LREDC - Lusail Development

General Information
Owner Lusail Real Estate Development Co
Masterplan Project (Parent Profile)
Location Lusail, Al Daayen Municipality, Qatar
Status --
Sector Construction, Mixed-Use, Mixed-Use
Contract Type Build
Onshore/Offshore Onshore
Greenfield/Brownfield Greenfield
Progress 81
Estimated Budget Value ---
Contract Value 0
Net Value $7267m
Award Date January 2006
Completion Date August 2028
Last Updated On April 2024
ProjectId (Old, New) 9757, 129656


Lusail Real Estate Development Co (LREDC) is undertaking the Lusail Development project in Qatar.

The US$45,902 million project includes the following:

1. Construction of Marina District

2. Construction of Qatar Entertainment City

3. Construction of Fox Hills

4. Construction of Energy City 1 and 2

5. Construction of Entertainment Island Waterfront

6. Construction of Seef Lusail Waterfront

7. Construction of Lusail Towers

8. Construction of Qetaifan Island

9. Construction of Al Kharaej Towers

10. Construction of Northern Residential district

11. Construction of Gulf district

12. Construction of commercial boulevard

13. Construction of associated facilities

Second Section

15 April 2024

For the Lusail Plaza 4 Tower Fit Out Works package: The construction works are yet to commence on the project.

06 March 2024

Lusail Development: Seef Lusail: A1 (BP-25-09): The construction works are progressing and completion is expected by Q4, 2024.

28 January 2024

Lusail Development: Lusail Plaza Tower III And IV: The construction works have been completed on the project.

03 January 2024

There is no news on the main contract tender issue yet on the Lusail Development: Lusail City Landscape Works package.

26 December 2023

Infrastructure: Package CP07B : Construction works are ongoing on the project and are expected to be completed by March, 2024. QIMC Tower (Plot no. 60080006): The construction works are ongoing and the project is expected to be complete by the second quarter of 2024.

12 December 2023

The main contract for the Lusail Development: Foxhills Residences (E-02) package is yet to be awarded.

21 November 2023

The construction works are ongoing on the Residential Building (Plot No: D54) package and likely to complete by February 2024.

03 October 2023

The bids are under evaluation for the Foxhills Residences (E-02) project and Shannon Engineering and Al Huda Engineering Works have submitted the bid.

27 September 2023

Energy City: Office Building (Plot No. ECQ-E07): Finishing works are ongoing on the project and expected to be completed by December 2023.

05 September 2023

Lusail Development: QIMC Tower (Plot no. 60080006) : Construction works are ongoing on the project as per the schedule.

31 August 2023

The main contract tender is issued for the Lusail Development: Foxhills Residences (E-02) project and the bid submission date is September 03, 2023. Amongst others, Al Sraiya Trading and Contracting Company is likely to submit the bid. Quantex Qatar is the consultant on the project.

21 August 2023

Infrastructure: Package CP07B : Finishing works are still ongoing on the project and is expected to be completed by December 2023.

07 August 2023

Lusail City School in Lusail: The construction works are ongoing on the project as per the schedule.

28 July 2023

Lusail Development: Seef Lusail: A1 (BP-25-09) : The construction works are ongoing and the project is expected to be completed by the fourth quarter of 2023.

10 July 2023

Lusail Development: Marina District : Iconic Development: External Landscaping Works - The main contract is not yet awarded and expected to be awarded by the end of July 2023.

14 June 2023

Lusail City School in Lusail : Cold star trading and contracting company is working as the MEP contractor for the project and the construction works are ongoing and the project is expected to be completed by Q2, 2025.

30 May 2023

Qetaifan Island North: Phase 1: Package 5 Rixos Doha Qetaifan : Finishing works are still ongoing and expected to be completed by 2023.

14 May 2023

Al Erkyah: Hotel and Residential Tower : The construction works are ongoing and expected to be complete by December 2023.

11 May 2023

Energy City: Office Building (Plot No. ECQ-D-25) : The Finishing works are ongoing on the project and expected to be completed by the end of July 2023.

