NAT - High Speed Rail Network: Luxor-Hurghada Railway Line (Phase 3)

General Information
Owner National Authority for Tunnels (NAT)
Masterplan Project (Parent Profile) NAT Egypt – High Speed Rail Network – Suez
Location Luxor, Luxor Governorate, Egypt
Status --
Sector Transport, Infrastructure, Railway
Contract Type Design Build (DB)
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 53
Estimated Budget Value ---
Contract Value 2000
Net Value $2000m
Award Date May 2022
Completion Date December 2025
Last Updated On March 2024
ProjectId (Old, New) 20576, 247197


National Authority for Tunnels (NAT) is undertaking the construction of a two-way electrified railway line from Luxor to Hurghada in Egypt.

The length of train lines extending from Luxor to Hurghada comprising 225km. The design speed of line is 250 km/h for passenger trains and 120 km/hr for freight trains. The project is also known as "Red Line". The will have 4 stations, 2 express train stations and 2 regional stations (East Sohag - Hurghada - Sahl Hasheesh - Safaga)

The US$3000 million project includes the following:

1. Laying of new tracks 225 km

2. Construction of Luxor-Qena new line

3. Rehabilitation of Qena-Safaga line

4. Construction of Safaga-Hurghada new line

5. Construction of 4 stations (2 express train stations and 2 regional stations)

6. Construction of associated works

Second Section

12 March 2024

Construction works are progressing on the project.

09 December 2023

Construction works are ongoing on the project.

18 September 2023

The construction works are progressing on the project as per schedule.

05 June 2023

The construction works are progressing on the project.

03 March 2023

Construction works are ongoing on the project as per schedule.

20 October 2022

Construction works are progressing on the project and the timeframe for completion is unknown at this juncture.

01 June 2022

The consortium of Siemens Mobility, The Arab Contractors and Orascom Construction has appointed as the main contractor on the project.

19 May 2022

The consortium of Siemens, The Arab Contractors and Orascom Construction is still negotiating and the official signing is expected to be done by end of May 2022

04 April 2022

The client is still negotiating with Siemens lead consortium for the main contract award. (Source: MEED)

20 March 2022

The client is in talks with consortium comprising Siemens, The Arab Contractors and Orascom Construction to finalize the contract on the project. Currently technical and financial evaluation is ongoing. It is understood that Siemens will do signaling and communication systems and supply rolling stock while The Arab Contractors and Orascom Construction will do civil and construction works.

09 January 2022

The main contract tender is expected to be issued by the first quarter of 2022. (Source: MEED)

22 September 2021

Design works are progressing on the project.

23 June 2021

Design works are ongoing on the project.

29 December 2020

The project is still in the early stages of development and listed under Egypt's futuristic development plan.

01 December 2020

The project is still in the early stages of development.

01 August 2020

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

29 May 2020

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

07 February 2020

The project is in early stages of development.

20 August 2019

The client is planning to speed up the implementation of the project.

11 April 2018

The feasibility studies are ongoing on the project

11 January 2018

The authority has received offers from four international companies to develop the project. Egyptian Phosphate Company is preparing the feasibility study for the project.

14 December 2017

The project is still in the planning stage & will take four years to develop.

27 September 2017

The project is in initial planning stage.

23 May 2017

The project is in planning stage.

23 February 2017

The project is in initial planning stage.

23 November 2016

Feasibility study will commence in January 2017.

23 August 2016

The client is looking for investors to finance the project.

05 May 2016

The project is in its early study stage and financial discussions are underway with some Chinese and Spanish companies.

29 January 2016

The client is negotiation with the World Bank to finance the project.

26 October 2015

The project is still in study stage.

30 August 2015

The client is still in discussions to appoint the consultant.

20 August 2015

Hamza Associates has conducted topographic, hydrological and environmental studies on the project.

20 July 2015

The client is considering to appoint Spanish Ineco as a consultant on the project. However the final decision not taken yet.

07 April 2015

The project is in very initial study stage. The ministry of transport has presented the project to international investors and developers in the economic summit in March 2015. The implementation on the project is expected to start after 2 years. The project is a part of mega transport development in Egypt estimated to complete in 2030.

07 January 2015

The feasibility study is ongoing on the project.

30 September 2014

The project is in initial study stage. The project’s costs are yet to be determined.

12 June 2014

The economic pre-feasibility study is in early stage.