MAF - Riyadh North Development: Mall of Saudi
Majid Al Futtaim (MAF) is planning to construct a shopping mall called " Mall of Saudi" located in Riyadh, Saudi Arabia.
Mall of Saudi which is expected to house over 600 stores across 300,000 m2 gross leasable area, is an integrated lifestyle destination that will host the largest ski slope and snow park in the Middle East.
The US$1,600 million project includes the following:
1. Construction of the mall
2. Development of snow park (26,000m2)
3. Development of ski slope
4. Construction of 31 VOX Cinema screens
5. Construction of IMAX
6. Construction of Magic Planet
7. Construction of restaurants and entertainment areas
8. Construction of parking facilities
9. Construction of temporary site office building
10. Earthworks
11. Site Preparatory works
12. Construction of associated facilities
Second Section
No Content
No Content
21 February 2024
The project continues to be on hold.
08 December 2023
The project continues to be on hold.
05 September 2023
The project continues to be on hold.
04 May 2023
The project has been placed on hold.
05 April 2023
The construction works are progressing on the Main Package.
29 November 2022
The JV of El-Seif Engineering Contracting Company and Alec has been awarded as the main contractor on the Riyadh North Development: Mall of Saudi : Main Package.
08 August 2022
The revised bids have been submitted on the Riyadh North Development: Mall of Saudi : Main Package.
29 June 2022
Mall of Saudi Early Works Package is nearing completion.
26 May 2022
The main contract is expected to be awarded in June 2022 for the Mall of Saudi Main package
24 February 2022
Majid al-Futtaim (MAF) has received bids to build for the Riyadh North Development: Mall of Saudi : Main Package. The bidders include Egyptâs Orascom, UAE headquartered Arabian Construction Company (ACC), and the local Saudi Constructioneers (Saudico); the local El-Seif and Alec; and Indiaâs Shapoorji Pallonji, UAE-based Unec, and the local Al-Rashid Trading & Contracting Company (RTCC). (Source: MEED)
13 January 2022
El Seif Engineering Contracting is no longer involved as foundation contractor on the project.
16 November 2021
Modern Building Leaders (MBL) is the main contractor appointed for the early works package and construction works have commenced.
01 June 2021
AECOM has been appointed as the lead consultant for the project. AECOM will be responsible for providing lead consultancy services for pre-contract and post contract construction supervision. Mace International is the PMC Consultant and Turner Construction is the Contract administrator for the project.
11 May 2021
The client has invited bids for the project management consultancy services contract. (Source: MEED)
20 April 2021
Design works are progressing at slow pace.
14 September 2020
The design works are ongoing at a slow pace.
30 July 2020
The design works are ongoing and the time frame for its completion is yet unknown.
14 May 2020
The design works are ongoing at a slow pace due to the current situation in the region.
05 March 2020
The conceptual design works are completed.
17 January 2020
The conceptual design works are progressing and overall the project is expected to complete by 2024.
26 December 2019
It is understood that the project is still under design stage. (Source: MEED)
24 June 2019
The client is re-working on the design of the project and it is expected to be completed by Q4 2019.
07 March 2019
The client is planning to re-tender the project (*). (Source: MEED)
10 February 2019
The main contract bid submission date has been extended to May 2019.
08 October 2018
The main contract tender has been issued and the bid submission is expected in early February, 2019. It is understood that the following companies among others have been invited. *TAV / Nesma & Partners JV *Salini Impregilo / Larsen & Toubro JV *Arabian Construction Company / Orascom Construction JV *Consolidated Contractors Company / El Seif Engineering Contracting JV
10 July 2018
The project is expected to be tendered by the end of October, 2018. (SOURCE : MEED)
11 June 2018
The schematic designs are ongoing on the project. The main contract tender has not yet been issued.
15 March 2018
The schematic designs are ongoing on the project. The main contract tender will be issued by the end of 2018.The enabling works contract has not yet been tendered.
17 January 2018
The main contract tender is expected to be issued by the third quarter of 2018.
07 November 2017
The concept designs are completed and the schematic designs will commence soon.
18 September 2017
The project is still under design stage.
25 July 2017
The project is still under design stage.
20 April 2017
The project is currently under concept design approval stage.
10 January 2017
The designs are ongoing on the project and are expected to be complete by Q 4 of 2017
17 October 2016
The lead consultant carrying out the main engineering & multi disciplinary design is Khatib & Alami. Callison is the Architect on the project
11 October 2016
The detailed design works are currently underway. Overall design work will get complete by 2017.
04 August 2016
The design work has commenced on the project. Callison is the design consultant on the project.
04 May 2016
Master planning is progressing for the project. *Architect - Callison
09 February 2016
The construction works on the project is expected to start by mid-2017 and will be completed by 2022.