerated pace on the project.

15 May 2018

*Tanmiyat - Aladdin Tower (Plot no: 6457549) Finishing works are ongoing on the project. The project will be completed in September.

10 May 2018

*Time Properties - Arabian Gate 2 at Wadi Al Safa 5 Hadi consultant is appointed as the Consultant.

24 April 2018

*Pal Developments - Dubai Sports City: Oasis Tower 2 (Plot No:682147) As per site visit on April 23, 2018, reveals that structural works are progressing on the twenty-third floor of the project along with external glassworks.

24 April 2018

*Titans Real Estate - Dubai Sports City: Hera Tower (Plot No: 6820110) As per site visit on April 23, 2018, reveals that the structural works are progressing on the project.

24 April 2018

*Limelight Real Estate - Dubai Sports City: Limelight Twin Towers As per site visit on April 23, 2018, reveals that finishing works have started on the project.

24 April 2018

*Lokhandwala Builders - Dubai Sports City: Eden Gardens As per site visit on April 23, 2018, reveals that finishing works are ongoing on the project.

23 April 2018

*Danube Properties - Arjan: Danube Miraclz Currently, raft foundation works are progressing on the project.

19 April 2018

*Falcon City of Wonders - Medium Pyramid As per site visit on April 1, 2018, reveals that the project is on hold.

19 April 2018

*CityLand Real Estate Developer - Dubailand: Cityland Mall As per site visit on April 1, 2018, reveals that structural works are progressing on the project.

19 April 2018

*GFH - Dubailand: California Village As per site visit on April 1, 2018, reveals that Linesight is working as Project Management Consultant on the project.

16 April 2018

*MAF - Dubailand: Tilal al Ghaf (Ghaf Hills) The overall project completion is scheduled for 2027.

04 April 2018

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

03 April 2018

*Al Mazaya Holding - Dubailand: Q Zone (Plot No - MU 5/6, MU 7) Currently, raft foundation works are ongoing on the project

30 March 2018

*Al Saud Company - Residential Building at Wadi Al Safa 5 (Plot No. 6488736) This main contract was expected to be tendered in Q1 2018. However, there is no news in the market on the tender status at this juncture.The tender issue date, therefore, has been moved to Q2 2018.

29 March 2018

*Private Developer - Residential Building at Al Barsha South 2(Plot No - 6729632) MEP contractor is not yet appointed on the project. The construction works are expected to commence within the next three months

23 March 2018

*Private Developer - Residential Building in Wadi Al Safa 3 (Plot No.: 645-7872) As per site visit on March 14, 2018, reveals that finishing works are ongoing on the project.

20 March 2018

*Esol Education - Dubailand: Dunecrest American School As per site visit on March 14, 2018, reveals that structural works are ongoing on the project.

19 March 2018

*Pacific Ventures - Dubailand: Pacific Village The project continues to remain on hold. The expected time frame for its revival is unknown at this juncture.

15 March 2018

*Private Developer - Residential Building in Wadi Al Safa 2 (Plot no 643-7606) Enabling works are ongoing. *Private Developer - Residential Building at Wadi Al Safa 3 (Plot No. 6457914) As per site visit on March 14, 2018 reveals that block works are progressing on the eighth floor.

23 February 2018

*Gems Education - Wadi Al Safa 7 : Gems Metropole School (Plot.6653091) Site visit on February 17, 2018 reveals that the structural works are at advanced stage and block works are progressing on the 3rd floor of the project.

23 February 2018

*Nshama - 2 Residential buildings at Al Barsha (Plot no. 6730929, 6730930) Site visit on February 02, 2018, reveals that the structural works are completed and finishing works are ongoing on the project.

22 February 2018

*Dubai Holding - Dubailand: Arjan : Fidarjan Limited - Arjan : Showrooms and Office Building (Plot no. 6731199) As per site visit on February 21, 2018 reveals that structural works and block works are ongoing simultaneously on the project.

16 February 2018

Gems Education - Dubailand: School (Plot No. 6468139) - Structural works have progressed up to 90 percent and it is expected to complete by April 2018. Emitech Technical Services LLC is the doing the MEP subcontractor on the project.

23 January 2018

*International Schools Partnership - Dubailand: Aquila School (Plot no- 6489184) - Construction works have progressed up to 30 percent and MEP works are done Inhouse. Aspect Project Management is the project management consultant on the project.