05 May 2023

Seef Lusail: A4, B1, C2 & C3 (BP-25 -12) and Seef Lusail A3b & D5 (BP-25-11) : The project is completed.

03 May 2023

Marina District: Nishan Tower (COM 019) : Finishing works are ongoing and expected to be completed by June 2023.

02 May 2023

Lusail Development: Al Kharaej Towers: The construction works are completed.

26 April 2023

Lusail Development: Infrastructure: Package CP07B : Finishing works are still ongoing on the project as per the schedule and the Lusail Development: Golf Land Project project is still on hold.

12 April 2023

Infrastructure works: Marina Mix-12: The project is still put on hold from the client's side.

12 April 2023

Fox Hills: Residential Building : The construction works are ongoing on the project.

07 April 2023

Lusail Development : Head Office Building (Plot No. C.6B) : The project is completed.

04 April 2023

Arkaz - Marina District: Rosewood Doha Hotel (Plot No. MIX 12 F) : Construction works are ongoing as per the schedule.

30 March 2023

Waterfront District: Residential Building (Plot No: Res 04) : Construction works were expected to commenced in May 2023.

27 March 2023

Finishing works are still ongoing as per the schedule on the Qetaifan Island North: Phase 1: Package 3 Meryal and Qetaifan Island North: Phase 1: Package 5 Rixos Doha Qetaifan project : Finishing works are still ongoing and expected to be completed by end of Q2 2023.

20 March 2023

Lusail Development : Seef Lusail Waterfront (BP-25) : Head Office Building (Plot No. C.6B) : The finishing works are ongoing as per the schedule.

10 March 2023

Lusail Development: Marina District : Iconic Development : External Landscaping Works : - The main contract is not yet awarded and expected to be awarded next month

08 March 2023

LREDC - Lusail Development: Seef Lusail: C1, C4 & C5 (BP-25-07) : The project is completed.

06 March 2023

Lusail Development: QIMC Tower : The project has been put on hold and is expected to start by November 2023.

01 March 2023

Fox Hills: Residential Building (Plot No: D54) : construction works are ongoing as per the schedule.

28 February 2023

Finishing works are ongoing on Lusail Development: Infrastructure: Package CP07B

11 January 2023

We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.

27 December 2022

Construction works have been completed on the Fox Hills: Terrace Residential Building project.

26 December 2022

Finishing works are ongoing on Marina District: Iconic Development Package 2 and Package 5A.

01 December 2022

Construction works are ongoing on the Lusail Development: QIMC Tower project.

27 November 2022

The construction works on Lusail Development: Infrastructure: Package (CP07B) are progressing on the project.

03 November 2022

There is no news regarding the main contract tender issue yet on Fox Hills: Residential Building (RES F-10).

17 October 2022

The Lusail Development: Commercial Boulevard: Residential R2 (BP-18B-2) and Lusail Development: Commercial Boulevard: Financial Center (BP-18C-2) project has been delayed since 2016. Hence, we assume that the project did not materialize. The status of the profile, therefore, has been changed to cancelled. We will update the project accordingly if anything changes in the future.

06 September 2022

Fox Hills: Commercial and Office Building continues to be on hold and the time frame for its revival is unknown at this juncture.

23 August 2022

Construction works of Rosewood Doha Hotel are progressing and is expected to be completed by March 2023.

06 July 2022

Marina District: Tower One (WR-MIX/01) continues to be on hold and the time-frame for its revival is unknown at this juncture.

14 June 2022

Finishing works are progressing on the Lusail Development: Alar Hotel and the project is in the final stage of completion.

31 May 2022

Construction works on Energy City: Office Building (Plot No. ECQ-E07) has commenced.

28 April 2022

Construction work is ongoing as per the schedule on QIMC Tower (Plot no. 60080006), expected to complete by July 2022.

20 March 2022

The structural works are underway in Fox Hills: Main Works of Zones 1 & 2 of Wadi Al Sail Development

02 February 2022

Fox Hills: North J Dara (B-F) is still on hold and the expected time frame for the revival is unknown at this moment.

