ADNOC Onshore - ASAB SIWAP EOR Pilot Project
ADNOC Onshore is planning to undertake the construction of construction of SIWAP EOR Pilot project at ASAB field, the UAE.
(Tender No: 17700)
The scope of work is briefly categorized into the following areas:
1. ASAB Pilot Area & Wellhead Tie-In
2. RDS-5
3. Pipeline & Crossing
4. OHL
The scope of construction includes Earth Works, Civil works, Structural steel works, Mechanical works, Piping works, E&I Works and Telecom works for the project facilities including modification of existing facilities.
The US$50 million project includes the following:
A. ASAB Pilot Area & Wellhead Tie-In includes the following:
1. Installation of a new polymer injection skid
2. Installation of a new power supply skid (PSS) shall be provided to feed the loads located within the ASAB SIWAP EOR Pilot Facilities area. The PSS shall be fed through OHL. Proposed Tee-off line, single circuit type, from exiting OHL LINE #5 & 6 (TRUNK LINE circuit 6) to supply new polymer injector water supply well
3. Construction of new water supply wells (WSW) with ESP / power supply Skid (The ESP and the Power supply skid are Free issued Material From ADNOC Onshore)
4. Construction of a new disposal well
5. Construction of a new Polymer injection well
6. Converting Observer well to new pilot oil producer (SIWAP-01). SIWAP-01 will be routed to existing M-102 in RDS-5 via a 900# flow line. To connect SWIAP-01 to RDS-5 one slot on RDS-5 shall be made available by sharing of existing SB-328 and SB-159
7. Installation of chemical Packages (Scale/Corrosion inhibitor package)
8. Installation of wellhead control panel(s) with PLC system for SIWAP 01
B. RDS-5 area includes the following:
1. Connecting SIWAP-01 tie-in to RDS-5
2. Connecting SB-863 will be tied-in to RDS-5. SB-863 oil pipeline is routed to nearest RDS-5 M-0101 (600#). To connect SB-863 to RDS-5 one slot on RDS-5 shall be made available. The slot availability shall be made by Sharing of existing Sb-153 with Sb-323
4. Providing dedicated sample connections at the oil and water outlet in order to monitor the polymer breakthrough in the existing test separator in RDS-5
5. Existing 415V MCC Panel (14-15-MCC-4402) spare feeders shall be modified/upgraded/retrofitted to provide 415V power supply to the new loads required for ASAB SIWAP EOR Pilot facilities
6. Installation of new PLC systems shall be provided at strategic area and interfaced with the existing systems. The monitoring and control of new facilities shall be carried out from the existing control room at ASAB CDS / RDS-5 by existing workstations
C. Pipeline & Crossing includes the following:
1. Laying of 6-inch above-ground oil flow lines 900# from SWIAP-01 to RDS-5
2. Laying of 6-inch above-ground oil flow lines 600# from SB-863 to RDS-5 (SB-863 WH tie-in including Gas lift by others)
3. Laying of 6-inch above-ground water supply and disposal Pipeline
4. Laying of 6-inch above-ground water injection Pipeline
5. Laying of 6-inch above-ground SB-48 Water supply (a back-up water supply line from SB-048 to the pilot wellhead area)
6. Laying of 3-inch underground gas lift pipeline from existing Gas lift network to SWIAP-01
7. Laying of 3-inch underground gas lift pipeline from existing Gas lift network to SB-155
D. OHL includes the following:
1. Laying of OHL which includes but not limited to Tee-off line, single circuit type, from exiting OHL LINE #5 & 6 (TRUNK LINE circuit 6) to supply new polymer injector water supply well and associated equipment
2. Construction of associated facilities
Second Section
No Content
No Content
18 March 2024
Construction works are ongoing on the project.
07 November 2023
Construction works are ongoing on the project as per the schedule.
26 July 2023
Construction works are progressing and are expected to be completed by 2024.
27 April 2023
Construction works are progressing and are expected to be completed by 2024 end.
19 December 2022
The Engineering works have been commenced on the project.
13 September 2022
SNF has been appointed as the technology provider for the project. (Source: MEED)
22 July 2022
MMEC Mannesmann has been awarded the main contractor for the project (Source: MEED)
20 July 2022
The client is in negotiation with MMEC Mannesmann for the award however, the time-frame for the award is not known for now.
25 May 2022
The main contract is yet to be awarded.
20 April 2022
The main contract is yet to be awarded.
16 March 2022
Punj Lloyd has submitted the commercial bids for the project, FEED works are done by ADNOC in house division and the project is yet to be awarded.
24 February 2022
The commercial bid submission took place on February 23, 2022, and the following companies have submitted the main contract bids for the project: Al Asab Contracting Establishment, Al Nasr Contracting Company, Archirodon, CAT Group, Descon Engineering, Galfar Engineering & Construction, Kalpataru Power Transmission Limited, Petrojet, Robt Stone, Target Engineering, Tata Projects, and MMEC Mannesmann.
10 February 2022
The main contract bid submission deadline has been extended from February 9, 2022, to February 23, 2022.
03 February 2022
The commercial bids submission deadline is on February 9, 2022. (Source: MEED)
20 December 2021
The commercial bid submission date is yet to be disclosed by the client.
19 September 2021
The Commercial submission date is yet to be announced by the client.
14 July 2021
The technical bids evaluation are underway. (Source: MEED)
30 May 2021
The technical bid submission took place on May 18, 2021, and the following contractors are understood to have submitted technical bids: Al Asab Contracting Establishment, Al Nasr Contracting Company, Archirodon, CAT Group, Descon Engineering, Galfar Engineering & Construction, Kalpataru Power Transmission Limited, Petrojet, Robt Stone, Target Engineering and Tata Projects. (Source: MEED)
04 May 2021
The technical bid submission has extended to May 16, 2021.
20 April 2021
The technical bid submission has extended to May 2, 2021.
18 April 2021
The technical bid submission has extended to April 20, 2021.
05 April 2021
The technical bid submission has extended to April 18, 2021.
30 March 2021
ITB has been issued with a technical bid submission deadline of April 4, 2021. Essar, Robt Stone, CPPE, Al Asab, Galfar E&C, Arabian Industries, Kalpataru Power Transmission, Archirodon and Emarat Aloula are the pre-qualified shortlisted companies.
14 February 2021
ITB is yet to be issued and the time frame for the same is unknown at this juncture.
01 December 2020
ITB is yet to be issued and the time frame for same is unknown at this juncture.
06 October 2020
ITB is yet to be issued and the time frame for same is unknown at this juncture.
21 July 2020
EOI submission has taken place on July 20, 2020 and EPPM, Robt Stone LLC, Archirodon, CAT Group, TATA Projects amongst the few other's have submitted the EOI documents.
17 July 2020
Expression of Interest (EOI) has been issued on July 15, 2020 with the submission date due on July 20, 2020. ITB is expected to be issued on October 8, 2020 with the contract period of 18 months.