01 January 2018

*Zenith Holding - Dubailand: Residential Building in Majan (Plot no 6457845) As per site visit on November 27, 2017 reveals that structural work is ongoing on ground level.

20 December 2017

*Gulf Developers - Dubailand : The Palmarosa The construction works are progressing on the project and the completion is expected by June 2018.

19 December 2017

*Alfardan group - Dubailand: Bin Fardan Alfardan group is the owner.

11 December 2017

*Al Mazaya Holding - Dubailand :Q Zone (Plot No - MU 5/6, MU 7) The main contract has been awarded to Al Sahel Contracting Company LLC however the construction works have not yet commenced on the project as they are waiting for the approvals from the master developer Dubai Holding. The construction works are expected to commence by January 2018. The total duration of the project for the buildings under plot no : MU 5 / 6 is of 22 months and the total duration of the project for the buildings under plot no : MU 7 is of 18 months. Elemec Electrical Contracting has been appointed as the subcontractor to carry out MEP works on the project. Stromek Emirates and Middle East Foundation have been appointed as the foundation contractor on the project.

27 November 2017

*Indigo Properties - Indigo Zen The finishing works are nearing completion on 4 show villas along with infrastructure and sewerage works are progressing at very slow pace on the project.

21 November 2017

*Al Mazaya Holding - Dubailand: Queue Point: Residential Building (Plot R - 085) The project has been completed.

07 November 2017

*Emirates NBD - Remraam Housing Community : South View School The construction works are progressing as per the schedule and the project is expected to complete by September 2018.

02 November 2017

*Foster Developers - Dubailand (Liwan) : Residential Building(Plot No:6437653) The construction works have progressed till 4th floor of the project.

18 October 2017

*Al Barari Development Company - Dubailand: Al Barari Development: Phase 2 -Al Barari Development Company - Ashjar Living The project will be handed over in June 2018.

25 September 2017

*Private Developer - Dubailand : Residential Tower in Majan (Plot No - 6457793) The design works are underway. The consultant is in the stage of getting the designs approved upto 32 storey on the project.

11 September 2017

*Al Mazaya Holding - Dubailand :Q Zone (Plot No - MU 5/6, MU 7) The project is expected to complete by 2019.

31 August 2017

*Posh Holdings - Majan : Residential Building (Plot no: 645-8043) Site visit on August 27, 2017 reveals that, the project continues to be on hold.

23 July 2017

Burgan Bank has signed the deal to provide finance worth US$ $94.24 million for Cityland mall. The project is expected to be operational by 2018.

15 June 2017

*Al Tawfeeq For Development & Investment - Motor City : First Avenue Mall & Hotel Site visit on June 13, 2017, reveals that exterior finishing works are progressing and the project is nearing completion.

19 April 2017

*Private Developer - Residential Building at Dubailand (Plot No: 673 -1301) - The project has been put on hold due to funding issues since one year. However, time frame for revival is yet unknown.

18 April 2017

*Al Liwan Contracting - Dubailand : Al Liwan Building ( Plot no. RC-E009 ) - The project continues to be on hold and is expected to revive by May 2017.

11 January 2017

*Residential Building in Liwan (Plot no: RC-F-009 6488554) - Construction work is ongoing on the fourth basement level. The contract duration is 32 months.

06 December 2016

*Continental Investment - Dubai Lifestyle City : Rukan : The tender for the main contract has not been issued. The client has appointed CV Tec Consulting Engineers to undertake the design revision and tender documentation for the main contract. The following consultants are no longer associated with the project : *Stantec *Pioneers of Experts Engineering Consultants Carbon General Contracting is no longer associated as the enabling contractor on the project.

10 November 2016

*Dubai Holding - Dubai Sports City : Elite Sports Residences 8 - Site visit on November 9, 2016 reveals that project is complete.

11 October 2016

*Condor Group - Condro Fortuna Hotel Building (Plot No. 645-7978) The project is currently kept on hold due to unknown reasons and the time frame for revival is unknown. However, Emsquare Engineering Consultants and Anmol Piling & Steel Structures are no longer associated with the project.

10 October 2016

*Canal Residences West: Phase 2: (Plot No: R8-13, 682-1403) : The project continues to be on hold and is expected to be revived soon.

