NHC - Dahiyat Al-Fursan New City Development
National Housing Company (NHC) is undertaking the construction of Dahiyat Alfursan in an area approximately 12 kilometres from King Khalid Airport in Riyadh, Saudi Arabia.
The US$20407 million project includes the following:
1. Construction of 50,000 apartments, Villas, & Semi-detached villas
2. Construction of hotels (3nos)
3. Construction of Dunes Museum
4. Construction of City Centre
5. Construction of Riyadh Megamall
6. Construction of the Grand Mosque
7. Construction of Medical Campus
8. Construction of Sports Complex
9. Construction of football stadium
10. Construction of Trams System
11. Construction of equestrian district
12. Construction of 20 km equestrian Bicycle Jogging Track and 13km bicycle jogging Track
13. Construction of open spaces and canal
14. Construction of Al Fursan gardens
15. Infrastructure works
16. Construction of commercial and retail space
17. Associated facilities
Second Section
No Content
No Content
30 October 2025
The client has signed the memorandum of understanding (MoU) with GS Engineering and Construction to implement the project.
16 October 2025
Construction works have progressed up to 61.13 per cent on the Dahiyat Al-Fursan: Phase 1: Tilal Homes.
29 July 2025
Dahia Al Fursan: Sewage Water Treatment Plant: Al Rawaf Trading & Contracting is working as main contractor and construction works are progressing on the project.
04 April 2025
The construction works are progressing, and the timeframe for its completion is unknown at the moment on the Dahiyat Al-Fursan: Residential Complex (550 Units).
07 January 2025
The construction works are ongoing on the Dahiyat Al-Fursan: Phase 1: Al Asila.
31 October 2024
The construction works are completed up to 72 percent on the Dahiyat Al-Fursan: Phase 1: Nesaj Town Fursan.
04 March 2024
The structural works are progressing on the Dahiyat Al-Fursan: Phase 1: Al Asila Package and Mesmack Construction & Development Company is the main contractor.
06 October 2023
NHC - Dahiyat Al-Fursan: Phase 1:Residential Complex (759 Units), (606 Units), (500 units), Saheel, Saraya Al Fursan (811 Units), Reem Residential Complex, Miskan Al Asayel, Tilal Homes, Aknan Al Fursan, Al Rasn Villas, Falwa, Al Athbah, Housing complex (by Abdul Rahman Saad, by Mohammad Al Habib, by Maskan Real Estate, by Innovest Real Estate and Phase 1 & 2: Residential Complex (Area No. 1/B) are under design stage.
03 July 2023
NHC - Dahiyat Al-Fursan: Phase 1:Residential Complex (759 Units), (606 Units), (500 units), Saheel, Saraya Al Fursan (811 Units), Reem Residential Complex, Miskan Al Asayel, Tilal Homes, Aknan Al Fursan, Al Rasn Villas, Falwa, Al Athbah, Housing complex (by Abdul Rahman Saad, by Mohammad Al Habib, by Maskan Real Estate, by Innovest Real Estate and Phase 1 & 2: Residential Complex (Area No. 1/B) are under design stage.
22 February 2023
The client has signed an agreement with Hill International to provide project management consultant services on the project.
18 January 2023
NHC - Saudi Housing: Dahiyat Al-Fursan 1 & 2: Residential Complex (Area No. 1/B), Dahiyat Al-Fursan 2: Residential Complex (550 Units) & (759 Units) are still under initial planning phase.
24 November 2022
The construction works are progressing on the Dahiyat Al-Fursan: Infrastructure Package. Al Omaier Trading & Contracting is working as the main contractor, earlier Al Ejtiyaz Contracting was appointed as the main contractor however they are no longer involved in the project.
22 November 2022
Construction works are progressing on Dahiyat Al-Fursan: Infrastructure Package and Al Ejtiyaz Contracting is working as the main contractor on the project.
05 September 2022
Market sources indicate that residential complex continues to be in the early stage of development.
23 May 2022
The Residential Complex is still in the early stage of development and the main contract tender is yet to be issued on Infrastructure Package.
22 August 2021
The project has been revived and the client is planning to appoint developer for 35000 houses in the next few years.
24 June 2021
The project is still on hold.
24 December 2020
The project continues to be on hold and the time frame for its revival is yet unknown.
01 August 2020
We have not been able to obtain further updates on this project. We have retained the same project stage and amended the key dates accordingly. We will update the profile as soon as we obtain any new information.
19 February 2020
The project still continues to be on hold.
12 April 2019
The project is now on hold due to issues around responsibilities and costs for the infrastructure element of the project.
29 May 2018
The negotiation and discussions are ongoing with Hanwha Engineering & Construction (E&C) and Daewoo E&C, and the local Saudi Pan Kingdom for Trading, Industry & Contracting (Sapac) to implement the project and the final decision will be taken by January 2019. The project will take 15 years to complete and will be divided in 5 phases, each phase is expected to take 3 years to complete.
05 March 2018
There is no progress on the project.
04 October 2017
The study and planning has been completed and the client is in the process of obtaining the necessary approvals from the relevant parties to implement the project in the coming months.
15 June 2017
Several International companies have singed an agreement with Ministry of Housing to participate in the construction works along with South Korea.
05 May 2017
In April, 2016 Riyadh signed a memorandum of understanding (MoU) with a consortium of South Korean contractors Hanwha Engineering & Construction (E&C) and Daewoo E&C, and the local Saudi Pan Kingdom for Trading, Industry & Contracting (Sapac) for the construction of Dahiyat Alfursan New City Development.
01 April 2014
The Ministry of Housing (MoH) is constructing Dahiyat Al-Fursan New City in Alfursan region, Riyadh, Saudi Arabia.