03 January 2022

Construction works on Qetaifan Island North: Phase I: Package III Water Park have been progressed up to 66 per cent and the project is expected to be completed by July 2022.

05 December 2021

Construction works on Marina District: Residential Building (Plot No. 021) have been completed.

21 November 2021

Lusail Development: Lusail Museum project has been cancelled.

01 November 2021

Construction works on Lusail Development: Lusail Plaza Tower 1 And 2 have been progressed up to 30 per cent and the project is expected to be completed by February 2023.

05 October 2021

Singapore Engineering & Contracting has been awarded the main contract for the Dar Al Sharq Headquarter Building project.

26 September 2021

Construction works have been progressed up to 60 per cent for Alar Hotel and the project is expected to be completed by April 2022. Residential Tower Al Kharaej (Plot No. Res-034) project is temporarily put on hold and is expected to be revived in November 2021.

30 August 2021

Seef Lusail A3 and CPC 07: Public Realm - the construction works are ongoing as per schedule.

27 July 2021

Skala Residential Tower (Mix-034) - Construction works are ongoing and the expected timeframe for completion is unknown.

23 June 2021

Qatar National Bank - QNB Tower in Lusail: Al Darwish Engineering has been appointed as the main contractor and construction works are ongoing.

30 May 2021

Qetaifan Islands South: Villa Infrastructure Work (CP08-A2): Construction works have been completed. Lusail Plaza Tower 1 And 2: Construction works are ongoing and the project is expected to complete by February 2023.

15 April 2021

Lusail Development: Residential Tower and Fox Hills: Residential Building (Plot No. RES F09) projects continue to be on hold and the time-frame for revival is unknown at this juncture. There is no news regarding the main contract tender issue for Lusail Development: CBD: Qatari Diar Headquarter Building (BP-17) project.

24 March 2021

There is no news regarding the main contract tender issue yet for Qetaifan Islands South 2 and 3: Villas & Apartment Blocks (BP21) project and Lusail Museum project continues to be on hold and the time-frame for revival is unknown at this juncture.

14 February 2021

Construction works on Commercial Boulevard: Infrastructure (CP07-C-1B) project and Lusail Plaza Towers: Enabling Works project have been completed. Construction works on Marina District: Iconic Development: Package 4C are ongoing and the project is expected to be completed by December 2021.

15 January 2021

Qetaifan Islands South: Villa Infrastructure Work (CP08-A2): Construction works have been progressed up to 95 per cent and the project is expected to be completed by April 2021. Qetaifan Islands South: Spine Road Infrastructure (CP08-A1): Construction works have been progressed up to 98 per cent and the project is expected to be completed by February 2021.

18 December 2020

Qetaifan Island North: Phase 1: Package 5 Rixos Doha Qetaifan: Accor has signed an agreement with Qetaifan Projects Company to manage the project and Qetaifan Island North: Phase 2: Villas project is in the initial stages of development. The Seef Lusail: A2 (BP-25-06) project continues to be on hold and the time-frame for its revival is unknown at this juncture.

18 November 2020

Qetaifan Island North: Phase 2B: Marine Works: Construction works have been completed.

16 October 2020

Design works on Qetaifan Island North: Phase 1: Package 7 Juma Mosque have been completed. Qetaifan Island North: Phase 2B: Marine Works: Construction works are nearing completion. Construction works on Commercial Boulevard: Infrastructure (CP07-C-1B) are ongoing and the time-frame for its completion is unknown at this juncture.

25 September 2020

Construction works on Energy City Qatar: HBK Contracting Headquarters are ongoing as per the schedule.

06 August 2020

Construction works are ongoing as per the schedule on the Fox Hills: Residential Building (Plot No. RES A025).

12 July 2020

GREC - Waterfront District: Residential Tower has been put on hold and the time frame for the revival is unknown at his juncture.

01 May 2020

The Pride Projects has been appointed as the main contractor on Fox Hills: Residential Building (Plot No. RES/A08).