04 October 2016

Dubai Holding - Dubailand: Universal City : Site visit on October 3rd, 2016 reveals that the project is still on hold. Al Ahli Group - Dubai Outlet Mall : Phase 2 (Plot No - 911-7199) : As per site visit on October 2,2016 reveals that the mobilization works are ongoing on the project

27 September 2016

A&A Residency - Dubailand : Majan : Residential building (Plot no. RC-C-037) : Site visit on September 25th, 2016 reveals that the project is on hold. Pacific Ventures - Dubailand: Pacific Village : Site visit on September 25th 2016, reveals that the project is still on hold. Tanmiyat - Rapunzel Tower (Plot no: 6457552) : Site visit as on September 25th, 2016 reveals that the construction works are ongoing on the project.

27 September 2016

Tanmiyat - Alibaba Tower (Plot no: 6457565) : As per site visit as on September 25th 2016, reveals that the construction works are progressing on the 7th floor. Tanmiyat - Cinderella Tower (Plot no: 6457561) : Site visit as on September 25th, 2016 reveals that the construction works are ongoing on the project. Tanmiyat - Caesar Tower (Plot no: 6457563) : Site visit as on September 25th, 2016 reveals that the construction works are ongoing on the project. Tanmiyat - Sinbad Tower (Plot No: 6457566) : Site visit as on September 25th, 2016 reveals that the construction works are ongoing on the project.

26 September 2016

Goldline Group - Dubailand : Cassia Park (RC-E-019) : Site visit as on September 25th, 2016 revealed that the project is still on hold.

22 September 2016

Dubai Holding - Dubailand: Universal City : The project is still on hold. The time frame for the revival of the project has not yet been decided.

21 September 2016

Private Developer - Dubailand: Pyramisa Hotel & Resorts (Plot No RC-E-033) : The project is still on hold. The time frame for revival is not known.

20 September 2016

*Rufi Real Estate - DSC: Rufi Twin Towers : The project is currently on hold, however is expected to revive back time frame not known. *Rufi Real Estate - Marmooka City: Akin Towers : The project is cancelled. *Rufi Real Estate - DSC: Rufi Golf Greens : The project is currently on hold, however is expected to revive back time frame not known. *Rufi Real Estate - Dubailand: Rufi Park View (DSC) (Plot No 682-1376): The project is currently on hold, however is expected to revive back time frame not known.

08 September 2016

The finishing works have progressed upto 70 per cent and the overall project will be complete by March 2017 on Al Habtoor Group - St. Regis Polo Resort and Club Project.

07 September 2016

Escan Real Estate - Dubailand: Aurora Tower : The project continues to b on hold however they are chances of the project to be cancelled.

02 August 2016

* Pacific Ventures - Dubailand: Pacific Village :The project has been placed on hold due to major changes in project design, infrastructure & utilities networks. The project is expected to revived in early 2017.

01 August 2016

Al Ahli Group - Dubailand : Fox Themed Park and Resorts The design work is still ongoing on the project and timeline for completion is not yet known. The construction tender is expected in 2017.

07 June 2016

Construction is facing delays in the Living Legends project. Finishing works are ongoing on the Remraan community.

21 March 2016

The Fox Themed Park and Resorts developed by Al Ahli Group is under its conceptual design. Demolition works are ongoing on the Cityland mall and will be completed by May 2016.

24 November 2015

*Dania Property Management &Consultancy : Residential Building(Plot No. 673-1156) - Finishing works are ongoing on the project. The project is expected to be complete by February 2016. *Dania Property Management &Consultancy :Residential Building(Plot no. 673-1146 ) - Finishing works are ongoing on the project. The project is expected to be complete by February 2016.

20 July 2015

Structural works are ongoing on the Windsor Residence and the project is expected to complete by October 2016. Construction on the Onyx project developed by Ishraqah is complete.

18 May 2015

Design works are completed on the Rukan residential community and have been submitted to the local authorities for their approval. Tenders for the main contract will be issued in July 2015.

22 March 2015

*I&M Galadari Group - Dubailand: City of Arabia: Wadi Tower Bin Lahej Electromechanical is handling the MEP works on the project.

22 March 2015

*I&M Galadari Group - Dubailand: City of Arabia: Wadi Tower Construction works on the project are progressing at a slow pace and is expected to be complete in September 2015.

19 February 2015

*Tanmiyat - Dubailand: Living Legends Villas (Plot No:6457145) Phase 1 of the project (150 villas) is expected to be complete by Q2 of 2015.

27 January 2015

*Dubai Holding - Dubailand: Mudon : Phase 2 Al Shamat has been appointed as the MEP contractor for the project.

