NEOM - NEOM City: Infrastructure and Utilities
NEOM is undertaking the construction of a project named NEOM which stands for 'New Future' in Tabuk city, Saudi Arabia.
This package is for infrastructure works.
The US$10,000 million project includes the following:
1. Infrastructure works
2. Construction of roads and parking network
3. Construction of bridges and underpasses
4. Installation of power distribution and street lighting network
5. Construction of Irrigation facilities
6. Construction of district cooling
7. Construction of water distribution
8. Construction of gas networks
9. Construction of gardens
10. Construction of sewage systems
11. Civil works
12. Installation of telecommunications networks
13. Development of landscape
14. Construction of associated facilities
Second Section
No Content
No Content
17 April 2024
NEOM City: 132/33kV NIC NR & EV2 Substation: Nesma Infrastructure & Technology has been appointed as the main contractor.
05 February 2024
SFSP Main Centre Building 1 - the construction works are progressing on the project
13 October 2023
The construction works are ongoing on the Air Traffic Control Tower: Earthworks.
15 June 2023
The main contract bids are under evaluation on SEC - NEOM City: 132/33kV NIC NR & EV2 Substation.
18 April 2023
132kV Double Circuit OHTL Between PSSA and PSSB Substations: The Main contract bid submission has been extended to May 10, 2023.
30 March 2023
132kV Double Circuit OHTL Between PSSA and PSSB Substations: The Main contract bid submission has been extended to April 4, 2023.
30 January 2023
NEOM City: Magna Storage Reservoir: TAQ Consulting Engineering Company is working as a consultant on the project.
08 December 2022
The construction works are ongoing on the NEOM City: Water Supply Facilities project.
04 December 2022
Magna Storage Reservoir: The main contract bids have been submitted and al yamama amongst others has submitted the bids.
29 September 2022
PSS A & PSS B 132/33kV Substations: Construction works have progressed up to 20 percent and are expected to be completed by November 2023.
02 August 2022
The main contract tender has been issued with a submission due on September 08, 2022 for the NEOM City: Magna Storage Reservoir project.
21 July 2022
NEOM Area Truck Service Center package continues to be on hold due to some internal issues.
13 January 2022
Mohammed Al Ojaimi Contracting has been appointed as the main contractor for PSS A & PSS B 132/33kV Substations.
09 December 2021
The main contract bids are under evaluation and Nesma Telecom and Technology has emerged as the lowest bidder for 132/33kV NIC NR & EV2 Substation.
20 October 2021
The client has invited international companies to submit their proposal to prequalify for the contract to provide PMC services on the project. It is understood that these companies include Aecom, Atkins, Egis, Hill International, Jasara, Parsons, Systra, WSP for the International Airport package. (Source: MEED)
06 July 2021
The client has started the procurement process for water utilities packages for various zones in the project. (Source: MEED)
23 May 2021
Construction works are ongoing on Sharma to Tabuk Road Upgrade.
03 February 2021
The PQ document for the Cut and Cover Tunnel Section, Drill and Blast Section, and Tunnel Section Excavation has been submitted and the shortlist is awaited.
26 October 2020
The following companies amongst other are invited to submit the PQ documents for Backbone Infrastructure package: L&T, Hyundai E&C, Itinera, Samsung C&T, Salini, and FCC along with a few local contracting firms for the cut and cover tunnel section, one simple excavation tunnel section, and one drill and blast section works.
16 September 2020
Aecom has been appointed as the design consultant for the Neom: Backbone Infrastructure. The scope also includes environmental and geotechnical support.
13 August 2020
The construction works on NEOM: Residential Buildings Site Preparation works is ongoing and the time frame for its completion is yet unknown.
05 April 2020
Construction works for the RO Plant at the Duba project are completed.
28 January 2020
The construction works have not yet started for the Residential Buildings Site Preparation works.
27 December 2019
The main contract has been awarded to Al Tamimi & Company and Saudi Arabian Trading and Construction Company (SATCO) for the Residential Buildings Site Preparation works.
05 September 2019
Construction works are ongoing for RO plant at Duba and early production unit of capacity 50,000m3 is expected to be commissioned on September 27, 2019.
29 July 2019
Construction works are ongoing for RO plant at Duba
24 April 2019
Metito has been awarded the main contract for RO Plant at Duba.
14 March 2019
Neom: RO Plant is under the main contract bid evaluation. AECOM has been appointed as the project management consultant on the project. (Source: MEED)
18 November 2018
Environmental study assessments on the project were ongoing construction works are expected to commence in 2019 and completed by 2025.
26 August 2018
The client is developing the master plan and undertaking environmental assessments on the project.
21 May 2018
Orascom Development Egypt (ODE), subsidiary of Orascom Development Holding AG are keen in investing in the development of NEOM City. Italian construction company Salini is interested in the future tenders for the infrastructure works on the project.
20 December 2017
The project is in very initial stage.
30 October 2017
The client is in talks with potential investors on the project.