30 March 2020

Construction works have been completed on the Fox Hills: Residential Building(Plot no.A038) and The construction works are facing delays on West District Cooling Plant Phase I.

19 February 2020

The main contract bid submission has been extended to March 8, 2020, for Lusail Development: Hotel Fit-Out Works (Package 4B).

02 February 2020

Qatar National Bank: Iconic Tower has been put on hold.

02 January 2020

The construction works are ongoing for the Mixed-Use Development in Lusail (Plot No.MIX 12F).

24 November 2019

The following companies have submitted the main contract bids on the Lusail Plaza Towers PI and PII – Qatar: UrbaCon Trading & Contracting, HBK Contracting, Midmac Contracting, Redco Construction - Almana, Construction Development Company, Renaissance Construction, TAV Construction, QDVC, and Al Jaber & Partners.

21 November 2019

The construction works are ongoing on office building (Plot No FV9) and it is expected to complete by the first quarter of 2020. The main contract tender has not been issued on Commercial Boulevard: Residential packages R1 (BP-18B-1), R2 (BP-18B-2), BP-18C-2, BP-18C-1.

01 November 2019

The construction works are progressed up to 80 per cent on Infrastructure: Package CP07B and it is expected to complete by the fourth quarter of 2020.

11 October 2019

Arab Engineering Bureau (AEB) is working as the consultant for QIMC Tower and the design works are ongoing.

03 September 2019

There is no news from the client regarding the main contract award of Residential Tower Plot No: RES 27.

05 August 2019

Seef Lusail: A2 (BP-25-06): Urbacon Trading and Contracting has been awarded as the main contractor on the project.

02 August 2019

Seef Lusail: A2 (BP-25-06) continues to be on hold.

02 August 2019

Redco Construction – Almana has been awarded the main contractor on the packages C1 BP-18A-1, C1 BP-18A-2, and BP18A.

31 July 2019

The construction works are ongoing on West District Cooling Plant Phase I.

24 July 2019

The main contracts prequalification bids are still under evaluation on Phase 2B: Marine Works. The main contract bids are still under evaluation for Fox Hills: Residential Building (Plot No. RES/A08) and Mixed-Use Building (MU/C07).

10 July 2019

Al Shareef Enterprises - Fox Hills: Residence (Plot No.N27) - The construction works are underway and the project is expected to complete by the third quarter of 2019.

11 June 2019

Lusail Development: Fox Hills: North J Dara (B-F): the project is kept on hold.

29 May 2019

Construction works have been completed on the Al Meera Lusail Supermarket project.

16 May 2019

Group For Wooden Industries has been appointed as the main contractor for the Hotel Fit-Out Works (Package 4a).

29 April 2019

QPC has signed a memorandum of understanding with the Rixos Hotels to manage and operate the hotels, the souq, the water park and the beach club in the Qetaifan Island North project.

27 March 2019

The main contract bids are under evaluation for the main contract on Fox Hills : North J Dara (B-F) project and Finishing works are underway on Al Okar Tower.

05 February 2019

Finishing works are underway on Al Okar Tower

12 December 2018

Design works are still underway on the QIMC Tower project

06 November 2018

*Nozul Real Estate - Marina District : Mixed Use Building - The project continues to be on hold.

06 September 2018

*Al Fardan Real Estate - Burj Al Fardan : - Finishing works are ongoing on the project and it is expected to be complete by Q4 2018.

08 June 2018

*Private Developer - Lusail: Fox Hills Residential Building (Plot RES A-24): As per site visit on May 23, 2018 reveals that structural works are ongoing on the third floor.

05 March 2018

Private Developer - Lusail: Fox Hills Residential Building (Plot no C16) : The project is complete.

01 March 2018

Private Developer : LREDC - Residential Building (Plot No.Marina Res-009) : Site visit on December 23, 2017 reveals that the finishing works have commenced on the project and block works are progressing simultaneously.

12 February 2018

Private Developer - Al Okar Tower : The civil works on the project has been completed. Internal Plastering works are now on going on the project.