20 January 2015

*Tanmiyat - Dubailand: Living Legends: Infrastructure works Road works and electricity works are ongoing and the project is expected to complete by July 2015.

15 January 2015

*Al Mazaya - Dubailand: Queue Point: Residential Building (Plot No.R-073) The project has been put on hold and its revival date is yet not known.

14 January 2015

*Rufi Real Estate - Dubailand: Rufi Park View (DSC) (Plot No 682-1376) Construction works are still ongoing and the project is expected to complete by December 2015.

13 January 2015

*Tameer Holding - Dubailand: Majan: Podium The $220m project is still on hold and the time frame for revival of the project has not yet been decided.

12 January 2015

*Dubai Holding- Dubailand: Freej Theme Park The $200m project is still on hold, the time frame for revival of the project has not yet been decided.

06 January 2015

*Emirates Planetarium - Dubailand: Planetarium The $190m project is still on hold and the time frame for revival of the project is not yet decided.

31 December 2014

I&M Galadari Group - Dubailand: Monorail System (City of Arabia) *The $136m project is still on hold and its revival date is still unknown.

17 December 2014

*Al Mazaya - Dubailand: Residential Building (Plot No: R-022) Site visit on November 20 ,2014 revealed that the structural works are complete and the finishing works are ongoing on the project.

15 December 2014

*Falcon City of Wonders - Medium Pyramid Design works are still ongoing on the project and are expected to be complete in August 2015. The tenders for the main contract are expected to be issued once the design works on the project are complete.

26 November 2014

*Dubai Holding - Dubailand: Mudon : Phase I Site visit on November 26, 2014 revealed that the finishing works are ongoing on the project.

26 November 2014

*Tanmiyat - Residential Building (Plot no: 6457549) Site visit as on November 26, 2014 revealed that the superstructure works are ongoing on the project.

26 November 2014

*Tanmiyat - Dubailand: Living Legends Villas (500 nos.) (Plot No:6457145) Site visit as on November 26, 2014 revealed that the structural works are complete on the project.

26 November 2014

*Tanmiyat - Residential Building (Plot no: 6457565) Site visit as on November 26, 2014 revealed that the superstructure woks are ongoing on the project.

25 November 2014

*Salya Developments - Dubailand: Dubai Sports City: Giovanni Boutique Suites The project is complete.

20 November 2014

*ASGC - Dubailand: Mixed-Use Building (Plot no: RC-A-026) Site visit on November 20, 2014 revealed that the superstructure works are ongoing on the ninth floor.

19 November 2014

*Middle East Development LLC - Dubai Sports City : Kensington Royale Site visit on November 19, 2014 revealed that that the project is nearing completion.

19 November 2014

*Bangash Properties - Dubailand: Dubai Sports City: Royale Residences 1 & 2 Site visit as on November 19, 2014 revealed that the construction works on the project are nearing completion.

19 November 2014

*Pan Global Trading - Mixed Use building (Plot No :682-133 Dubai Sports City) Site visit on November 19, 2014 revealed that the superstructure works are nearing completion.

19 November 2014

*Almasah International Real Estate - Dubailand: Dubai Sports City: Chess Tower Site visit as on November 19, 2014 revealed that the construction works are ongoing on the seventh floor.

18 November 2014

*Shaikhani Group - Dubailand: Dubai Sports City: Frankfurt Sports Tower 1 Site visit as on November 18, 2014 revealed that the finishing works are ongoing on the project.

05 November 2014

*Gulf General Investment Co - Residential Building At DSC (Plot No:R-8-6) Currently the project is in finishing stage and around ninety percent of the construction work is Complete.The project is expected to get completed by December 2014.

05 November 2014

*Emirates NBD - Dubailand: Motorcity : Hotel The $150m project is on hold and its revival date is yet not known.

27 October 2014

*Al Madar - Dubailand: Siraj Tower Structural works are complete and currently finishing works are ongoing on the project. The project is expected to be complete in March 2015.

27 October 2014

*Ajmal Real Estate - Dubailand: Ajmal Sarah Tower (Plot No: RC-A-001) Construction works have progressed by 98 per cent and currently only minute maintenance works are ongoing on the project. The project is expected to be complete in November 2014.

27 October 2014

*Union Properties - Dubailand: The Ribbon Mall Foundation works are almost done and the superstructure works are ongoing on the ground floor.The project is expected to get completed by March ,2015.