01 February 2018

Qatari Diar:Neighbourhood Retails ( Plot No NRV RET-02 ) - Site visit on December 24, reveals that the structural works are on going on the first floor.

12 January 2018

*Al Meera - Al Meera Lusail Supermarket : Site visit as per December 24, 2017 reveals that the structural works have commenced on the ground floor. *LREDC - Marina District East, South and North Promenades Public Realm : As per site visit on December 24,2017 construction works are ongoing on the project. *Private Developer - Foxhills Residential Development Plot No D-21 : Site visit on December 24, 2017 reveals that the structural works have commenced on the fourth floor.

09 October 2017

*Private Developer - Entertainment City: Residential Building - (Plot No: C6): As per site visit on August 13, 2017 reveals that structural works are completed and block work has commenced on the project.

12 July 2017

*Al Shareef Enterprises - Fox Hills Residence N27 : Finishing works are still ongoing on the project and overall project is expected to be complete by December 2017.

01 June 2017

Infrastructure: Design Package VI : The project is complete.

05 March 2017

It is understood that overall, 80 per cent infrastructure works are complete.

06 February 2017

LREDC - Lusail Development - Infrastructure: Design Package VI : The construction works for 3 to 4 bridges are completed however construction on remaining bridges are ongoing and expected to be complete by end of 2017.

06 February 2017

LREDC - Lusail Development: Infrastructure: CP5B : The project has progressed upto 98 per cent and expected to be completed by end of March 2017.

06 February 2017

LREDC - Lusail Development - Infrastructure: Design Package 3A : The construction works are ongoing on the project and expected to be completed in 2018.

07 December 2016

* LREDC - Lusail Development : Lusail Plaza Towers (4 nos.) : The design works are underway and the tenders for the main contract are expected to be issued between Q1 and Q2 of 2017.

06 October 2016

Al Merqab Real Estate - Lusail Fox Hills Housing Complex - As per site visit on September 14th,2016 finishing works are ongoing on the project.

19 September 2016

*LREDC - Lusail Development: Infrastructure: CP4 The project is almost complete.

27 May 2016

It is anticipated that the infrastructure is likely to complete by 2018.

21 March 2016

*Earthworks Subcontractor: Emdad Holding for CP5B

25 November 2015

*Barwa Real Estate Company - Lusail Development: Dara : Phase 2 (B-F) The project was on hold recently; however, the project has revived. The client has requested re-design due to certain modification works.

23 July 2015

*QDREIC - Lusail Development - Infrastructure: Design Package 3A Works are around 75 per cent complete and the project is expected to complete by March 2016. *QDREIC - Lusail Development - Infrastructure: CP6B Works are about 79 per cent complete and the project is scheduled for completion in April 2016.

09 July 2015

*QDREIC - Commercial Boulevard (CP07-C-1B) MACE (Mechanical and Civil Engineering) have been awarded the MEP contract

30 June 2015

*QDREIC - Lusail Development - Infrastructure: CP5B Works on the project are still ongoing and timeline for completion has been extended. The project is now scheduled to be completed by end of August 2015.

22 June 2015

*Real Estate Services Group - Lusail Development: Commercial 5 No MEP contractor has been appointed yet. The project was expected to complete by end of 2016, however it is likely to get extended.

11 June 2015

*QDREIC - Lusail Development - Infrastructure: CP5B The major road works in the project are complete and the smaller service roads are scheduled to complete by the end of June, 2015.

01 June 2015

*Qatari Diar - Lusail Development : Commercial Avenue : Enabling Works The project is complete.

22 April 2015

*QDREIC - Lusail Development - Infrastructure: CP4 The construction work on this project is ongoing and is expected to be completed by December 2015.

11 March 2015

*Qatari Diar- Lusail Development : Residential Building(Marina Rest./18) Site visit on March 11, 2015 revealed that the structural works on the project is complete.

31 December 2014

*Qatari Diar- Lusail Development : Residential Building(Marina Rest./18) Site visit on December 10, 2014 revealed that the construction works on the superstructure are complete.