21 October 2014

*SOL Properties - Bloomingdale In Dubai Sports City Construction works are ongoing on the project and are expected to be complete in January 2015.

20 October 2014

*Dubai Sports City - Canal Residence West: Phase 1: (Plot no: 6821402) Construction works on Classic European Tower and Mediterranean Tower is complete. Finishing works on Venetian Tower is ongoing and is expected to be complete in December 2014.

04 September 2014

*Dubai Municipality - Dubailand: Sewer Network & Pressure (DS 190/3) Finishing works are ongoing and the project is expected to complete in November 5, 2014.

29 August 2014

*I&M Galadari Group - Dubailand: Monorail System (City of Arabia) The $136m project is still on hold and its revival date is still unknown.

19 August 2014

*Ajmal Real Estate - Dubailand: Ajmal Sarah Tower Finishing works are ongoing and the project is expected to complete in October 2014.

07 August 2014

For package Al Barakah - Dubailand: Majan: Le Stelle - The project is still on hold. However the time frame for revival has not been decided yet.

04 August 2014

For package Dubai Sports City - Canal Residence West: Phase 1: (Plot no: 6821402) - Finishing works are ongoing and are expected to be completed by October 2014. Also for package Shaikhani Group - Dubailand: Dubai Sports City: Frankfurt Sports Tower 1 - Finishing works are ongoing & the entire project is expected to be completed by November 2014.

23 July 2014

Package Dubai Holding - Dubailand: Tijara Town - The project is still on hold. However the time frame for revival has not been decided yet.

18 June 2014

Condor Group is appointed as a main contractor on the "Dubai Holding - Dubailand - Mudon Retail Centre" project. The project is expected to be complete in Q1 2015.

20 January 2014

Industry sources indicate that for the project "Al Madar - Dubailand: Siraj Tower", the construction works are in progress. For the project 15th to 16th floor columns and core walls are in progress with the slab works completed till 15th floor, 50 per cent block work has been completed.

21 August 2013

A company active on the project "Rufi Real Estate - Dubailand: Dubai Sports City: Rufi Twin Towers", quoted that almost 55 percent of the construction works have been completed and the project is likely to be complete by Q3, 2014 as the construction works are progressing very slowly.

09 July 2013

A company active on the Frankfurt : Sports Tower 1 project quoted that construction works are ongoing and are 55 per cent complete.

04 June 2013

A company active on the project quoted that the construction works on the Rufi waterfront project are on going and expected to finish by Q4 2014.

30 May 2013

A company active on the project quoted that construction on the Dubailand: Dubai Sports City: Chess Tower project is 35 per cent complete and expected to complete by December, 2014.

30 May 2013

A company active on the project quoted that construction on the Ajmal Sarah tower project is ongoing and expected to complete by December, 2013

17 December 2012

Industry sources indicate that construction works are ongoing on Rufi Century Tower and Dubai Lifestyle City, whereas finishing works are ongoing on Remraam and Rufi Twin Towers.

28 September 2012

Industry sources indicate that construction works are ongoing on Rufi Century Tower and Dubai Lifestyle City, whereas finishing works are ongoing on Remraam and Rufi Twin Towers.

03 June 2012

Industry sources indicate that structural works are ongoing for siraj tower project, while finishing works are ongoing for remraam project. So far most of the projects in dubailand are kept on hold.

04 March 2012

Most of the projects in dubailand are on hold; while a project callled as Remraam's construction works is in its final stages with few project such as Eden Garden , Wadi Walk, Palmarosa, Madison Residency, Platinum I & II Ajmal Sarah Tower and Lincoln Park construction works are ongoing. The client has plans to revive the Al Sahra desert resort project by 2013.

29 April 2010

On 23 October 2003, Tatweer, a division of Dubai Holding announced the world’s most ambitious tourism, leisure and entertainment project, “Dubailand” in Dubai. Designed to catalyse the position of Dubai as an international hub of family tourism, the development will cover an area of about three billion square feet (sq ft) which will include 45 mega projects and 200 sub projects. Dubailand is the divided into six zones also called world which are as follows: *Attractions and Experience World *Sports and Outdoor World *Eco-Tourism World *Themed Leisure and Vacation World *Retail and Entertainment World *Downtown Dubailand will be twice the size of Walt Disney World Resort, and will be the largest collection of theme parks in the world. On completion Dubailand will have a population of 2.5 million people, including tourists, workers and residents. It will expect about 40000 visitors a day.