22 December 2014

*QDREIC - Lusail Development - Infrastructure: CP4 The project is expected to complete by June 2015. The landscaping work is not included in the contractor's scope of work. The client, Aspire Zone Foundation would be appointing a subcontractor separately for the same.

10 December 2014

*Al Shareef Enterprises - Foxhills Residence D27 Construction works are ongoing on the project and are expected to be complete in September 2015.

10 December 2014

*Al Shareef Enterprises - Foxhills Residences D23 Construction works are ongoing on the project and are expected to complete in September 2015.

10 December 2014

*Al Shareef Enterprises - Foxhills Residence D16 & 19 (Permit No.6693 Lusail) Construction works are ongoing on the project and are expected to be complete in September 2015.

09 December 2014

*QDREIC - Lusail Development: Waterfront Commercial District (Northern Area) Construction works have progressed upto 31 per cent and the project is expected to complete by October 2015.

04 December 2014

*Marafeq Qatar: Lusail Development District Cooling Plant: Phase 1 Works on the project have progressed upto 50 per cent and expected to complete by June, 2015.

28 October 2014

The CP7B project is expected to be awarded by January 2015.

04 September 2014

Shapoorji Pallonji has been shortlisted on the Marina mall project.

12 August 2014

The Burj Marina project is expected to complete by December 2014.

07 August 2014

The Lusail Development: Blues Tower project is still on hold.

16 June 2014

Preliminary works are ongoing on Lusail Development: Waterfront Commercial District (Northern Area) project.

20 February 2014

The Lusail Development: Waterfront Commercial District Northern Area has been awarded to Al Jaber Engineering and they are the front runner for the Southern Area as well.

01 October 2013

Industry sources indicate that indicated that the tender document has been issued for the Lusail Development: Waterfront Commercial District project and the bid submission is on November 4th, 2013.

14 May 2013

Industry sources indicate that the infrastructure tenders have been issued for the Lusail waterfront commercial district project.

28 March 2013

A company active on the project quote d that study is ongoing on Lusail Mix 11 where as works are 60 per cent complete on Burj Marina project.

27 December 2012

Construction works on Piazza I & II is in its finishing stage.

18 September 2012

A company active on the project quoted that the project is scheduled to be completed by 2019.

19 April 2012

Dorsch Gruppe has been awarded a contract for construction supervision consultancy services for the Lusail City development quoted by arabian business dtd April 18, 2012.

22 March 2012

Abu Dhabi Investment House (Adih) are the major shareholders on the project. DP Architects has been appointed the master planner.

03 February 2012

Infrastructure works are Burj Marina project are under execution while many other projects are still under the design stage.

19 October 2010

*Marina Mourjan Marinas IGY has been awarded for design, construct and operate work on the first marina which includes 96 modern floating marina berths, suitable for yachts of 10m to 40m in length, three on-water lounge areas, a shisha café, a juice bar and a family lounge area. (31/12/2010) *Budget The overall investment on the project will be between $30000m to $45000m.

07 May 2010

The Lusail project has been divided into the following districts:- -Marina District -Qatar Entertainment City -Fox Hills -Energy City 1 & 2 -Entertainment Island Waterfront -Commercial -Lusail Towers -Qetaifan Island -Al Kharaej Towers -Northern Residential district -Waterfront Residential -Gulf district -Commercial Boulevard *Associated facilities

29 April 2010

Qatari Diar Real Estate Investment Company has embarked on a major real estate development called the Lusail Development. Lusail is the most strategic remaining piece of waterfront land north of the capital. The development which is a meticulously planned fusion of living environments and communities will grow and prosper among wide open spaces. There project includes many parks, beaches and recreational areas. The Lusail project has been divided into the following Districts:- -Marina District -Qatar Entertainment City -Fox Hills -Energy City 1 & 2 -Entertainment Island Waterfront -Commercial -Lusail Towers -Qetaifan Island -Al Kharaej Towers -Northern Residential district -Waterfront Residential -Gulf district -Commercial Boulevard